Question

Robin Construction Company began a long term contract in 2018. The contract price was $800,000. The...

Robin Construction Company began a long term contract in 2018. The contract price was $800,000. The estimated cost of the contract at the time it was begun was $500,000. The actual cost incurred in 2018 was $350,000. The contract was completed in 2019 and the cost incurred was $125,000. Under the percentage of completion method.

a. Robin should report $90,000 of income in 2018

b. Robin should report $210,000 income in 2018

c. Robin should report $300,000 income in 2018

d. Robin should report $325,000 income in 2018

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Option (b) is correct

First we will calculate the estimated income of the contract as per below:

Estimated income = Contract price - Estimated cost

Estimated income = $800000 - $500000

Estimated income = $300000

Next we will calculate the percentage of work done in 2018 as per below:

Percentage of work done in 2018 = Costs incurred in 2018 / Total estimated cost * 100

Percentage of work done in 2018 = $350000 / $500000 * 100 = 70%

Now, we will calculate the net income in 2018 as below:

Net income in 2018 = Estimated income * Percentage of work done in 2018

Net income in 2018 = $300000 * 70% = $210000

Add a comment
Know the answer?
Add Answer to:
Robin Construction Company began a long term contract in 2018. The contract price was $800,000. The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Considering the following data for a project begun in 2018 by Timber Construction, with a contract price of $3,000,000....

    Considering the following data for a project begun in 2018 by Timber Construction, with a contract price of $3,000,000. Dominion’s customer controls the building during the period of construction. 2018 2019 Current period costs $360,000 $440,000 Estimated additional costs to complete 1,440,000 800,000 Progress billings 350,000 300,000 Collection on billings-current year 200,000 200,000 Using the table below, calculate the revenue to be recognized by Timber Construction during 2018 and 2019. Assume that percentage of completion is measured by the ratio...

  • On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year Estimated costs to complete as of December 31 S 30 140 $40...

  • On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 60 $ 120 $ 70 Estimated costs to complete as of...

  • On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $390 million. The expected completion date is April 1, 2020. lust in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2018 2019 2020 $ 60 $130 $70...

  • 7 On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a...

    7 On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 0.5 points 2018 2019 2020 Costs incurred during the year Estimated costs to complete as of December 31 120...

  • 2018, Cupid Construction Co. (CCC) began work on a two-year fixed price contract project. CCC recognizes...

    2018, Cupid Construction Co. (CCC) began work on a two-year fixed price contract project. CCC recognizes revenue over time according to percentage of completion for this contract, and provides the following information (dollars in millions): Accounts receivable, 12/31/2018 (from construction progress billings) $ 37.5 Actual construction costs incurred in 2018 $ 135 Cash collected on project during 2018 $ 105 Construction in progress, 12/31/2018 $ 207 Estimated percentage of completion during 2018 60 % 1.How much revenue (in millions) is...

  • n 2016, Long Construction Corporation began construction work under a three-year contract. The contract price is...

    n 2016, Long Construction Corporation began construction work under a three-year contract. The contract price is $1,600,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2016, is as follows: Balance Sheet Accounts receivable (from construction progress billings) $ 30,000 Construction in progress $ 100,000 Less: Billings on construction contract (94,000 ) Cost and profit of uncompleted contracts in excess of billings 6,000 Income...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,060,000. During 2018, costs of $2,020,000 were incurred with estimated costs of $4,020,000 yet to be incurred. Billings of $2,520,000 were sent, and cash collected was $2,270,000. In 2019, costs incurred were $2,520,000 with remaining costs estimated to be $3,630,000. 2019 billings were $2,770,000 and $2,495,000 cash was collected. The project was completed in 2020 after additional costs of...

  • During year​ 1, Fox Co. started a construction job with a contract price of​ $1,500,000. The...

    During year​ 1, Fox Co. started a construction job with a contract price of​ $1,500,000. The job was completed in year 2 and the company uses the percentage of completion method. The following information is available for year 1 and year​ 2: Year 1 Year 2 Cost incurred to date $350,000 $1,100,000 Estimated cost to complete 650,000 0 Billings to date 300,000 1,100,000 Collections to date 100,000 1,000,000 What amount of gross profit should Fox recognize for this job for...

  • Hollywood Construction Company recognizes revenue over time according to percentage of completion for its long term...

    Hollywood Construction Company recognizes revenue over time according to percentage of completion for its long term construction contracts. During 2018 Hollywood began work on a $3,000,000 foed-fee construction contract which was completed in 2021. The accounting records disclosed the following data at year-end: Estimated costs to complete at end of year $1,800,000 1,100,000 400,000 Cumulative contract costs incurred S 200,000 1,100,000 2,000,000 2018 2019 2020 For the 2020 year, Hollywood should have recognized gross profit on this contract of

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT