way co d es , m and o r e Problem 17-3 Shaker Co designs and build factory-made premium wooden stairways for homes. The manuf
(Round answer to 2 decimal places, .g. 12.25.) Compute the predetermined overhead rate using traditional costing with machine
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1.

Predetermined overhead rate = Estimated overhead costs / Estimated machine hours

Predetermined overhead rate = $1,184,050 / 100,000 = $11.84 per machine hour

2.

Cost per stairway:

Total manufacturing cost = $104,600+112,400+181,152 (15,300*$11.84) = $398,152

Cost per stairway = $398,152 / 250 = $1,592.61

3.

Activity Overhead rate
Purchasing $126 (75,600/600) per order
Handling materials 10.26 (82,080/8,000) per move
Production 2.14 (214,000/100,000) per D/L hour
Setting up machines 81 (101,250/1,250) per setup
Inspecting 20 (120,000/6,000) per inspection
Inventory control 0.84 (141,120/168,000) per component
Utilities 5 (450,000/90,000) per sq.ft.

4.

Purchasing $7,560 (60*$126)
Handling materials 8,208 (800*$10.26)
Production 10,914 (5,100*$2.14)
Setting up machines 8,100 (100*$81)
Inspecting 9,000 (450*$20)
Inventory control 13,440 (16,000*$0.84)
Utilities 40,000 (8,000*$5)
Total overhead assigned $97,222

5.

Total cost per stairway:

Total manufacturing cost = $104,600+112,400+97,222 = $314,222

Cost per stairway = $314,222 / 250 = $1,256.89

Add a comment
Know the answer?
Add Answer to:
way co d es , m and o r e Problem 17-3 Shaker Co designs and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components...

    Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows. Overhead Cost Pools Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities Total budgeted overhead costs Amount $75,000 82,000 220,000 100,000 120,000 126,000...

  • Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components...

    Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows. Overhead Cost Pools Amount Purchasing $75,000 Handling materials 82,000 Production (cutting, milling, finishing) 220,000 Setting up machines 105,000 Inspecting 114,000 Inventory control (raw materials and finished goods) 126,000 Utilities 360,000 Total budgeted overhead...

  • CALCULATOR PRINTER VERSION BACK NEXT Problem 17-3A (Part Level Submission) Shaker Stairs Co. designs and builds...

    CALCULATOR PRINTER VERSION BACK NEXT Problem 17-3A (Part Level Submission) Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, handrais) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2017 are as follows. Overhead Cost Pools Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities Total budgeted...

  • Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components...

    Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows. Amount Overhead Cost Pools Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities $75,000 82,000 210,000 100,000 96,000 126,000 270,000 Total budgeted overhead...

  • Problem 4-3A a-b, c1-c3 (Video) (Part Level Submission) Shaker Stairs Co. designs and builds factory-made premium...

    Problem 4-3A a-b, c1-c3 (Video) (Part Level Submission) Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows. Overhead Cost Pools Amount Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities Total budgeted...

  • P17-3A--- Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway...

    P17-3A--- Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2017 are as follows. Overhead Cost Pools Amount Purchasing $ 75,000 Handling materials 82,000 Production (cutting, milling, finishing) 210,000 Setting up machines 105,000 Inspecting 90,000 Inventory control (raw materials and finished goods) 126,000 Utilities 180,000 Total...

  • Shaker Stairs Co.designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles,...

    Shaker Stairs Co.designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows. Overhead Cost Pools Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities Total budgeted overhead costs Amount $75,000 82,000 220,000 105,000 108,000 126,000 270,000...

  • Problem 17-03A a-b, c-c (Part Level Submission) Shaker Stars Co, designs and builds factory made premium...

    Problem 17-03A a-b, c-c (Part Level Submission) Shaker Stars Co, designs and builds factory made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, handrais permit installation of starways of varying lengths and widths. All are of white oak wood Budgeted manufacturing overhead costs for the year 2020 are as follows. Overhead Cost Pools Purchaung Handing materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utaties Total budgeted overhead costs...

  • Shaker Stairs Co.designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles,...

    Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows.Overhead Cost PoolsAmountPurchasing$75,000Handling materials82,000Production (cutting, milling, finishing)210,000Setting up machines100,000Inspecting96,000Inventory control (raw materials and finished goods)126,000Utilities450,000Total budgeted overhead costs$1,139,000For the last 4 years, Shaker Stairs Co. has been charging overhead to products on the basis...

  • using P4-3A Shaker Stairs Co. designs and builds factory-made premium wooden stai ABC omes. The manufactured...

    using P4-3A Shaker Stairs Co. designs and builds factory-made premium wooden stai ABC omes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2017 are as follows. Overhead Cost Pools Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities Total budgeted overhead costs Amount $ 75,000 82,000 210,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT