Copy Center pays an average wage of $12 per hour to employees for printing and copying...

Copy Center pays an average wage of $12 per hour to employees for printing and copying jobs, and allocates $18 of overhead for each employee hour worked. Materials are assigned to each job according to actual cost. If Job M-47 used $365 of materials and took 20 hours of labor to complete, what is the total cost that should be assigned to the job?

Multiple Choice

  • $605.

  • $725.

  • $845.

  • $600.

  • $965.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

overhead cost = 20 hours * 18 per hour

= 360

labor cost = 20 hours * 12 per hour

= 240

direct materials = 365

total cost assigned = 365+240+360

= 965

Add a comment
Know the answer?
Add Answer to:
Copy Center pays an average wage of $12 per hour to employees for printing and copying...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Copy Center pays an average wage of $13 per hour to employees for printing and copying...

    Copy Center pays an average wage of $13 per hour to employees for printing and copying jobs, and allocates $19 of overhead for each employee hour worked. Materials are assigned to each job according to actual cost. If Job M-47 used $360 of materials and took 20 hours of labor to complete, what is the total cost that should be assigned to the job? Multiple Choice 0 $640. 0 $620 0 $740. 0 $880 0 $1,000 Preu 10 of 25

  • A company pays its employees an average wage of $15.90 an hour with a standard deviation...

    A company pays its employees an average wage of $15.90 an hour with a standard deviation of $1.50. If the wages are approximately normally distributed and paid to the nearest cent, (a) what percentage of the workers receive wages between $13.75 and $16.22 an hour inclusive? (b) the highest 5% of the employee hourly wages is greater than what amount?

  • Plantwide Overhead Rate, Activity-Based Costing, Job Costs Foto-Fast Copy Shop provides a variety of photocopying and...

    Plantwide Overhead Rate, Activity-Based Costing, Job Costs Foto-Fast Copy Shop provides a variety of photocopying and printing services. On June 5, the owner invested in some computer-aided photography equipment that enables customers to reproduce a picture or illustration, input it digitally into the computer, enter text into the computer, and then print out a four-color professional quality brochure. Prior to the purchase of this equipment, Foto-Fast Copy Shop's overhead averaged $46,200 per year. After the installation of the new equipment,...

  • Weaver Company's predetermined overhead rate is $17.00 per direct labour-hour, and its direct labour wage rate...

    Weaver Company's predetermined overhead rate is $17.00 per direct labour-hour, and its direct labour wage rate is $11.00 per hour. The following information pertains to Job A-200: Direct materials Direct labour $120 $110 Required: 1. What is the total manufacturing cost assigned to Job A-200? Total manufacturing cost 2. If Job A-200 consists of 40 units, what is the average cost assigned to each unit included in the job? Average cost per unit

  • Weaver Company’s predetermined overhead rate is $20.00 per direct labour-hour, and its direct labour wage rate...

    Weaver Company’s predetermined overhead rate is $20.00 per direct labour-hour, and its direct labour wage rate is $15.00 per hour. The following information pertains to Job A-200:        Direct materials $240   Direct labour $180 Required: 1. What is the total manufacturing cost assigned to Job A-200?       2. If Job A-200 consists of 55 units, what is the average cost assigned to each unit included in the job?         

  • Mickley Company’s predetermined overhead rate is $14.00 per direct labor-hour and its direct labor wage rate...

    Mickley Company’s predetermined overhead rate is $14.00 per direct labor-hour and its direct labor wage rate is $12.00 per hour. The following information pertains to Job A-500:         Direct materials $230   Direct labor $108    Required: 1. What is the total manufacturing cost assigned to Job A-500?             2. If Job A-500 consists of 40 units, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places.)      

  • Mickley Company’s predetermined overhead rate is $22.00 per direct labor-hour and its direct labor wage rate...

    Mickley Company’s predetermined overhead rate is $22.00 per direct labor-hour and its direct labor wage rate is $13.00 per hour. The following information pertains to Job A-500:         Direct materials $290   Direct labor $195    Required: 1. What is the total manufacturing cost assigned to Job A-500?           2. If Job A-500 consists of 60 units, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places.)

  • Weaver Company's predetermined overhead rate is $21.00 per direct labor-hour and its direct labor wage rate...

    Weaver Company's predetermined overhead rate is $21.00 per direct labor-hour and its direct labor wage rate is $13.00 per hour. The following information pertains to Job A-200: Direct materials Direct labor $230 $195 Required: 1. What is the total manufacturing cost assigned to Job A-200? Total manufacturing cost 2. If Job A-200 consists of 40 units, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places.) Average cost per unit

  • Weaver Company's predetermined overhead rate is $23.00 per direct labor-hour and its direct labor wage rate...

    Weaver Company's predetermined overhead rate is $23.00 per direct labor-hour and its direct labor wage rate is $12.00 per hour. The following information pertains to Job A-200: Direct materials Direct labor $240 $60 Required: 1. What is the total manufacturing cost assigned to Job A-200? Total manufacturing cost 2. If Job A-200 consists of 80 units, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places.) Average cost per unit

  • Weaver Company's predetermined overhead rate is $21.00 per direct labor-hour and its direct labor wage rate...

    Weaver Company's predetermined overhead rate is $21.00 per direct labor-hour and its direct labor wage rate is $13.00 per hour. The following information pertains to Job A- 200: Direct materials Direct labor $250 $130 Required: 1. What is the total manufacturing cost assigned to Job A-200? Total manufacturing cost $ 385 2. If Job A-200 consists of 70 units, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places.) Average...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT