Solution:
1a) Calculate the standard cost per unit for direct material
Direct material = cost per lbs * Total lbs per unit
=$9*7
=$63
1b) Calculate the standard cost per unit for direct lobor
Direct labor = Cost per hour * Total hours per unit
=$16*2
=$32
1c) Calculate the standard cost per unit for overhead
Overhead = cost per hour * Total hours per unit
=$11 * 2
=$22
2)
Calculate the total standard cost
Particular | Amount $ |
Direct materials cost(8,400*9*7) | 529,200 |
Add: Direct lanor costs(8,400*16*2) | 268,800 |
Add: Overhead costs(8,400 *11*2) | 184,800 |
Total standard cost | 982,800 |
Calculate the total actual cost
Particular | Amount $ |
Direct materials cost(59,400*9.10) | 540,540 |
Add: Direct lanor costs(16,400 * 16.5) | 270,600 |
Add: Overhead costs | 190,200 |
Total Actual cost | 1,001,340 |
Total cost variance = Total actual cost - Total standard cost
=1,001,340 -982,800
=$18,540 unfavorable
HYEUVROUE [The following information applies to the questions displayed below.) A manufactured product has the following...
Required information [The following information applies to the questions displayed below] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (6 lbs. @ $7 per lb.) (2 hrs. $16 per hr.) (2 hrs. @ $13 per hr.) Actual 44.3e9 lbs. @ $7.10 per lb. 14,300 hrs. $16.50 per hr. $196,700 7,300 (1) Compute the standard cost per unit Direct materials Direct labor Overhead Total (2) Compute the total cost variance for June,...
[The following information applies to the questions displayed below.] A manufactured product has the following information for June. Standard (6 lbs. @ $8 per lb.) (2 hrs. @ $16 per hr.) |(2 hrs. @ $12 per hr.) Actual 48,500 lbs. @ $8.10 per lb 15,700 hrs. @ $16.50 per hr. $198,000 8,000 Direct materials Direct labor Overhead Units manufactured (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total $ 0 (2) Compute the total cost variance...
Required information (The following information applies to the questions displayed below.) A manufactured product has the following information for June. Standard (7 lbs. e $7 per lb.) (2 hrs. e $16 per hr.) (2 hrs. e S$12 per hr.) Actual Direct materials Direct labor Overhead 51, 600 lbs. e S7.10 per 1b. 14, 200 hrs.e S16.50 per hr. S180, 400 7, 300 Units manufactured (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total (2) Compute the...
Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (5 lbs. @ $8 per lb.) (2 hrs. @ $17 per hr.) (2 hrs. @ $12 per hr.) Actual 43,900 lbs. @ $8.10 per lb. 17,100 hrs. @ $17.40 per hr. $214,700 8,700 (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total (2) Compute the total cost variance...
Use the following information for the Exercises below. (The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured (5 lbs. (2 hrs. (2 hrs. Standard 58 per lb.) $17 per hr.) $13 per hr.) Actual 42,400 lbs. $8.20 per lb. 16,400 hrs. $17.50 per hr. $224,700 8,400 Exercise 23-8 Standard unit cost; total cost variance LO C2 (1) Compute the standard cost per unit. Direct...
Use the following information for the Exercises below. (The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured (5 lbs. (2 hrs. (2 hrs. Standard 58 per lb.) $17 per hr.) $13 per hr.) Actual 42,400 lbs. $8.20 per lb. 16,400 hrs. $17.50 per hr. $224,700 8,400 Exercise 23-8 Standard unit cost; total cost variance LO C2 (1) Compute the standard cost per unit. Direct...
Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard 5 lbs. @ $7 per lb. 3 hrs. @ $16 per hr. 3 hrs. @ $11 per hr. Actual 43, 600 lbs. @ $7.10 per lb. 25,600 hrs. @ $16.60 per hr. $290,400 8,600 (1) Compute the standard cost per unit. (2) Compute the total cost variance for June. Complete this question...
Required information [The following information applies to the questions displayed below. A manufactured product has the following information for June. Direct materials 1 Actual lbs. @ $7.20 per 9 54,400 lb. Standard (7 lbs. @ $7 per lb.) (3 hrs. @ $15 per hr.) (3 hrs. @ $12 per hr.) Direct labor Overhead Units manufactured 32 saa hrs. @ $15.50 per 22,8001 hr. $283,300 7,700 (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total (2) Compute...
Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (6 lbs. @ $8 per lb.) (3 hrs. @ $16 per hr.) (3 hrs. @ $12 per hr.) Actual 49,000 lbs. @ $8.10 per lb. 23,900 hrs. @ $16.50 per hr. $297,500 8,100 (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total (2) Compute the total cost variance...
Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (6 lbs. $8 per lb.) (2 hrs. @ $16 per hr.) (2 hrs. @ $12 per hr.) Actual 49,700 lbs. @ $8.10 per lb. 16,000 hrs. @ $16.60 per hr $202,300 8,200 (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total (2) Compute the total cost variance for...