If it is helpful, please rate the answer and if any doubt arises let me know
Correct option is: B. Division A $4.71 , Division B $15.91 | |||
Workings: | |||
Division A | Division B | ||
(i) | Manufacturing overhead cost | $ 1,60,000 | $ 3,50,000 |
(ii) | Machine hours / Direct labor hours | 34000 | 22000 |
(i) / (ii) | Predetermined overhead rate | $ 4.71 | $ 15.91 |
Aradial tire manufacturer produces products in two departments Divisions A and B. The company uses separate...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Estimated total machine-hours (MHS) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH Machining Finishing 4,000 6,000 $ 5,200 $ 20,400 $ 1.50 $ 6.00 Total 10,000 $ 25,600 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Finishing Total Estimated total machine-hours (MHs) 7,000 3,000 10,000 Estimated total fixed manufacturing overhead cost $ 8,400 $ 11,700 $ 20,100 Estimated variable manufacturing overhead cost per MH $ 3.00 $ 5.00 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Estimated total machine-hours (MHS) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH Machining Finishing 5,000 5,000 $ 6,500 $ 29,500 $ 2.00 $ 4.00 Total 10,000 $ 36,000 During the most recent month, the company started and completed two jobs-- Job B and Job K. There were no beginning inventories....
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Finishing Total Estimated total machine-hours (MHs) 9,000 8,000 17,000 Estimated total fixed manufacturing overhead cost $ 18,000 $ 7,800 $ 25,800 Estimated variable manufacturing overhead cost per MH $ 2.70 $ 5.00 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Finishing Total Estimated total machine-hours (MHs) 7,000 3,000 10,000 Estimated total fixed manufacturing overhead cost $ 8,400 $ 11,700 $ 20,100 Estimated variable manufacturing overhead cost per MH $ 3.00 $ 5.00 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Finishing Total Estimated total machine-hours (MHs) 7,000 3,000 10,000 Estimated total fixed manufacturing overhead cost $ 8,400 $ 11,700 $ 20,100 Estimated variable manufacturing overhead cost per MH $ 3.00 $ 5.00 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Estimated total machine-hours (MH) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH Machining Finishing 6,000 5,000 $ 5,100 $ 39,200 $ 1.40 $ 2.00 Total 11,000 $ 44,300 During the most recent month, the company started and completed two jobs-Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Estimated total machine-hours (MS) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH Machining Finishing 6,000 5,000 $ 5,100 $ 39,200 $ 1.40 $ 2.00 Total 11,000 $ 44,300 During the most recent month, the company started and completed two jobs Job B and Job K. There were no beginning inventories....
The Oswell Company manufactures products in two departments: Mixing and Packaging. The company was allocating manufacturing overhead using a single plantwide rate of $2.35 with direct labor hours as the allocation base. The company has refined its allocation system by separating manufacturing overhead costs into two post pools one for each department. The estimated costs for the Mixing Department, $598,500, will be allocated based on direct labor hours, and the estimated direct labor hours for the year are 190,000. The...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Finishing Total Estimated total machine-hours (MHs) 9,000 8,000 17,000 Estimated total fixed manufacturing overhead cost $ 18,000 $ 7,800 $ 25,800 Estimated variable manufacturing overhead cost per MH $ 2.70 $ 5.00 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...