You are a project manager with Striker Projects Pvt. Ltd. As the project manager, you need to evaluate two projects “Salient” and “Stylish”, and make a recommendation to management for the selection of a suitable project. Both the projects “Salient” and “Stylish” entail an initial investment of ₹5,00,000. Projected cash inflows for the Project “Salient” are ₹1,50,000 in year 1; ₹1,60,000 in year 2; ₹1,70,000 in year 3, and ₹1,65,000 in year 4. Projected cash inflows for the Project “Stylish” are ₹1,40,000 in year 1; ₹1,40,000 in year 2; ₹1,40,000 in year 3, ₹1,25,000 in year 4; and ₹1,22,000 in year 5. The required rate of return is 10%. The present value of ₹1 at 10% is ₹0.909 for year 1, ₹0.826 for year 2, ₹0.751 for year 3, ₹0.683 for year 4, and ₹0.621 for year 5. Calculate Net Present Value (NPV), Internal Rate of Return (IRR) and Profitability Index (PI) for both the projects “Salient” and “Stylish”. Compare and contrast NPV, IRR and PI values of projects “Salient” and “Stylish”, and recommend a suitable project for investment to the management. Require Answer in 1000 Words
Project Salient | ||||
Year | cash flow | present value factor at 10% | present value of cash flow = cash flow*present value factor | |
0 | -500000 | 1 | -500000 | |
1 | 150000 | 0.909 | 136350 | |
2 | 160000 | 0.826 | 132160 | |
3 | 170000 | 0.751 | 127670 | |
4 | 165000 | 0.683 | 112695 | |
Net present value = sum of present value of cash flow | 8875 | |||
PI =1+(NPV/Initial investment) | 1+(8875/500000) | 1.018 | ||
IRR =Using IRR function in MS excel | IRR(J569:J573) | 10.81% | ||
Project Stylish | ||||
Year | cash flow | present value factor at 10% | present value of cash flow = cash flow*present value factor | |
0 | -500000 | 1 | -500000 | |
1 | 140000 | 0.909 | 127260 | |
2 | 140000 | 0.826 | 115640 | |
3 | 140000 | 0.751 | 93875 | |
4 | 125000 | 0.683 | 75762 | |
5 | 122000 | 0.621 | 75762 | |
Net present value = sum of present value of cash flow | -11701 | |||
PI =1+(NPV/Initial investment) | 1+(-11701/500000) | 0.976598 | ||
IRR =Using IRR function in MS excel | IRR(J580:J585) | 10.74% | ||
Project Salient | Project Stylish | Accept or reject | ||
NPV | 8875 | -11701 | Accept project Sailent | As per decision criteria of NPV a higher value NPV project is preferred so project sailent would be selected |
PI | 1.018 | 0.976598 | Accept project Sailent | As per decision criteria of PI a project with a more than PI is preferred so project sailent would be selected |
IRR | 10.81% | 10.74% | As per IRR criteria even both the project can be selected as IRR of both the project is more than the required rate of return of 10% but as manager has to select one project so project sailent with more IRR would be preferred. | |
From the analysis of the above results it is recommended that NPV and PI techniques prefer the slection of Project Sailent but according to IRR both project would be selected, but as it is mutually exclusive projects so Project sailent would be selected as it results in more IRR than the project stylish | ||||
You are a project manager with Striker Projects Pvt. Ltd. As the project manager, you need...
(NPV, PI, and IRR calculations) You are considering two independent projects, project A and project B. The initial cash outlay associated with project A is $50,000 and the initial cash outlay associated with project B is $70,000. The required rate of return on both projects is 11 percent. The expected annual free cash inflows from each project are on the table below. Calculate the NPV, PI, and IRR for each project and indicate if the project should be accepted. Project...
(NPV, PI, and IRR calculations) You are considering two independent projects, project A and project B. The initial cash outlay associated with project A is $50,000 and the initial cash outlay associated with project B is $70,000. The required rate of return on both projects is 11 percent. The expected annual free cash inflows from each project are on the table below. Calculate the NPV, PI, and IRR for each project and indicate if the project should be accepted. Project...
(NPV, PI, and IRR calculations) You are considering two independent projects, project A and project B. The initial cash outlay associated with project A is $55,000, and the initial cash outlay associated with project B is $75,000. The required rate of return on both projects is 10 percent. The expected annual free cash inflows from each project are in the popup window: PROJECT A PROJECT B Initial Outlay -55,000 -75,000 Inflow year 1 16,000 17,000 Inflow year 2 16,000 ...
Suppose you are the financial manager of a firm considering the following five projects. Project A Project B Project C Project D Project E Initial Investment -$10,000 -$15,000 -$14,000 -$6,000 -$1,500 Year 1 $5,000 $5,000 $6,000 $4,000 $1,000 Year 2 $4,000 $5,000 $4,000 $2,000 $250 Year 3 $2,000 $5,000 $3,500 $2,000 $100 Year 4 $1,000 $5,000 $2,500 $2,000 $100 Year 5 $5,000 $2,000 $100 Year 6 $2,000 $100 Calculate the Payback Period for each project. Calculate the NPV for each...
Farrah Corporation is considering two projects (see below). For your analysis, assume these projects are mutually exclusive with a required rate of return of 12%. Project 1 Initial investment $185,000 Cash inflow Year 1 $230,000 Project 2 Initial investment $1,100,000 Cash inflow Year 1 $1,450,000 Compute the following for each project: • NPV (net present value) • PI (profitability index) • IRR (internal rate of return) Which project should be selected? Why?
Jill Harrington, a manager at Jennings Company, is considering several potential capital investment projects. Data on these projects follow: Project X Project Y Project Z Initial investment $40,000 $20,000 $50,000 Annual cash 25,000 10,000 25,400 inflows PV of cash 45.000 33,000 70,000 inflows Required: 1. Compute the payback period for each project and rank order them based on this criterion. (Round your answers to 2 decimal places.) Payback par Period Rani Project Project Project 2. Compute the NPV of each...
Jill Harrington, a manager at Jennings Company, is considering several potential capital investment projects. Data on these projects follow Initial investment Annual cash inflows PV of cash inflows Project X $40,000 25,000 45,000 Project Y $20,000 10,000 33,000 Project Z $50,000 25,400 70,000 Required: 1. Compute the payback period for each project and rank order them based on this criterion. (Round your answers to 2 decimal places.) Payback Period Rank Project X Project Y Project Z 2. Compute the NPV...
(NPV, PV, and IRR calculations) You are considering two independent projects, project A and project B. The initial cash outlay associated with project Als $55,000 and the initial cash outlay associated with project is $75,000. The required role of return on both projects is 12 percent. The expected arvual free cash inflows from each project are in the popup window. Calculate the NPV, Pt, and IRR for each project and indicate if the project should be accepted. a. What is...
4. Farrah Corporation is considering two projects (see below). For your analysis, assume these projects are mutually exclusive with a required rate of return of 12%. Initial investment Cash inflow Year 1 Project 1 $185,000 $230,000 Project 2 $1,100,000 $1,450,000 Compute the following for each project: NPV (net present value) PI (profitability index) IRR (internal rate of return) Which project should be selected? Why?
Consider the following two mutually exclusive projects: Year CF of Project A CF of Project B 0 -$350,000 -$50,000 1 45,000 24,000 2 65,000 22,000 3 65,000 19,500 4 440,000 14,600 Whichever project you choose, if any, you require a 15 percent return on your investment. a)If you apply the payback (PB) criterion, which investment will you choose? Why? b)If you apply the NPV criterion, which investment will you choose? Why? c)If you apply the IRR criterion, which investment will...