Question

For the PERT Chart shown below, indicate the following:

- For the PERT Chart shown below, indicate the following: Start 6 End 0-0 D What activities are on the critical path? Which a

please provide the answers to the text in red

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1st Ans: The critical path is the longest distance between the start and the finish of your project, including all the tasks, their duration, which gives you a clear picture of the project's actual schedule.

The activities F, G and C are on a critical path.

2nd Ans: Slack time can be defined as the amount of time an task can be delayed without causing another task to be delayed or impacting the completion date of your project.

The activity between F and G has slack time.

Add a comment
Know the answer?
Add Answer to:
For the PERT Chart shown below, indicate the following: please provide the answers to the text...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Answer the following questions based on the PERT chart below with task times given in hours....

    Answer the following questions based on the PERT chart below with task times given in hours. [All answer should be given as a single number only without units]. Answer the following questions based on the PERT chart below with task times given in hours [All answer should be given as a single number only without units] A(5) E(5) Start B1) D(8) H(4) End C(6) G(3) 1(7) a. The number of priority lists that can be created for this project is...

  • Given is a PERT project network diagram as shown below. Start D Activity Start ABCDEFGH End...

    Given is a PERT project network diagram as shown below. Start D Activity Start ABCDEFGH End Time 0 1.35 3.65 4.327 .36 8.25 1.394 .68 3.250 a) The Project Completion time = (in 2 decimal places) b) The Earliest Start time, Es, of Activity G- (in 2 decimal places) c) The Latest Finish time, LF, of Acitivity C (in 2 decimal places) d) The critical activities are (ex. type in critical activities as ABCD no comma, no space)

  • Provide step by step please thank you, no exce Assume you have a project with ten...

    Provide step by step please thank you, no exce Assume you have a project with ten activities labeled A-J, as shown. Derive the earliest completion time (or early finish-EF), latest completion time (or late finish-LF), and slack for each of the following tasks (begin at time 0) the critical path on your network diagram. . Which tasks are on the critical path? Highligh Preceding Expected Critical Path? Activity Event Duration EF LF Slack A, D C,E D, E F, G...

  • Given is a PERT project network diagram as shown below: Start End ctivity |StarA KEnd 15...

    Given is a PERT project network diagram as shown below: Start End ctivity |StarA KEnd 15 me 10 13 12 20 a) The Project Completion time = b) The Earliest Start time, ES, of Activity F- c) The Earliest Start time, ES, of Activity K = d) The Latest Start time, LS, of Activity. E = e) The non-critical activities are comma, no space) (ex. type in critical activities as ABCD, no

  • 1. State whether each of the following statement is true or false. a) The sequence of...

    1. State whether each of the following statement is true or false. a) The sequence of activities in a project is depicted by the precedence (0.5 mark) (0.5 mark) relationships. The critical path is the shortest path through the project network. Slack is the amount of time an activity can be delayed without delaying the project. In PERT, three time estimates (optimistic, most likely and pessimistic) provide an estimate of the mean and variance for each activity based on the...

  • Do the following a) draw the pert nert work resulting from the above information b) draw the Gantt chart from the same information above c) state the paths in the PERT network and determine the cr...

    Do the following a) draw the pert nert work resulting from the above information b) draw the Gantt chart from the same information above c) state the paths in the PERT network and determine the critical path d) what is the minimum number of weeks the project will take to be complete d) what is the maximum cost that the project will take to be completed e) give two advantages and disadvantage of using the Gantt chart as a planning...

  • 5-9 answer only, 10 please tell me how to get the answer. mal limits (keep three...

    5-9 answer only, 10 please tell me how to get the answer. mal limits (keep three deci 5 What are the upper and lower control chart limits using 3-sigma I places if necessary and select the closest one) (d) (6.583, 33.416] () [17,23] (d) I6.583, 33.41 (o) [o.o96, 0.105) (e) (0.037,0.163] (b) 10.099, 0.101) 6. Is the process in control? (a) Yes (b) No 7. If the parking office didn't count how many vehicle every day, is the process s...

  • (3) Determine the critical path and critical time of the network shown below. Use the critical...

    (3) Determine the critical path and critical time of the network shown below. Use the critical path method (the table of ES, EF, etc.). (3) Determine the critical path and critical time of the network shown below. Use the critical path method (the table of ES, EF, etc.). po Problem . Example a 100 For all starting activities, ES is taken as 0. Activities 1-2, 1-3 gets ES of O. Find EF-ES +time. Activity Time ES E F LS L...

  • The following is a table of activities associated with a project at Rafay​ Ishfaq's software firm...

    The following is a table of activities associated with a project at Rafay​ Ishfaq's software firm in​ Chicago, their durations and what activities each must​ precede: Activity Duration​ (weeks) Precedes A​ (start) 2 ​B, C B 2 E C 6 F E 3 F F​ (end) 4 — This exercise contains only parts​ b, c, and d. ​b) Define the critical​ path, listing all critical activities in chronological order. Critical path activities are the activities that lie on the longest...

  • 2. Assume you have a project with ten activities labeled A-J, as shown. Derive the earliest...

    2. Assume you have a project with ten activities labeled A-J, as shown. Derive the earliest completion time (EF), latest completion time (LF) and slack for each of the following tasks (begin at time 0). Which tasks are on the critical path? Highlight the critical path on your network diagram [5] Activity Preceding Expected EF LF Slack Critical Event Duration Path? A 4 A 5 C A 6 A 7 E A, D 6 C, E 4 G D, E...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT