Question

Scenario

Cartech Manufacturing is engaged in the production of replacement parts for automobiles. One plant specializes in the production of two parts: Part 271 and Part 342. Part 271 produces the highest volume of activity, and for many years it was the only part produced by the plant. Five years ago, Part 342 was added. Part 342 was more difficult to manufacture and required special tooling and setups. Profits increased for the first three years after the addition of the new product. In the past two years, however, the plant has faced intense competition, and its sales of Part 271 have dropped. In fact, the plant showed a small loss in the most recent reporting period. Much of the competition was from foreign sources, and the plant manager was convinced that the foreign producers were guilty of selling the part below the cost of producing it. The following conversation between Tricia Goodson, plant manager, and Jackson Fielding divisional marketing manager, reflects the concerns of the division about the future of the plant and its products.

Jackson: You know, Tricia, the divisional manager is really concerned about the plant’s trend. He indicated that in this budgetary environment, we can’t afford to carry plants that don’t show a profit. We shut one down just last month because it couldn’t handle the competition.

Tricia: Joe, you and I both know that Part 271 has a reputation for quality and value. It has been a mainstay for years. I don’t understand what’s happening.

Jackson: I just received a call from one of our major customers concerning Part 271. He said that a sales representative from another firm offered the part at $20 per unit-- $11 less than what we charge. It’s hard to compete with a price like that. Perhaps the plant is simply obsolete.

Tricia: No. I don’t buy that. From my sources, I know we have good technology. We are efficient. And it’s costing a little more than $21 to produce that part. I don’t see how these companies can afford to sell it so cheaply. I’m not convinced that we should meet the price. Perhaps a better strategy is to emphasize producing and selling more of Part 342. Our margin is high on this product, and we have virtually no competition for it.

Jackson: You may be right. I think we can increase the price significantly and not lose business. I called a few customers to see how they would react to a 25 percent increase in price, and they all said that they would still purchase the same quantity as before.

Tricia: It sounds promising. However, before we make a major commitment to Part 342, I think we had better explore other possible explanations. I want to know how our production costs compare with those of our competitors. Perhaps we could be more efficient and find a way to earn our normal return on Part 271. The market is so much bigger for this part. I’m not sure we can survive with only Part 342. Besides, my production people hate that part. It’s very difficult to produce.

After her meeting with Jackson, Tricia requested an investigation of the production costs and comparative efficiency. She received approval to hire Wake Consulting Group to make an independent investigation.

You, as the staff accountant for Wake Consulting Group, have uncovered the following costs and activities associated with the two products.

Part 271

Part 342

Production

500,000

100,000

Selling Price

$31.86

$24.00

Prime costs per unit

$9.53

$8.26

Number of production runs

100

200

Receiving orders

400

1,000

Machine hours

125,000

60,000

Direct labor hours

250,000

22,500

Engineering hours

5,000

5,000

Material moves

500

400

Overhead is allocated using a plant-wide rage based on direct labor hours.

Preliminary analysis of costs by Wake Consulting Group revealed that similar costs can be categorized into the following cost pools. Setup costs are costs that occur each time a new production run is made. They involve retooling and reconfiguring the machines and technology. Material handling costs include the equipment and personnel required to transport materials from supplier trucks to the machines. Typically, materials are taken to a storage area before being transported to machines. Each production run will need new materials and materials may also be transported during production runs. Machine costs primarily include depreciation and machine maintenance. Although the machines are depreciated using accelerated depreciation schedules, typically the machine wear out from use and are replaced before they become obsolete. Receiving costs include the costs of clerical and technical help associated with the processing of each order received from a customer. Engineering costs include the technical support staff that implement design changes in the part, manage processes to maintain quality, and provide technical information on the product. The engineering staff maintain a record of the amount of time spent on each product. General plant costs include all the other administrative costs not included in the other cost pools.

Overhead Cost Pools

Setup costs

$240,000

Material handling costs

$900,000

Machine costs

$1,750,000

Receiving costs

$2,100,000

Engineering costs

$1,500,000

General plant costs

$500,000

Total

            TOTAL :   $6,990,000

Part 1: Compute overhead and gross margin using traditional costing. Per unit Part 342 Part 271 Selling Price $ $ Product Cos

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer

Requirement a

Per unit Part 271 Part 342
Selling Price $          31.86 $            24.00
Product Cost
Prime cost $            9.53 $              8.26
Overheads (Note) $          12.83 $              5.77
Total Product Cost $          22.36 $            14.03
Total Profits $            9.50 $              9.97

Requirement b

Cost Pool Cost Driver Overhead Rate Calculation
Setup Costs Number of production runs $          800.00 $ 240,000/300
material handling cost Material moves $       1,000.00 $ 900,000/900
Machine costs Machine hours $              9.46 $ 1,750,000/185,000
Receiving costs Receiving orders $       1,500.00 $ 2,100,000/1,400
Engineering costs Engineering hours $          150.00 $ 1,500,000/10,000
General plant costs Direct Labor Hours $              1.83 $ 500,000/272,500

Workings for Overheads:

part 271: (($ 6,990,000 / 272,500) * 250,000) / 500,000 = $ 12.83

Part 342: (($ 6,990,000 / 272,500) * 22,500) / 100,000 = $ 5.77

In case of any doubt, please comment.

Add a comment
Know the answer?
Add Answer to:
Scenario Cartech Manufacturing is engaged in the production of replacement parts for automobiles. One plant specializes...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Product-Costing Accuracy, Corporate Strategy, ABC Autotech Manufacturing is engaged in the production of replacement parts for...

    Product-Costing Accuracy, Corporate Strategy, ABC Autotech Manufacturing is engaged in the production of replacement parts for automobiles. One plant specializes in the production of two parts: Part #127 and Part #234. Part #127 produced the highest volume of activity, and for many years it was the only part produced by the plant. Five years ago, Part #234 was added. Part #234 was more difficult to manufacture and required special tooling and setups. Profits increased for the first three years after...

  • Cost Accounting Assignment 1 Fellco Manufacturing Fellco Manufacturing produces replacement parts for motorcycles. They specialize in...

    Cost Accounting Assignment 1 Fellco Manufacturing Fellco Manufacturing produces replacement parts for motorcycles. They specialize in the production of Part 240 and Part 390. Part 240 is the highest volume of the two and for many years was the only part the company produced. Four years ago, Part 390 was added. Part 390 is much more difficult to manufacture and requires special tooling and setups. Profits were on the rise for the first two years after the addition of Part...

  • Hello, If anyone can help me I will grestly appreciate it! I will also give a...

    Hello, If anyone can help me I will grestly appreciate it! I will also give a thumbs up! Autotech Manufacturing is engaged in the production of replacement parts for automobiles. One plant specializes in the production of two parts: Part 127 and Part 234. Part 127 produces the highest volume of activity, and for many years it was the only part produced by the plant. Five years ago, Part 234 was added. Part 234 was more difficult to manufacture and...

  • Barnes Boards produces skateboard parts for six different major US skateboard manufacturers. Barnes specializes in the...

    Barnes Boards produces skateboard parts for six different major US skateboard manufacturers. Barnes specializes in the production of trucks, which attach the skateboard wheels to the skateboard deck and allow the rider to turn the skateboard.  Barnes Boards' trucks are made primarily of molded aluminum.  Currently, Barnes Boards produces two different types of trucks: The 700 and the 775. The 700 has the highest sales and for many years was the only truck produced by Barnes Boards. As a result of the...

  • Widget Manufacturer A plant produces several related models of widgets. Production of each model involves the...

    Widget Manufacturer A plant produces several related models of widgets. Production of each model involves the same machinery. The plant produces each model in separate production runs. Each production run has significant setup costs and the cost per setup is the same for every model. Also, the assembly of each unit requires hand labor (direct labor). The following costs were incurred during a recent year: a) direct labor costs. b) costs of placing orders to procure parts. c) costs of...

  • Consider the following data for two products of Gitano Manufacturing. (Loss amounts should be indicated with...

    Consider the following data for two products of Gitano Manufacturing. (Loss amounts should be indicated with a minus sign. Round your intermediate calculations and "OH rate and cost per unit" answers to 2 decimal places) Number of units produced Direct labor cost (@ $24 per DLH) Direct materials cost Product A 11,500 units 0.20 DLH per unit $ 2.40 per unit Product B 1,500 units 0.27 DLH per unit $ 2.70 per unit Activity Machine setup Materials handling Quality control...

  • Required Information UprIver Parts manufactures two products, V-1 and V-2, at Itss RIver Plant. Selected data...

    Required Information UprIver Parts manufactures two products, V-1 and V-2, at Itss RIver Plant. Selected data for an average month for the two products follow. V-1 V-2 Units produced Direct materials cost per unit Machine hours per unit Production runs per month 1,eee 10,eee $ 2. 4 2 80 40 Production at the plant is automated and any labor cost Is Included in overhead. Data on manufacturing overhead at the plant follow Machine depreciation Setup labor Material handling 93,eee 40,8ee...

  • Consider the following data for two products of Gitano Manufacturing. (Loss amounts should be indicated with...

    Consider the following data for two products of Gitano Manufacturing. (Loss amounts should be indicated with a minus sign. Round your intermediate calculations and "OH rate and cost per unit" answers to 2 decimal places) Number of units produced Direct labor cost (@ $26 per DLH) Direct materials cost Product A 13,000 units 0.18 DLH per unit $ 2.40 per unit Product B 1,200 units 0.26 DLH per unit $ 2.70 per unit Activity Machine setup Materials handling Quality control...

  • Required information [The following information applies to the questions displayed below.] Knickknack, Inc. manufactures two products:...

    Required information [The following information applies to the questions displayed below.] Knickknack, Inc. manufactures two products: Odds and Ends. The firm uses a single, plantwide overhead rate based on direct-labor hours. Production and product-costing data are as follows: Odds $ Production quantity Direct material Direct labor (not including setup time) Manufacturing overhead 40 20 (2 hr. at $15) 96 (2 hr. at $48) 166 Ends 5,000 units $ 60 15 (3 hr. at $15) 144 (3 hr. at $48) $...

  • Everlast Co. manufactures a variety of drill bits. The company's plant is partially automated. The budget...

    Everlast Co. manufactures a variety of drill bits. The company's plant is partially automated. The budget for the year includes $444,000 payroll for 5,000 direct labor-hours. Listed below is cost driver information used in the product-costing system: Overhead Cost Pool Machine setups Materials handling Quality control Other overhead cost Total overhead Budgeted Overhead $ 171,250 105,000 300,000 175,000 $ 751, 250 Cost Driver # of setups # of barrels # of inspections # of machine hours Estimated Cost Driver Level...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT