Question

Product-Costing Accuracy, Corporate Strategy, ABC Autotech Manufacturing is engaged in the production of replacement parts for...

Product-Costing Accuracy, Corporate Strategy, ABC

Autotech Manufacturing is engaged in the production of replacement parts for automobiles. One plant specializes in the production of two parts: Part #127 and Part #234. Part #127 produced the highest volume of activity, and for many years it was the only part produced by the plant. Five years ago, Part #234 was added. Part #234 was more difficult to manufacture and required special tooling and setups. Profits increased for the first three years after the addition of the new product. In the last two years, however, the plant faced intense competition, and its sales of Part #127 dropped. In fact, the plant showed a small loss in the most recent reporting period. Much of the competition was from foreign sources, and the plant manager was convinced that the foreign producers were guilty of selling the part below the cost of producing it. The following conversation between Patty Goodson, plant manager, and Joseph Fielding, divisional marketing manager, reflects the concerns of the division about the future of the plant and its products.

JOSEPH: You know, Patty, the divisional manager is real concerned about the plant's trend. He indicated that in this budgetary environment, we can't afford to carry plants that don't show a profit. We shut one down just last month because it couldn't handle the competition.

PATTY: Joe, you and I both know that Part #127 has a reputation for quality and value. It has been a mainstay for years. I don't understand what's happening.

JOSEPH: I just received a call from one of our major customers concerning Part #127. He said that a sales representative from another firm offered the part at $20 per unit—$11 less than what we charge. It's hard to compete with a price like that. Perhaps the plant is simply obsolete.

PATTY: No. I don't buy that. From my sources, I know we have good technology. We are efficient. And it's costing a little more than $21 to produce that part. I don't see how these companies can afford to sell it so cheaply. I'm not convinced that we should meet the price. Perhaps a better strategy is to emphasize producing and selling more of Part #234. Our margin is high on this product, and we have virtually no competition for it.

JOSEPH: You may be right. I think we can increase the price significantly and not lose business. I called a few customers to see how they would react to a 25 percent increase in price, and they all said that they would still purchase the same quantity as before.

PATTY: It sounds promising. However, before we make a major commitment to Part #234, I think we had better explore other possible explanations. I want to know how our production costs compare to those of our competitors. Perhaps we could be more efficient and find a way to earn our normal return on Part #127. The market is so much bigger for this part. I'm not sure we can survive with only Part #234. Besides, my production people hate that part. It's very difficult to produce.

After her meeting with Joseph, Patty requested an investigation of the production costs and comparative efficiency. She received approval to hire a consulting group to make an independent investigation. After a three-month assessment, the consulting group provided the following information on the plant's production activities and costs associated with the two products:

Part #127 Part #234
Production 500,000 100,000
Selling price $31.86 $24.00
Overhead per unit* $12.83 $5.77
Prime cost per unit $8.53 $6.26
Number of production runs 100 200
Receiving orders 400 1,000
Machine hours 125,000 60,000
Direct labor hours 250,000 22,500
Engineering hours 5,000 5,000
Material moves 500 400

* Calculated using a plantwide rate based on direct labor hours. This is the current way of assigning the plant’s overhead to its products.

The consulting group recommended switching the overhead assignment to an activity-based approach. It maintained that activity-based cost assignment is more accurate and will provide better information for decision making. To facilitate this recommendation, it grouped the plant's activities into homogeneous sets with the following costs:

Overhead:        
   Setup costs         $ 240,000
   Machine costs         1,750,000
   Receiving costs         2,100,000
   Engineering costs         2,000,000
   Materials-handling costs         900,000
     Total         $6,990,000

Required:

1. Verify the overhead cost per unit reported by the consulting group using direct labor hours to assign overhead. Round your interim calculations and answers to the nearest cent.

Overhead rate $ per direct labor hour
Part #127 $ per unit
Part #234 $ per unit

Compute the per-unit gross margin for each product. Round your answers to the nearest cent.

Part #127 $ per unit
Part #234 $ per unit

2. After learning of activity-based costing, Patty asked the controller to compute the product cost using this approach. Recompute the unit cost of each product using activity-based costing. Round your interim calculations and answers to the nearest cent.

Part #127 $ per unit
Part #234 $ per unit

Compute the per-unit gross margin for each product. Round your answers to the nearest cent. If an answer is a loss, use a minus (-) sign to indicate.

Part #127 $ per unit
Part #234 $ per unit

3. Should the company switch its emphasis from the high-volume product to the low-volume product?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution

1a Overhead cost per unit using direct labor hours to assign overhead. Total Overheads (a) 6,990,000.00 Direct labor hours (b

2 Product cost and Gross Margin using activity-based costing Total Rate per Part #234 Part #127 Cost Part #234 Cost Overhead:

10 Should the company switch its emphasis from the high-volume product to the low-volume product Particulars Part #127 Part #

.

Add a comment
Know the answer?
Add Answer to:
Product-Costing Accuracy, Corporate Strategy, ABC Autotech Manufacturing is engaged in the production of replacement parts for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • There is no 1 or 2, only 3-5 Problem 4.34 Product-Costing Accuracy, Corporate Strategy, ABC Autotech...

    There is no 1 or 2, only 3-5 Problem 4.34 Product-Costing Accuracy, Corporate Strategy, ABC Autotech Manufacturing is engaged in the production of replacement parts for automobiles. One plant specializes in the production of two parts: Part #127 and Part #234, Part #127 pro- duced the highest volume of activity, and for many years it was the only part produced by the plant. Five years ago, Part #234 was added. Part #234 was more difficult to manufacture and required special...

  • There is no 1 or 2, only 3-5 Problem 4.34 Product-Costing Accuracy, Corporate Strategy, ABC Autotech...

    There is no 1 or 2, only 3-5 Problem 4.34 Product-Costing Accuracy, Corporate Strategy, ABC Autotech Manufacturing is engaged in the production of replacement parts for automobiles. One plant specializes in the production of two parts: Part #127 and Part #234, Part #127 pro- duced the highest volume of activity, and for many years it was the only part produced by the plant. Five years ago, Part #234 was added. Part #234 was more difficult to manufacture and required special...

  • Hello, If anyone can help me I will grestly appreciate it! I will also give a...

    Hello, If anyone can help me I will grestly appreciate it! I will also give a thumbs up! Autotech Manufacturing is engaged in the production of replacement parts for automobiles. One plant specializes in the production of two parts: Part 127 and Part 234. Part 127 produces the highest volume of activity, and for many years it was the only part produced by the plant. Five years ago, Part 234 was added. Part 234 was more difficult to manufacture and...

  • Scenario Cartech Manufacturing is engaged in the production of replacement parts for automobiles. One plant specializes...

    Scenario Cartech Manufacturing is engaged in the production of replacement parts for automobiles. One plant specializes in the production of two parts: Part 271 and Part 342. Part 271 produces the highest volume of activity, and for many years it was the only part produced by the plant. Five years ago, Part 342 was added. Part 342 was more difficult to manufacture and required special tooling and setups. Profits increased for the first three years after the addition of the...

  • Cost Accounting Assignment 1 Fellco Manufacturing Fellco Manufacturing produces replacement parts for motorcycles. They specialize in...

    Cost Accounting Assignment 1 Fellco Manufacturing Fellco Manufacturing produces replacement parts for motorcycles. They specialize in the production of Part 240 and Part 390. Part 240 is the highest volume of the two and for many years was the only part the company produced. Four years ago, Part 390 was added. Part 390 is much more difficult to manufacture and requires special tooling and setups. Profits were on the rise for the first two years after the addition of Part...

  • Product-Costing Accuracy, Plantwide and Departmental Rates, ABC Escuha Company produces two type of calculators: scientific and...

    Product-Costing Accuracy, Plantwide and Departmental Rates, ABC Escuha Company produces two type of calculators: scientific and business. Both products pass through two producing departments. The business calculator is by far the most popular. The following data have been gathered for these two products: Product-Related Data Scientific Business Units produced per year 78,000 780,000 Prime costs $247,000 $2,470,000 Direct labor hours 96,500 965,000 Machine hours 53,000 530,000 Production runs 100 150 Inspection hours 2,000 3,000 Maintenance hours 2,250 9,000 Department Data...

  • Product-Costing Accuracy, Plantwide and Departmental Rates, ABC Escuha Company produces two type of calculators: scientific and...

    Product-Costing Accuracy, Plantwide and Departmental Rates, ABC Escuha Company produces two type of calculators: scientific and business. Both products pass through two producing departments. The business calculator is by far the most popular. The following data have been gathered for these two products: Product-Related Data Scientific Business Units produced per year 75,000 750,000 Prime costs $249,000 $2,490,000 Direct labor hours 99,700 997,000 Machine hours 50,500 505,000 Production runs 100 150 Inspection hours 2,000 3,000 Maintenance hours 2,250 9,000 Department Data...

  • Product-Costing Accuracy, Plantwide and Departmental Rates, ABC Escuha Company produces two type of calculators: scientific and...

    Product-Costing Accuracy, Plantwide and Departmental Rates, ABC Escuha Company produces two type of calculators: scientific and business. Both products pass through two producing departments. The business calculator is by far the most popular. The following data have been gathered for these two products: Product-Related Data Scientific Business Units produced per year 77,000 770,000 Prime costs $265,000 $2,650,000 Direct labor hours 101,000 1,010,000 Machine hours 49,000 490,000 Production runs 100 150 Inspection hours 2,000 3,000 Maintenance hours 2,250 9,000 Department Data...

  • Product-Costing Accuracy, Plantwide and Departmental Rates, ABC Escuha Company produces two type of calculators: scientific and...

    Product-Costing Accuracy, Plantwide and Departmental Rates, ABC Escuha Company produces two type of calculators: scientific and business. Both products pass through two producing departments. The business calculator is by far the most popular. The following data have been gathered for these two products: Product-Related Data Scientific Business Units produced per year 76,000 760,000 Prime costs $253,000 $2,530,000 Direct labor hours 103,400 1,034,000 Machine hours 51,200 512,000 Production runs 100 150 Inspection hours 2,000 3,000 Maintenance hours 2,250 9,000 Department Data...

  • Product-Costing Accuracy, Plantwide and Departmental Rates, ABC Escuha Company produces two type of calculators: scientific and...

    Product-Costing Accuracy, Plantwide and Departmental Rates, ABC Escuha Company produces two type of calculators: scientific and business. Both products pass through two producing departments. The business calculator is by far the most popular. The following data have been gathered for these two products: Product-Related Data Scientific Business Units produced per year 74,000 740,000 Prime costs $248,000 $2,480,000 Direct labor hours 102,200 1,022,000 Machine hours 50,000 500,000 Production runs 100 150 Inspection hours 2,000 3,000 Maintenance hours 2,250 9,000 Department Data...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT