Question

(Ch 12) Assume that a task in a project has the following three time estimates: Optimistic...

(Ch 12) Assume that a task in a project has the following three time estimates:

Optimistic completion time = 10 weeks

Most likely completion time = 14 weeks

Pessimistic completion time = 21 weeks

Compute the estimated task completion time for this task.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Optimistic completion time (To) = 10 weeks

Most likely completion time (Tm) = 14 weeks

Pessimistic completion time (Tp) = 21 weeks

Estimated task completion time is given below-

T+* 1m +7

10 +4*14+ 21

= 14.5 weeks

Hence the estimated task completion time for this task is 14.5 weeks

Add a comment
Know the answer?
Add Answer to:
(Ch 12) Assume that a task in a project has the following three time estimates: Optimistic...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT