Question

The manager at Ormonde Inc. collected the value stream mapping data from the plants most problematic manufacturing cell that

Overall Process Attributes Process Step 1 Average demand: 520/day Batch size: 30 Number of shifts per day: 3 Availability: 8

Process Step 2 Process Step 3 Bending Cycle time = 240 seconds Setup time = 7 minutes Up time = 90% Operators = 2 WIP = 550 u

Help with question b. please!

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Takt time of cell = (Production time * Number of shifts * hour conversion to seconds) / Average daily demand

= (8- (45/60))*3 * 3600 / 520

= 150.58 seconds

= 2.51 minutes

****Please please please LIKE THIS ANSWER, so that I can get a small benefit, Please****

Add a comment
Know the answer?
Add Answer to:
Help with question b. please! The manager at Ormonde Inc. collected the value stream mapping data...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The manager at FunQ, Inc collected the value stream mapping data from one of t manufacturing...

    The manager at FunQ, Inc collected the value stream mapping data from one of t manufacturing cell. This produces The data is shown in the below table. ll produces a special steel part that is widely used in automotive industries Average demand:180 units/day Batch size: 30 units Number of shifts per day: 1 Availability: 8-hours shift with including two 30 min breaks (60 min break time in total), 7 hours net available time Basic cell information Cycle time 140 sec...

  • Anguilla Manufacturing is interested in using the data collected during value stream mapping to evaluate the...

    Anguilla Manufacturing is interested in using the data collected during value stream mapping to evaluate the current state of performance of the capacity of its manual assembly line process under different batch size assumptions. The availability of processing per shift, after accounting for breaks and a midshift employee meeting, is 436 minutes. The current operating characteristics of each processing step are found in the accompanying table. Note that each step can only process one part at a time and all...

  • 13. manufacturing is interested is in using the data Collected Stream mapping to Curosent state perstormance...

    13. manufacturing is interested is in using the data Collected Stream mapping to Curosent state perstormance of its manual under UUUUUUU Anguilla interested dusing value evaluate the of the Capacity assembly line process different butch Size assumptions. The cuandbility of processing pero shift, after accounting for breaks and a midshift employee meeling is L36 mimutesThe current Opexeting Characterstics of each processing Step Com, only process one pest cat a time and all steps the must process Same Sized betches. 20...

  • Question Help The table below provides the parameters for a new current state vake stream map...

    Question Help The table below provides the parameters for a new current state vake stream map for the family traine e Jensen Bearings infirm described in the chapter. This table depicts the value stream atter Kline Steel agrees to condaily orders for steel sheels and also agrees to deliver on a daily basis Calculate each component of the new value stream's reduced lead me Jensen Bearings operates 5 days per week Click the icon to view the data from the...

  • I AM COMPLETELY CONFUSED! Any help would be greatly appreciated. Chairvana’s Table Assembly Operations: Chairvana Inc....

    I AM COMPLETELY CONFUSED! Any help would be greatly appreciated. Chairvana’s Table Assembly Operations: Chairvana Inc. manufactures metal tables and chairs at its plant in Paxton, Illinois. Recently hired general manager, Bob Behar, is concerned about the large inventories and manufacturing inefficiencies in the plant. The Paxton plant has two separate assembly lines – one for chairs and one for tables. Demand for chairs is significantly larger than tables, so Bob decides to tackle the table assembly process for first....

  • Lead Time Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC)...

    Lead Time Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC board assembly operation, a number of individuals are responsible for assembling electronic components into printed circuit boards. Each operator is responsible for soldering components according to a given set of instructions. Operators work on batches of 50 printed circuit boards. Each board requires 4 minutes of board assembly time. After each batch is completed,...

  • Lead Time Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC)...

    Lead Time Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC board assembly operation, a number of individuals are responsible for assembling electronic components into printed circuit boards. Each operator is responsible for soldering components according to a given set of instructions. Operators work on batches of 50 printed circuit boards. Each board requires 4 minutes of board assembly time. After each batch is completed,...

  • Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly,...

    Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC board assembly operation, a number of individuals are responsible for assembling electronic components into printed circuit boards. Each operator is responsible for soldering components according to a given set of instructions. Operators work on batches of 50 printed circuit boards. Each board requires 4 minutes of board assembly time. After each batch is completed, the operator...

  • Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC boand assembly o...

    Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC boand assembly operation, a number。individuals are esponsible for assenting electronic components into pn te i ut boards. Each operator s es ons le r so den g e net erdg to a given set of instructions. Operators work on batches of s0 printed dircuit boards. Each board requires 4 minutes of board assembly time. After each...

  • what are the answers to the last question Save Homework: HW #3 Score: 6.67 of 8...

    what are the answers to the last question Save Homework: HW #3 Score: 6.67 of 8 pts Problem 1 2 of 9 (7 complete) HW Score: 76.67%, 30.67 of 40 pts 3 Question Help Billy's Hamburger Barn has a single drive-up window. Currently, there is one attendant at the window who takes the order (40 - 60 seconds), gathers up the food and bags it (45-50 seconds), and then takes the customer's money (40-50 seconds) before handing the food to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT