Question

13. manufacturing is interested is in using the data Collected Stream mapping to Curosent state perstormance of its manual un
w Identify and the the bottleneda Operaction nes poolessing Cerpaucity batch size listed in a lines for each la D Explain w
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

It is given that-

Availability of processing per shift = 436 minutes

  1. Average processing time per unit:

Average processing time per unit = Cycle Time (sec) + ( Setup time (min) * 60 / Batch size)

Using this formula Average processing time is calculated as follows:

Process

Cycle Time per part (seconds)

Set-up Time per batch (minutes)

Processing Time per unit (Seconds per unit)

10

20

30

40

Saw

20

3

38

29

26

24.5

Sand

15

4

39

27

23

21

Drill

30

0

30

30

30

30

Assemble

25

3

43

34

31

29.5

Mark

10

8

58

34

26

22

  1. Bottleneck operations and Line’s processing capacity:

Bottleneck operation is the one with highest processing time for each batch size option. Bottleneck operations are highlighted in red and listed against the batch sizes as below:

Process

Cycle Time per part (seconds)

Set-up Time per batch (minutes)

Processing Time per unit (Seconds per unit)

10

20

30

40

Saw

20

3

38

29

26

24.5

Sand

15

4

39

27

23

21

Drill

30

0

30

30

30

30

Assemble

25

3

43

34

31

29.5

Mark

10

8

58

34

26

22

Bottleneck

Mark

Assemble

Assemble

Drill

Line's processing capacity (Units per shift)

451.03

769.41

843.87

872.00

Also, the Line’s processing capacity is calculated by dividing available seconds per shift (436*60) by processing time per unit of the bottleneck operation. i.e. The Line capacity for batch size 30 is = (436*60)/31, and so on.

  1. Batch sizes beyond 40 units will not increase the line’s capacity further.

Higher batch sizes distribute loss in set-up time, hence reduce the processing time per unit. For batch size 40, the bottleneck operation is “Drill” with a cycle time per unit of 30 seconds. This is already the operation with maximum cycle time among all. Batch sizes higher than 40 will reduce the processing times of other operations further, and hence bottleneck operation is not going to change. So, we can conclude that Drill is going to determine the line’s capacity and because its set up time is ZERO, its processing time will remain 30 seconds for all batch sizes.

So, beyond 40 units batch size, bottleneck operation and processing time are not changing, and the capacity will remain 872 units. For example, capacity is calculated below for batch size 50.

Process

Cycle Time per part (seconds)

Set-up Time per batch (minutes)

Processing Time per unit (Seconds per unit)

10

20

30

40

50

Saw

20

3

38

29

26

24.5

23.6

Sand

15

4

39

27

23

21

19.8

Drill

30

0

30

30

30

30

30

Assemble

25

3

43

34

31

29.5

28.6

Mark

10

8

58

34

26

22

19.6

Bottleneck

Mark

Assemble

Assemble

Drill

Drill

Line's processing capacity (Units per shift)

451.03

769.41

843.87

872.00

872.00

Add a comment
Know the answer?
Add Answer to:
13. manufacturing is interested is in using the data Collected Stream mapping to Curosent state perstormance...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Anguilla Manufacturing is interested in using the data collected during value stream mapping to evaluate the...

    Anguilla Manufacturing is interested in using the data collected during value stream mapping to evaluate the current state of performance of the capacity of its manual assembly line process under different batch size assumptions. The availability of processing per shift, after accounting for breaks and a midshift employee meeting, is 436 minutes. The current operating characteristics of each processing step are found in the accompanying table. Note that each step can only process one part at a time and all...

  • Help with question b. please! The manager at Ormonde Inc. collected the value stream mapping data...

    Help with question b. please! The manager at Ormonde Inc. collected the value stream mapping data from the plant's most problematic manufacturing cell that fabricates parts for washing machines. This data is shown in Table 1. Using this data, calculate the current state performance of the cell and answer the following questions. Click the icon to view Table 1. a. What is the cell's current inventory level? The cell's current inventory level is 2050 parts. (Enter your response as a...

  • The manager at FunQ, Inc collected the value stream mapping data from one of t manufacturing...

    The manager at FunQ, Inc collected the value stream mapping data from one of t manufacturing cell. This produces The data is shown in the below table. ll produces a special steel part that is widely used in automotive industries Average demand:180 units/day Batch size: 30 units Number of shifts per day: 1 Availability: 8-hours shift with including two 30 min breaks (60 min break time in total), 7 hours net available time Basic cell information Cycle time 140 sec...

  • Two-step Process Utilization: A two- used to finish a product: painting and drying. There are 5 workers and each one ta...

    Two-step Process Utilization: A two- used to finish a product: painting and drying. There are 5 workers and each one takes an average of 60 minutes to paint each unit. Drying takes place in an oven that can hold up to 100 units and it takes 5 minutes to load each unit. Once all the units are loaded into the oven, it takes 6 hours to dry each load. Assume that the process is capacity constrained (so the demand rate...

  • Question Help The table below provides the parameters for a new current state vake stream map...

    Question Help The table below provides the parameters for a new current state vake stream map for the family traine e Jensen Bearings infirm described in the chapter. This table depicts the value stream atter Kline Steel agrees to condaily orders for steel sheels and also agrees to deliver on a daily basis Calculate each component of the new value stream's reduced lead me Jensen Bearings operates 5 days per week Click the icon to view the data from the...

  • Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC boand assembly o...

    Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC boand assembly operation, a number。individuals are esponsible for assenting electronic components into pn te i ut boards. Each operator s es ons le r so den g e net erdg to a given set of instructions. Operators work on batches of s0 printed dircuit boards. Each board requires 4 minutes of board assembly time. After each...

  • Atlas Inc. is a toy bicycle manufacturing company producing a five inch small version of the...

    Atlas Inc. is a toy bicycle manufacturing company producing a five inch small version of the bike that Lance Armstrong rode to win his first Tour de France. The assembly line at Atlas Inc. consists of seven work stations, each performing a single step. Stations and processing times are summarized here: Step 1 (50 sec.): The plastic tube for the frame is cut to size. Step 2 (40 sec.): The tube is put together. Step 3 (55 sec.): The frame...

  • Data Analysis Project Part 1 Custom Fabric Ventures is a small company that produces fabric-based wardrobe...

    Data Analysis Project Part 1Custom Fabric Ventures is a small company that produces fabric-based wardrobe accessories (such as, handbags, scarves, and headbands) and home accessories (such as placemats, pillows, and window treatments).   The company keeps a limited number of popular items in stock, but primarily produces custom orders. Customers are able to choose from a wide selection of styles, sizes, and fabrics for each type of product. Most of the company’s customers are small boutiques, home décor shops, and home-decorators...

  • 109 CASE STUDY Dream Desk Compary Dream Desk Company is a major supplier of office desks for can ...

    109 CASE STUDY Dream Desk Compary Dream Desk Company is a major supplier of office desks for can profit from this market growth if prices can be held in line home and business. The company has been in existence since 1875. Affler serving an apprenticeship as a cabinet maker in the and quick delivery can be promised. Dream Desk operates a 250,000 sq. ft. manufacturing fa- cast, George Dreamer had a violent disagreement with the shop eility in Casa Petite,...

  • 10. Write a one-page summary of the attached paper? INTRODUCTION Many problems can develop in activated...

    10. Write a one-page summary of the attached paper? INTRODUCTION Many problems can develop in activated sludge operation that adversely affect effluent quality with origins in the engineering, hydraulic and microbiological components of the process. The real "heart" of the activated sludge system is the development and maintenance of a mixed microbial culture (activated sludge) that treats wastewater and which can be managed. One definition of a wastewater treatment plant operator is a "bug farmer", one who controls the aeration...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT