1-a.
Throughput time = Process time + Inspection time + Move time + Queue time
Month |
||||
1 |
2 |
3 |
4 |
|
Move time per unit |
0.7 |
0.7 |
0.4 |
0.7 |
Process time per unit |
0.5 |
0.5 |
0.6 |
0.7 |
Queue time per unit |
3.7 |
4 |
2.6 |
1.7 |
Inspection time per unit |
0.5 |
0.4 |
0.7 |
0.7 |
Throughput time (in days) |
5.4 |
5.6 |
4.3 |
3.8 |
1-b.
Manufacturing Cycle Efficiency (MCE) = Process time/ Throughput time
Month |
||||
1 |
2 |
3 |
4 |
|
Process time per unit |
0.5 |
0.5 |
0.6 |
0.7 |
÷Throughput time |
5.4 |
5.6 |
4.3 |
3.8 |
MCE |
9.3% |
8.9% |
14.0% |
18.4% |
1-c.
Delivery cycle time = Wait time + Process time + Inspection time + Move time + Queue time
Month |
||||
1 |
2 |
3 |
4 |
|
Wait time |
10.0 |
8.0 |
5.0 |
4.0 |
Move time per unit |
0.7 |
0.7 |
0.4 |
0.7 |
Process time per unit |
0.5 |
0.5 |
0.6 |
0.7 |
Queue time per unit |
3.7 |
4 |
2.6 |
1.7 |
Inspection time per unit |
0.5 |
0.4 |
0.7 |
0.7 |
Delivery cycle time(in days) |
15.4 |
13.6 |
9.3 |
7.8 |
3-a.
Month 5 |
|
Move time per unit |
0.7 |
Process time per unit |
0.7 |
Inspection time per unit |
0.7 |
Throughput time (in days) |
2.1 |
Month 5 |
|
Process time |
0.7 |
÷Throughput time |
2.1 |
MCE |
33.3% |
3-b.
Month 6 |
|
Move time per unit |
0.7 |
Process time unit |
0.7 |
Throughput time (in day) |
1.4 |
Month 6 |
|
Process time unit |
0.7 |
÷Throughput time |
1.4 |
MCE |
50.0% |
400 points DataSpan, Inc, automated its plant at the start of the current year and installed...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month Throughput time (days) Delivery cycle time (days) Manufacturing...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations, Month 34 Throughput time (days) Delivery cycle time (days)...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month نية Throughput time (days) Delivery cycle time (days)...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 ? Throughput time (days) Delivery...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 2 1 Throughput time (days) Delivery cycle time...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1. 4. ? 3 ? > Throughput time...
DataSpan, Inc. automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Throughout te (days) Delivery cycle time (days) Manufacturing cycle...
DataSpan, Inc., automated its plant at the start of the current
year and installed a flexible manufacturing system. The company is
also evaluating its suppliers and moving toward Lean Production.
Many adjustment problems have been encountered, including problems
relating to performance measurement. After much study, the company
has decided to use the performance measures below, and it has
gathered data relating to these measures for the first four months
of operations.
Problem 10-14 Measures of Internal Business Process Performance (LO10-3]...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month ? Throughput time (days) Delivery cycle time (days)...