A firm uses a serial assembly system and needs answers to the following:

a. An output of 900 units per shift (10.50 hours) is desired for a new processing system. The system requires product to pass through four stations where the work content at each station is 30 seconds. What is the required cycle time for such a system? (Round your answer to the nearest whole number.)

b. How efficient is your system with the cycle time you calculated? (Round your answer to 1 decimal place.)

c. Station 3 changes and now requires 50 seconds to complete. What will need to be done to meet demand (assume only 10.50 hours are available)? What is the efficiency of the new system? (Round your answer to 1 decimal place.)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer a:

desired output = 900 units per 10.5 hours=  10.5*60*60/900= 42 secs per unit

Hence the workstation cycle time required is 42 secs

Answer b: Total task time= 30 secs*4 = 120 secs, No. of workstation= 4

Efficiency= total task time / no. of workstation* cycle time = 120/(4*42)= 0.7142 or 71.4%

Answer c: If station 3 now takes 50 secs, than the cycle time will be 50 secs. We need to employ 2 parallel workstations at station 3 so that the effective cycle time becomes its half that is 50/2= 25 secs.

If station 3 takes 50 secs, total task time= 30+30+50+30= 140

cycle time= 50 secs

Efficiency= total task time / no. of workstation* cycle time = 140/(4*50)= 0.7 or 70.0%

Add a comment
Know the answer?
Add Answer to:
A firm uses a serial assembly system and needs answers to the following: a. An output...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • An assembly line is to operate eight hours per day with a desired output of 160...

    An assembly line is to operate eight hours per day with a desired output of 160 units per day. The following table contains information on this product's task times and precedence relationships: IMMEDIATE PREDECESSOR TASK TIME (SECONDS) 100 TASK A 70 D 50 40 C C. D 70 140 G H b. What is the required workstation cycle time meet the desired output rate? (Round your answer to the nearest whole number.) Workstation cycle time seconds per unit c. Balance...

  • The following tasks are to be performed on an assembly line: TASK SECONDS TASKS THAT MUST...

    The following tasks are to be performed on an assembly line: TASK SECONDS TASKS THAT MUST PRECEDE A 18 — B 10 A C 25 B D 15 B E 14 C F 17 D G 12 E, F H 20 G The workday is 6.25 hours long. Demand for completed product is 750 per day. a. Find the cycle time required to meet the desired output rate. (Round your answer to 1 decimal place.) b. What is the theoretical...

  • Francis Johnson's plant needs to design an efficient assembly line to make a new product. The...

    Francis Johnson's plant needs to design an efficient assembly line to make a new product. The assembly line needs to produce 12 units per hour, and there is room for only five workstations. The tasks and the order in which they must be performed are shown in the following table. Tasks cannot be split, and it would be too expensive to duplicate any task. TASK TIME IMMEDIATE TASK (MINUTES) PREDECESSOR 2.5 2.0 2.0 3.0 3.0 3.0 3.0 A,B, C b....

  • Problem 6-22 Francis Johnson's plant needs to design an efficient assembly line to make a new...

    Problem 6-22 Francis Johnson's plant needs to design an efficient assembly line to make a new product. The assembly line needs to produce 24 units per hour, and there is room for only five workstations. The tasks and the order in which they must be performed are shown in the following table. Tasks cannot be split, and it would be too expensive to duplicate any task TASK TIME IMMEDIATE TASK (MINUTES) PREDECESSOR 1.0 1.0 2.5 1.5 A, B, C 1.5...

  • Suppose a 20-station automatic assembly line with no storage or slack between stations is being planned...

    Suppose a 20-station automatic assembly line with no storage or slack between stations is being planned for a major automation thrust in the manufacturing plant where you are employed as the automation engineer. A cycle time objective has been set at 10 seconds in order to meet production quotas of 2000 units per eight-hour shift. a) Assuming no station jamming at all, what is the ideal production rate of this line? Can the production quota of 2000 units per eight-hour...

  • The desired daily output for an assembly line is 540 units. This assembly line will operate...

    The desired daily output for an assembly line is 540 units. This assembly line will operate 729 minutes per day. The following table contains information on this product's task times and precedence relationships: TASK TASK TIME (SECONDS) IMMEDIATE PREDECESSOR A 30 — B 28 A C 18 B D 69 B E 34 A F 36 E G 42 C, D H 24 F, G b. What is the workstation cycle time? Cycle time seconds c. Balance this line using...

  • You have been asked to balance a flow shop assembly operation to achieve an output rate...

    You have been asked to balance a flow shop assembly operation to achieve an output rate of 80 units over two eight-hour shifts - 16 hours. Task times and precedence relationships are shown in the table below: Task Predecessor Time (minutes) A -- 2 B A 4 C 7 D A, B 11 E C 9 F D 10 G E, F 7 H D, G 4 What is the cycle time in minutes? What is the theoretical number of...

  • All airplane passengers at the Lake City Regional Airport must pass through a security screening area...

    All airplane passengers at the Lake City Regional Airport must pass through a security screening area before proceeding to the boarding area. The airport has three screening stations available, and the facility manager must decide how many to have open at any particular time. The service rate for processing passengers at each screening station is 3.5 passengers per minute. On Monday morning the arrival rate is 4.9 passengers per minute. Assume that processing times at each screening station follow an...

  • TASK SECONDS TASKS THAT MUST PRECEDE A 25 — B 15 A C 20 B D...

    TASK SECONDS TASKS THAT MUST PRECEDE A 25 — B 15 A C 20 B D 29 B E 16 C F 8 D G 35 E, F H 32 G The workday is 10.5 hours long. Demand for completed product is 900 per day. a. Find the cycle time required to meet the desired output rate. (Round your answer to 1 decimal place.) b. What is the theoretical number of workstations required to meet the desired output rate? (Round...

  • QUESTION 6 An industrial food processor needs to design a product layout for a new line...

    QUESTION 6 An industrial food processor needs to design a product layout for a new line of frozen pizza. The company plans to use this new production line ten hours a day in order to meet projected demand of 1,000 pizzas per day. The following table describes the tasks involved in the production of a frozen pizza. Task Immediate Predecessors Task Duration (Seconds) none 10 B C,D F E Design this layout using the decision rule of Longest Processing Time...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT