Question

The BOM for product A is given below Weeks of Lead Time On Hand 75 150 50 100 Part D2 Assume the master schedule calls for 20
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Below is the material plan -

A
LT 1
On Hand 1 2 3 4 5 6
Gross Requirement 0 0 0 0 200 250
Scheduled Receipts 0 0 0 0 0 0
Projected on Hand 75 75 75 75 75 0 0
Net Requirements 0 0 0 0 125 250
Planned Order Receipts 0 0 0 0 125 250
Planned Order Releases 0 0 0 125 250 0
C
LT 1
Gross Requirement 0 0 0 250 500 0
Scheduled Receipts 0 0 0 0 0 0
Projected on Hand 50 50 50 50 0 0 0
Net Requirements 0 0 0 200 500 0
Planned Order Receipts 0 0 0 200 500 0
Planned Order Releases 0 0 200 500 0 0
B
LT 2
Gross Requirement 0 0 200 500 0 0
Scheduled Receipts 0 0 0 0 0 0
Projected on Hand 150 150 150 0 0 0 0
Net Requirements 0 0 50 500 0 0
Planned Order Receipts 0 0 50 500 0 0
Planned Order Releases 50 500 0 0 0 0
D
LT 2
Gross Requirement 0 0 400 1125 250 0
Scheduled Receipts 0 0 0 0 0 0
Projected on Hand 100 100 100 0 0 0 0
Net Requirements 0 0 300 1125 250 0
Planned Order Receipts 0 0 300 1125 250 0
Planned Order Releases 300 1125 250 0 0 0

Production of D & B should be started from Week 1 itself.

Add a comment
Know the answer?
Add Answer to:
The BOM for product A is given below Weeks of Lead Time On Hand 75 150...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The MPS for the product shown calls for 75 units to be produced in weeks 2...

    The MPS for the product shown calls for 75 units to be produced in weeks 2 and 4. Item B has a lead time of 1 week, the batch size is 200, and there are currently 100 units of inventory. A planned order release for B will be needed in week(s) ________. a. 1 b. 2 c. 3 d. 1 and 2 e. 1 and 3

  • The MPS for the product shown calls for 75 units to be produced in weeks 2...

    The MPS for the product shown calls for 75 units to be produced in weeks 2 and 4. Item B has a lead time of 1 week, the batch size is 200, and there are currently 100 units of inventory. A planned order release for B will be needed in week(s) ________. a. 1 b. 2 c. 3 d. 1 and 2 e. 1 and 3 A B (3) С D (2)

  • Determine planned order releases for each part shown in the product structure tree. 180 units of...

    Determine planned order releases for each part shown in the product structure tree. 180 units of the finished product 565 are needed in week 6 (as shown in the master production schedule below). To figure out X43 material plan, look at planned order releases of both 565 and Y36. So, fill out X43 form after filling out 565 and Y36 plans. 565 X43 Y36(2) N78 J27(4) X43 Part Number On Hand Lot Size Lead Time 565 0 Lot-for-lot 1 week...

  • The following table lists the components needed to assemble an end item, lead times (in weeks),...

    The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 12 B(2), J(3) C 4 15 G(2), B(2) K 4 21 H(4), B(2) B 3 32 J 4 27 G 4 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...

  • The following table lists the components needed to assemble an end item, lead times (in weeks),...

    The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 2 0 L(2), C(1), K(3) L 2 8 B(2), J(3) C 3 12 G(2), B(2) K 3 17 H(4), B(2) B 2 32 J 3 27 G 3 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...

  • Problem 12-18 Develop a material requirements plan for component H. Lead times for the end item a...

    Problem 12-18 Develop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the start of week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are in production and will be completed by the start of week 2. (Leave no cells...

  • Product A needs 3 components of B and 2 components of C. Component B on the...

    Product A needs 3 components of B and 2 components of C. Component B on the other hand needs 2 units of component C and E. Component C requires a unit of D, and 3 components of E. Component D on the other hand requires 5 units of E. Lead time is 2 weeks. The company expects to deliver 100 units of A on the 3rd week, 250 units on the 5th week, and 500 units on the 8th week....

  • Given the product structure tree and the inventory on-hand shown in figure and table, determine the...

    Given the product structure tree and the inventory on-hand shown in figure and table, determine the net requirement for A, B, C, D, and E. Given the product structure tree and the inventory on-hand shown in figure and table, determine the net requirement for C and E to produce 50 units of finished goods(X). Show all processes for solution. component A B C D E 50 50 50 100 250 Inventory on Hand A(2) B(3) E(2) D(3) E(2) 1. What...

  • The following table lists the components needed to assemble an end item, lead times (in weeks),...

    The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand on Hand Iten End Direct Components L(2), C(1), K(3) B(2), (3) G(2), B(2) H(4), B(2) a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an MRP plan.) Additional units C b. An order for the end item is scheduled to be shipped at...

  • You need to schedule 10 units of product Alpha for delivery in 6 weeks. Three units...

    You need to schedule 10 units of product Alpha for delivery in 6 weeks. Three units of D and 2 units of F are required for each Alpha. The lead time for Alpha is 1 week. Lead time for D is 1 week, and lead time for F is 2 weeks. Click the icon to view the product structure Click the icon to view the time-phased product structure. i More Info Construct a net material requirements plan if there are...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT