Question

Create a precedence diagram from the given table, then find a workstation assignment by taking cycle...

Create a precedence diagram from the given table, then find a workstation assignment by taking cycle time=17 minutes and assigning in the order of the greatest task time.

Task Label Time Predecessors
A 2 ------
B 7 A
C 5 ------
D 2 ------
E 15 C, D
F 7 A, E
G 6 ------
H 4 B, G
I 9 A
J 10 -------
K 4 -------
L 8 J, K
M 6 A, L
N 15 F, H, I, M
0 0
Add a comment Improve this question Transcribed image text
Answer #1

4i 3 Time ん(G 5+4 4, A,1 2+9 IS 8 6 6. MH 64 1-01 4. N is

Add a comment
Know the answer?
Add Answer to:
Create a precedence diagram from the given table, then find a workstation assignment by taking cycle...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Construct an Activity-on-branch network from the precedence relationships of activities shown Activity Predecessors Duration 6 7...

    Construct an Activity-on-branch network from the precedence relationships of activities shown Activity Predecessors Duration 6 7 A A A B с D E F 1 14 5 8 9 3 5 3 B C D C, D D H F E, J F GI G, I L, N H I J K L M 12 6

  • Question 2 (20%): A precedence table is given below for a process with 6 tasks, their...

    Question 2 (20%): A precedence table is given below for a process with 6 tasks, their immediate predecessors and their task times: Immediate Task time label predecessors minutes) 2.0 1.5 2.0 3.0 15 2.0 Daily working time is 14 hours. The daily output need is 210 piece a) Draw the relationship structure of these tasks? 8) Calculate the cycle sims? Use the line balancing technique to determine the number of stations and arrange these tasks to each station? Calculate the...

  • Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and...

    Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and the following precedence diagram. Task A 20 sec Task B 40 sec Task E 60 sec Task G 50 sec Task C 40 sec Task D 10 sec Task F 20 sec a) Assign tasks to workstations using the "most following tasks" heuristic rule to break any ties. Show which tasks are assigned to each workstation (4 points). b) Assign tasks to workstations using...

  • The operations manager of an instruments company is balancing an assembly line. The company needs to...

    The operations manager of an instruments company is balancing an assembly line. The company needs to build 96 instruments per 24-hour day. The assembly line activities are: a. Draw the precedence diagram. b. If the daily (24-hour) production rate is 96 units, what is the greatest possible cycle time? c. If the cycle time after allowances is given as 10 minutes, what is the daily (24-hour) production rate? d. With a 10-minute cycle time, what is the theoretical minimum number...

  • Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and...

    Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and the following precedence diagram. Task A 20 sec Task B 40 sec Task E 60 sec Task G 50 sec Task C 40 sec Task D 10 sec Task F 20 sec a) Assign tasks to workstations using the most following tasks" heuristic rule to break any ties. Show which tasks are assigned to each workstation (4 points) b) Assign tasks to workstations using...

  • Agent Smith, operations manager at the Matrix franchise, faces assembly line balancing problems. He has been...

    Agent Smith, operations manager at the Matrix franchise, faces assembly line balancing problems. He has been told that the firm needs to assemble 1400 agents per day. There are 420 minutes of productive time in each working day. The assembly line activities are given below: Task Time (seconds) Predecessor A 13 - B 4 A C 10 B D 10 - E 6 D F 12 E G 5 E H 6 F, G I 7 H J 5 H...

  • Problem 15-7 Consider the following table of precedence relationships for a portion of a house building...

    Problem 15-7 Consider the following table of precedence relationships for a portion of a house building project: Task Duration Estimates Immediate Predecessor(s) A Prepare Site 3 days None B Install Rough Plumbing 2 days Prepare Site C Pour Concrete Foundation 3 days Install Rough Plumbing D Concrete Curing Time 4 days Pour Concrete Foundation E Preassemble Wall Frames 6 days None F Erect Wall Frames 2 days Preassemble WF, Cure Concrete G Install Roof 1 day Erect Wall Frames H...

  • Problem Statement: A factory producing the new COVID-19 at-home testing kits is determining how to best...

    Problem Statement: A factory producing the new COVID-19 at-home testing kits is determining how to best line balance their production process. There are 12 steps to the production process, and they are presented below, along with their predecessors and how long it takes to complete each task. Assume all times are in minutes. This facility operates for 7 hours per day. Task C D E F G H I J K L A B Nil A B B B B...

  • a) The correct precedence relationship with one of the possible assignment of tasks to workstations is...

    a) The correct precedence relationship with one of the possible assignment of tasks to workstations is shown in ? b) What is the operating efficiency of the assembly​ line, using your answer to​ (a)? c) What is the theoretical minimum number of​ workstations? d) What is the idle time per boat​ produced? IOIIGWufk. Cny Score: 0 of 1 pt Problem 9.18 Assembly Line Balancing 10 of 11 (6 complete) HW Score: 54.55%, 6 of 11 Question Holp The final assembly...

  • Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and...

    Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and finish, and slack for each task. Activity Duration (Days) Immediate Predecessor none none none KUHIGT mono 00 00 ONTHOOOO D, E G, J, K b. Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) Task Earliest Start s+ Start (ES) Earliest Completion (EC) Immediate Predecessors None None None B C...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT