Why is it difficult to estimate mega project's cost and benefits. (Project Management)
Ans: First, the time horizon of 2-5 years to complete large, complex projects makes it difficult to accurately forecast costs and user needs. Second, the sheer complexity of these kinds of projects makes it difficult to accurately estimate all of the costs. Third, the severity of the risks involved is significant. When things go wrong, they go wrong is a big way. While such conditions would suggest a very conservative estimate, the opposite occurs. Either blind enthusiasm or calculated deception is used to promote an exaggerated case for the project.
Why is it difficult to estimate mega project's cost and benefits. (Project Management)
IT Project Management: Chapter 7 Project Cost Management: 1. If the cost estimate will be the basis for contract awards and performance reporting, it should be a ____ and as accurate as possible. a. budgetary estimate b. definitive estimate c. rough order of magnitude estimate d. final estimate 2. The main outputs of the ____________________ process are activity cost estimates, basis of estimates, and project document updates. 3. It’s important for the team to ____________________ assumptions they made when developing...
For this Discussion, read Change Management on a Mega Project: A Case Study. Analyze the change management process using the change requests from different stakeholders. To whom were change requests made? How were the change requests handled for each stakeholder? What was the consequence of the change requests on the project?
1 What is involved in project scope management, and why is good project scope management so important on IT projects? 2 What is involved in collecting requirements for a project? Why is it often such a difficult thing to do? 3 Why do you think schedule issues often cause the most conflicts on projects?
the cost if common equity financing is more difficult to estimate than the cost of debt and preffered equity why?
Why use continuums? What makes up project cost management plan? Why determine and outline project objectives? Explain project cash flow statement What’s top down and bottom up estimating? Cost trade offs management?
The cash flows associated with an investment project are an immediate cost of $1600 and benefits of $500 in one year, $1500 in two years, and $1700 in three years. The cost of capital (WACC) is 10%. What is the project's NPV? Your Answer:
What is the role of the PMIS in project management? Discuss the applications and benefits of web-based project management. Discuss the uses of the PMIS throughout the phases of the project life cycle.
Project S has a cost of $15,000 and is expected to produce benefits (cash flows) of $3,000 per year for 6 years. Calculate the project's Net Present Value (NPV) assuming a cost of capital of 15%. -$5,734 -$1,675 -$3,647 -$814 $3,000
Do you agree with the statement that management jobs are increasingly more difficult? Why or why not? What factors are leading to the increasing difficulty of management jobs?
Why is it so difficult to estimate the effect of Government spending on the economy and how have economists addressed the problems?