Question

Given the project information in the following table, what is the probability of completing the National Holiday Toy project
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Activity Time=(Optimistic+(4*Most Likely)+Pessimistic)/6

Variance=((Pessimistic-Optimistic)/6)^2

1 B C D E F G H I
2 Activity ID Predecessor Optimistic Most Likely Pessimistic Activity Time=(Optimistic+(4*Most Likely)+Pessimistic)/6 Variance=((Pessimistic-Optimistic)/6)^2 Critical activities
3 1 --- 6 12 24 13 9.00 Yes
4 2 1 16 19 28 20 4.00 Yes
5 3 1 4 7 10 7 1.00
6 4 2 21 30 39 30 9.00 Yes
7 5 2 17 29 47 30 25.00 Yes
8 6 3,4,5 4 7 12 7 1.78 Yes
9 7 6 13 15 19 15 1.00 Yes
10 Project completion time 85
11 Variance of critical path 1 16.778
12 Variance of critical path 2 40.778
13 Standard Deviation of critical path 1 4.096
14 Standard Deviation of critical path 2 6.386
1 B C D E F G H I
2 Activity ID Predecessor Optimistic Most Likely Pessimistic Activity Time=(Optimistic+(4*Most Likely)+Pessimistic)/6 Variance=((Pessimistic-Optimistic)/6)^2 Critical activities
3 1 --- 6 12 24 =(D3+(4*E3)+F3)/6 =((F3-D3)/6)^2 Yes
4 2 1 16 19 28 =(D4+(4*E4)+F4)/6 =((F4-D4)/6)^2 Yes
5 3 1 4 7 10 =(D5+(4*E5)+F5)/6 =((F5-D5)/6)^2
6 4 2 21 30 39 =(D6+(4*E6)+F6)/6 =((F6-D6)/6)^2 Yes
7 5 2 17 29 47 =(D7+(4*E7)+F7)/6 =((F7-D7)/6)^2 Yes
8 6 3,4,5 4 7 12 =(D8+(4*E8)+F8)/6 =((F8-D8)/6)^2 Yes
9 7 6 13 15 19 =(D9+(4*E9)+F9)/6 =((F9-D9)/6)^2 Yes
10 Project completion time 85
11 Variance of critical path 1 =H3+H4+H5+H8+H9
12 Variance of critical path 2 =H3+H4+H7+H8+H9
13 Standard Deviation of critical path 1 =SQRT(G11)
14 Standard Deviation of critical path 2 =SQRT(G12)

Network Diagram:

13 | 2 133 이 20 | 0 13 33. 33 |4 | 63 0 30 | 0 33 63 0 0 0 1 13 13 | 01 13 63 6170 0 17 이 63 70 13 43 56. 3 | 20 7143 63. 33

Critical path 1: 1-2-4-6-7

Given, X =98

Thus, Value of Z score = (X- μ)/ Standard Deviation = (98-85)/4.096 = 3.17 (Rounded up to 2 Decimal Numbers)

Thus, using Z table, the probability that the project will complete within 98 =99.92%

Critical path 1: 1-2-5-6-7

Given, X =98

Thus, Value of Z score = (X- μ)/ Standard Deviation = (98-85)/6.386 = 2.04 (Rounded up to 2 Decimal Numbers)

Thus, using Z table, the probability that the project will complete within 98 =97.93%

Add a comment
Know the answer?
Add Answer to:
Given the project information in the following table, what is the probability of completing the National...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Given the project information below, what is the probability of completing the National Holiday Toy project...

    Given the project information below, what is the probability of completing the National Holiday Toy project in 93 time units? Hint: Use the =NORM.S.DIST(z, TRUE) function in Excel to compute the probability. (Carry at least 3 decimal places in all intermediate calculations and the Z value. Enter your final probability answer to 3 decimal places.) Acct. ID Description Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) Activity Time (te) Variance [(b - a)/6]2 Critical ? 1 Design package None 6...

  • What is the probability of completing the National Holiday Toy project in 95 time units? Carry...

    What is the probability of completing the National Holiday Toy project in 95 time units? Carry at least 3 decimal places in all calculations, enter the final value in 3 decimal places. Act. ID Description Predecessor Optm. (a) Most likely (m) Pess. (b) Act time te Variance [(b 2 a)/6]2 Critical 1 Design package None 6 12 24 13 9 x 2 Design product 1 15 19 28 19.83 4.69 x 3 Build package 1 4 7 10 7 1...

  • Using the information provided in the table below, find the probability of completing the project in...

    Using the information provided in the table below, find the probability of completing the project in 44 weeks? Pessimistic Time Estimates Time Estimates (weoks) Optimistic Time Most Likely Immediate PredecessorisEstimate (wooks) Activity ) (weeks) A none A B 12 A C 10 B 12 18 F F D, E 6 D, E G 6 10 H 8 11 G 3 3 H I J

  • 4. For the following project, the expected times and variances for the project activities are given....

    4. For the following project, the expected times and variances for the project activities are given. a. Draw the AON diagram. b. What is the probability of completing the project in 30 time periods? (10 points) Activity ID Predecessor ariance [(b-a)/6) 4 1 2 Naluna 2, 5, 6, 7 Z Value Probability Z Value Probability +0.0 9893

  • It was determined on the following project that the duration for the tasks contained some uncertainty....

    It was determined on the following project that the duration for the tasks contained some uncertainty. After more research, the optimistic and pessimistic values were determined. 1. a. Calculate the expected time and variance (using the 95 percent level of confidence) for each activity. b. Determine the critical path and time for completion c. Calculate the probably that the project will finish in 30 days. Calculate the probably of completing the project in 27 days. Other than the critical path,...

  • 1- Consider the table shown below: Task Predecessor Time (weeks) Expected time Variance of time Optimistic...

    1- Consider the table shown below: Task Predecessor Time (weeks) Expected time Variance of time Optimistic Most likely Pessimistic A - 1 3 5 B A 2 6 10 C B 4 7 10 D B, C 1 2 9 E D 2 4 6 F D,E 4 7 10 G F 1 3 5 a) Calculate expected time and variance for each task.   b) Find the critical path and expected project competition time? c) What is the probability of...

  • You are responsible for managing a project with the following activities (all times are given in...

    You are responsible for managing a project with the following activities (all times are given in weeks): Optimistic Most Likely Pessimistic Immediate Time Predecessor(s) Time Activity Time 4 C, D D, E 12 4 8 6 4 What is the expected time of completion of the project? (weeks) (Include 1 decimal place, e.g.,3.1.) abs What is the probability that the project will be completed in 24 weeks or less? (Provide ab 2 decimal places, no 90 sign, e.g., 2.12 for...

  • Question 1. Activities and activity durations of a Project is given below. (10 points) Find the...

    Question 1. Activities and activity durations of a Project is given below. (10 points) Find the probability of completing the Projcct in 50 weeks b. (10 points) Find the probability of completing the Project in 20 weeks. (10 points) Find the probability of completing the Project in 58 weeks. d. (10 points) Find the probability of completing the Project in 90 weeks. Most Pessimistic Time (weeks) 6 Most Optimistic Time (weeks) Most Probable Previous Activity 2 Activity Time (weeks) 4...

  • The expected times and variances for the project activities follow. Complete the table showing which activities...

    The expected times and variances for the project activities follow. Complete the table showing which activities are critical ID Predecessor te Critical? 1 None 6 Variance 3 4 2. None 22 3 None 4 2 4 Description Pilot production Select channels of distrib. Developmktg program Test market Patent Full production Ad promotion Release 4 1 1 2 5 14 5 6 7 4 10 22 13 2 3 2,5,6,7 B 2 1 ces What is the probability of completing the...

  • 1. Consider the following table providing the needed tasks to completing a successful project. Th...

    1. Consider the following table providing the needed tasks to completing a successful project. The first column provides the name of the task, the second column states the time to complete that task and the third column tells when a task can begin. Task Time to Condition to start task complete #1 #2 #3 #4 #5 #6 #7 #8 #9 #10 #11 #12 #13 #14 #15 #16 #17 #18 #19 7 days None 5 days 8 daysNone 4 days 3...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT