Activity Time=(Optimistic+(4*Most Likely)+Pessimistic)/6
Variance=((Pessimistic-Optimistic)/6)^2
1 | B | C | D | E | F | G | H | I |
2 | Activity ID | Predecessor | Optimistic | Most Likely | Pessimistic | Activity Time=(Optimistic+(4*Most Likely)+Pessimistic)/6 | Variance=((Pessimistic-Optimistic)/6)^2 | Critical activities |
3 | 1 | --- | 6 | 12 | 24 | 13 | 9.00 | Yes |
4 | 2 | 1 | 16 | 19 | 28 | 20 | 4.00 | Yes |
5 | 3 | 1 | 4 | 7 | 10 | 7 | 1.00 | |
6 | 4 | 2 | 21 | 30 | 39 | 30 | 9.00 | Yes |
7 | 5 | 2 | 17 | 29 | 47 | 30 | 25.00 | Yes |
8 | 6 | 3,4,5 | 4 | 7 | 12 | 7 | 1.78 | Yes |
9 | 7 | 6 | 13 | 15 | 19 | 15 | 1.00 | Yes |
10 | Project completion time | 85 | ||||||
11 | Variance of critical path 1 | 16.778 | ||||||
12 | Variance of critical path 2 | 40.778 | ||||||
13 | Standard Deviation of critical path 1 | 4.096 | ||||||
14 | Standard Deviation of critical path 2 | 6.386 |
1 | B | C | D | E | F | G | H | I |
2 | Activity ID | Predecessor | Optimistic | Most Likely | Pessimistic | Activity Time=(Optimistic+(4*Most Likely)+Pessimistic)/6 | Variance=((Pessimistic-Optimistic)/6)^2 | Critical activities |
3 | 1 | --- | 6 | 12 | 24 | =(D3+(4*E3)+F3)/6 | =((F3-D3)/6)^2 | Yes |
4 | 2 | 1 | 16 | 19 | 28 | =(D4+(4*E4)+F4)/6 | =((F4-D4)/6)^2 | Yes |
5 | 3 | 1 | 4 | 7 | 10 | =(D5+(4*E5)+F5)/6 | =((F5-D5)/6)^2 | |
6 | 4 | 2 | 21 | 30 | 39 | =(D6+(4*E6)+F6)/6 | =((F6-D6)/6)^2 | Yes |
7 | 5 | 2 | 17 | 29 | 47 | =(D7+(4*E7)+F7)/6 | =((F7-D7)/6)^2 | Yes |
8 | 6 | 3,4,5 | 4 | 7 | 12 | =(D8+(4*E8)+F8)/6 | =((F8-D8)/6)^2 | Yes |
9 | 7 | 6 | 13 | 15 | 19 | =(D9+(4*E9)+F9)/6 | =((F9-D9)/6)^2 | Yes |
10 | Project completion time | 85 | ||||||
11 | Variance of critical path 1 | =H3+H4+H5+H8+H9 | ||||||
12 | Variance of critical path 2 | =H3+H4+H7+H8+H9 | ||||||
13 | Standard Deviation of critical path 1 | =SQRT(G11) | ||||||
14 | Standard Deviation of critical path 2 | =SQRT(G12) |
Network Diagram:
Critical path 1: 1-2-4-6-7
Given, X =98
Thus, Value of Z score = (X- μ)/ Standard Deviation = (98-85)/4.096 = 3.17 (Rounded up to 2 Decimal Numbers)
Thus, using Z table, the probability that the project will complete within 98 =99.92%
Critical path 1: 1-2-5-6-7
Given, X =98
Thus, Value of Z score = (X- μ)/ Standard Deviation = (98-85)/6.386 = 2.04 (Rounded up to 2 Decimal Numbers)
Thus, using Z table, the probability that the project will complete within 98 =97.93%
Given the project information in the following table, what is the probability of completing the National...
Given the project information below, what is the probability of completing the National Holiday Toy project in 93 time units? Hint: Use the =NORM.S.DIST(z, TRUE) function in Excel to compute the probability. (Carry at least 3 decimal places in all intermediate calculations and the Z value. Enter your final probability answer to 3 decimal places.) Acct. ID Description Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) Activity Time (te) Variance [(b - a)/6]2 Critical ? 1 Design package None 6...
What is the probability of completing the National Holiday Toy project in 95 time units? Carry at least 3 decimal places in all calculations, enter the final value in 3 decimal places. Act. ID Description Predecessor Optm. (a) Most likely (m) Pess. (b) Act time te Variance [(b 2 a)/6]2 Critical 1 Design package None 6 12 24 13 9 x 2 Design product 1 15 19 28 19.83 4.69 x 3 Build package 1 4 7 10 7 1...
Using the information provided in the table below, find the probability of completing the project in 44 weeks? Pessimistic Time Estimates Time Estimates (weoks) Optimistic Time Most Likely Immediate PredecessorisEstimate (wooks) Activity ) (weeks) A none A B 12 A C 10 B 12 18 F F D, E 6 D, E G 6 10 H 8 11 G 3 3 H I J
4. For the following project, the expected times and variances for the project activities are given. a. Draw the AON diagram. b. What is the probability of completing the project in 30 time periods? (10 points) Activity ID Predecessor ariance [(b-a)/6) 4 1 2 Naluna 2, 5, 6, 7 Z Value Probability Z Value Probability +0.0 9893
It was determined on the following project that the duration for the tasks contained some uncertainty. After more research, the optimistic and pessimistic values were determined. 1. a. Calculate the expected time and variance (using the 95 percent level of confidence) for each activity. b. Determine the critical path and time for completion c. Calculate the probably that the project will finish in 30 days. Calculate the probably of completing the project in 27 days. Other than the critical path,...
1- Consider the table shown below: Task Predecessor Time (weeks) Expected time Variance of time Optimistic Most likely Pessimistic A - 1 3 5 B A 2 6 10 C B 4 7 10 D B, C 1 2 9 E D 2 4 6 F D,E 4 7 10 G F 1 3 5 a) Calculate expected time and variance for each task. b) Find the critical path and expected project competition time? c) What is the probability of...
You are responsible for managing a project with the following activities (all times are given in weeks): Optimistic Most Likely Pessimistic Immediate Time Predecessor(s) Time Activity Time 4 C, D D, E 12 4 8 6 4 What is the expected time of completion of the project? (weeks) (Include 1 decimal place, e.g.,3.1.) abs What is the probability that the project will be completed in 24 weeks or less? (Provide ab 2 decimal places, no 90 sign, e.g., 2.12 for...
Question 1. Activities and activity durations of a Project is given below. (10 points) Find the probability of completing the Projcct in 50 weeks b. (10 points) Find the probability of completing the Project in 20 weeks. (10 points) Find the probability of completing the Project in 58 weeks. d. (10 points) Find the probability of completing the Project in 90 weeks. Most Pessimistic Time (weeks) 6 Most Optimistic Time (weeks) Most Probable Previous Activity 2 Activity Time (weeks) 4...
The expected times and variances for the project activities follow. Complete the table showing which activities are critical ID Predecessor te Critical? 1 None 6 Variance 3 4 2. None 22 3 None 4 2 4 Description Pilot production Select channels of distrib. Developmktg program Test market Patent Full production Ad promotion Release 4 1 1 2 5 14 5 6 7 4 10 22 13 2 3 2,5,6,7 B 2 1 ces What is the probability of completing the...
1. Consider the following table providing the needed tasks to completing a successful project. The first column provides the name of the task, the second column states the time to complete that task and the third column tells when a task can begin. Task Time to Condition to start task complete #1 #2 #3 #4 #5 #6 #7 #8 #9 #10 #11 #12 #13 #14 #15 #16 #17 #18 #19 7 days None 5 days 8 daysNone 4 days 3...