Given the project information below, what is the probability of completing the National Holiday Toy project in 93 time units? Hint: Use the =NORM.S.DIST(z, TRUE) function in Excel to compute the probability. (Carry at least 3 decimal places in all intermediate calculations and the Z value. Enter your final probability answer to 3 decimal places.)
Acct. ID | Description | Predecessor | Optimistic (a) | Most Likely (m) | Pessimistic (b) | Activity Time (te) | Variance [(b - a)/6]2 |
Critical ? |
1 | Design package | None | 6 | 12 | 24 | 13 | 9 | x |
2 | Design product | 1 | 17 | 19 | 28 | 20.17 | 3.36 | x |
3 | Build package | 1 | 4 | 7 | 10 | 7 | 1 | |
4 | Secure patent | 2 | 21 | 30 | 39 | 30 | 9 | |
5 | Build product | 2 | 17 | 29 | 47 | 30 | 25 | x |
6 | Paint | 3,4,5 | 4 | 7 | 10 | 7 | 1 | x |
7 | Test market | 6 | 13 | 17 | 19 | 16.67 | 1 | x |
1). The probability of completing the project in 93-time units is______.
*PLEASE SHOW WORK!*
Critical Path using activity time :
Note: Please like the answer, if it is helpful to you. Please mention the reason in the comment section, before disliking. Thank You.......!
Given the project information below, what is the probability of completing the National Holiday Toy project...
Given the project information in the following table, what is the probability of completing the National Holiday Toy project in 98-time units? Hint: Use the =NORM.S.DISTIZ, TRUE) function in Excel to compute the probability (Carry at least 3 decimal places in all intermediate calculations and the Z value. Enter your final probability answer to 3 decimal places.) (b) Acet. ID 1 2 3 4 5 6 7 Description Design package Design product Build package Secure patent Build product Paint Test...
What is the probability of completing the National Holiday Toy project in 95 time units? Carry at least 3 decimal places in all calculations, enter the final value in 3 decimal places. Act. ID Description Predecessor Optm. (a) Most likely (m) Pess. (b) Act time te Variance [(b 2 a)/6]2 Critical 1 Design package None 6 12 24 13 9 x 2 Design product 1 15 19 28 19.83 4.69 x 3 Build package 1 4 7 10 7 1...
Using the information provided in the table below, find the probability of completing the project in 44 weeks? Pessimistic Time Estimates Time Estimates (weoks) Optimistic Time Most Likely Immediate PredecessorisEstimate (wooks) Activity ) (weeks) A none A B 12 A C 10 B 12 18 F F D, E 6 D, E G 6 10 H 8 11 G 3 3 H I J
4. For the following project, the expected times and variances for the project activities are given. a. Draw the AON diagram. b. What is the probability of completing the project in 30 time periods? (10 points) Activity ID Predecessor ariance [(b-a)/6) 4 1 2 Naluna 2, 5, 6, 7 Z Value Probability Z Value Probability +0.0 9893
Question 1. Activities and activity durations of a Project is given below. (10 points) Find the probability of completing the Projcct in 50 weeks b. (10 points) Find the probability of completing the Project in 20 weeks. (10 points) Find the probability of completing the Project in 58 weeks. d. (10 points) Find the probability of completing the Project in 90 weeks. Most Pessimistic Time (weeks) 6 Most Optimistic Time (weeks) Most Probable Previous Activity 2 Activity Time (weeks) 4...
1- Consider the table shown below: Task Predecessor Time (weeks) Expected time Variance of time Optimistic Most likely Pessimistic A - 1 3 5 B A 2 6 10 C B 4 7 10 D B, C 1 2 9 E D 2 4 6 F D,E 4 7 10 G F 1 3 5 a) Calculate expected time and variance for each task. b) Find the critical path and expected project competition time? c) What is the probability of...
PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 3 8 14 B - 8 8 8 C A 6 9 18 D B 6 11 17 According to the data in the above Table: What is the critical path? What is the minimum expected completion time for the project? According to the above Table, there are four activities in the project....
You are responsible for managing a project with the following activities (all times are given in weeks): Optimistic Most Likely Pessimistic Immediate Time Predecessor(s) Time Activity Time 4 C, D D, E 12 4 8 6 4 What is the expected time of completion of the project? (weeks) (Include 1 decimal place, e.g.,3.1.) abs What is the probability that the project will be completed in 24 weeks or less? (Provide ab 2 decimal places, no 90 sign, e.g., 2.12 for...
2. Given the table below (10 pts): A. Draw the project network B. Calculate the expected time to complete each activity as well as the variance (or standard deviation) associated with that time C. Determine the time associated with each potential path and denote the critical path D. Given the calculated data, what is the probability of completing the project in 30 days? 35 days? E. If you were to try to improve your performance (in terms of time), what...
Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A в B C D E, F D G The following table contains the pessimistic, likely, and optimistic estimates for how long activities are estimated to take for Project A. Activity Pessimistic Likely Optimistic 2 5 20 H 16 e. Calculate the time estimates (TE) f. Calculate the variance (s) g. Convert the TE to whole integers and place them in the network diagram for...