Question 1. Activities and activity durations of a Project is given below. (10 points) Find the probability of completing the Projcct in 50 weeks b. (10 points) Find the probability of completing the Project in 20 weeks. (10 points) Find the probability of completing the Project in 58 weeks. d. (10 points) Find the probability of completing the Project in 90 weeks. Most Pessimistic Time (weeks) 6 Most Optimistic Time (weeks) Most Probable Previous Activity 2 Activity Time (weeks) 4...
Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A в B C D E, F D G The following table contains the pessimistic, likely, and optimistic estimates for how long activities are estimated to take for Project A. Activity Pessimistic Likely Optimistic 2 5 20 H 16 e. Calculate the time estimates (TE) f. Calculate the variance (s) g. Convert the TE to whole integers and place them in the network diagram for...
Using Table 2.13 below, if the expected time for activity E is changed to nine weeks, by how many weeks will the project's expected completion time increase? Table 2.13 (All activity times for the project are in weeks.) Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessors(s) A 3 4 5 --- B 5 7 9 --- C 2 3 10 A D 2 5 8 B E 1 7 7 B F 3 5 7 CD G 7...
Given the information below, what is the probability that the critical path will be completed in 25 weeks? Time Estimates (Weeks) Activity Optimistic Most Likely Pessimistic IP A 1 4 7 None B 5 6 7 None C 2 4 6 B D 4 16 10 A E 4 6 14 A, C F 6 8 16 B G 1 5 9 D,E,F The probability is less than 0.25. The probability is between 0.5 to 0.75. The probability is between...
(50 points) Data regarding the activities for a project are presented below. The times are in weeks The critical path for this project is A-D-H-I-J-K 2. Pessimistic Time Most Likely Time y Optimistic Time 8 16 10 8 10 12 8 14 5 6 2 a. Determine the standard deviation of the critical path. b. Determine the probability of completing the project in 38 weeks or less c What is the probability of completing the project in 32 weeks or...
QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questions 1-15. The expected activity completion times are provided in days. Each question is 1 point. Most Probable Activity Optimistic Pessimistic A 7 B 12 C 5 12 7 E 10 15 20 6 9 18 G 6 13 H 11 What is the early start (ES) time for activity F? 13 12 10 None of the above are...
Given the project information below, what is the probability of completing the National Holiday Toy project in 93 time units? Hint: Use the =NORM.S.DIST(z, TRUE) function in Excel to compute the probability. (Carry at least 3 decimal places in all intermediate calculations and the Z value. Enter your final probability answer to 3 decimal places.) Acct. ID Description Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) Activity Time (te) Variance [(b - a)/6]2 Critical ? 1 Design package None 6...
Activity Predecessor Optimistic time Most likely time Pessimistic time A - 3 5 8 B - 4 6 10 C A,B 2 5 8 D B 3 5 9 E A,C 3 6 9 F C,E 1 3 5 G C,D 3 4 9 H D 4 6 10 I F,G 3 4 9 J H 2 4 6 A).Draw the project network b).what is the expected completion time of the project. c) after your calculation, if you find one...
1- Consider the table shown below: Task Predecessor Time (weeks) Expected time Variance of time Optimistic Most likely Pessimistic A - 1 3 5 B A 2 6 10 C B 4 7 10 D B, C 1 2 9 E D 2 4 6 F D,E 4 7 10 G F 1 3 5 a) Calculate expected time and variance for each task. b) Find the critical path and expected project competition time? c) What is the probability of...
The following table shows estimates of activity times (weeks) for a project: Activity Optimistic Time Most Probable Time Pessimistic Time A 3 4.5 9 B 1.5 2 2.5 C 5 6 7 D 4 4.5 8 E 5 6 7 F 1 2.5 7 G 7 9 11 Suppose that the critical path is A-B-D-F-G. Use Appendix A to answer the questions. Do not round intermediate calculations. Round your answers to three decimal places. What is the probability that the...