Question

Check my word 1 You have prepared the following schedule for a project in which the key resource is a tractor. There are thre
Check my work 1 Use the following order of heuristics: 1. Minimum slack, 2. Smallest duration, 3. Lowest identification numbe
How long will the resource-constrained project take? time periods. k List the order in which you scheduled the activities of
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1)

If it was NOT resource-constrained, the project will take = 8 time periods

2)

Gantt chart and resource loading chart before resource leveling, is following:

Gantt chart based on Early Start and Finish times ID RES DURES LF SL 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 11 203 1 1 1 2 2 3 0

Activities 3 and 5 need to be rescheduled , in order to limit the resource usage up to 3  

Resulting Gantt chart and resource loading chart is following:

8 14 Gantt chart based on resource constraint ID RES DURES LF SL 11 2 3 4 5 6 7 9 10 11 12 13 15 1 1 2 03 1 1 1 2 2 3 0 3 0 2

We see that duration of the project increased from 8 to 9 time periods.

Order in which we scheduled the activities of the resource-constrained project.

First 2
Second 1
Third 3
Fourth 4
Fifth 5
Sixth 6
Add a comment
Know the answer?
Add Answer to:
Check my word 1 You have prepared the following schedule for a project in which the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You have prepared the following schedule for a project in which the key resource is a...

    You have prepared the following schedule for a project in which the key resource is a backhoe. This schedule is contingent on having four backhoes. You receive a call from your partner, Brooker, who desperately needs one of your backhoes. You tell Brooker you are willing to let him have the backhoe if you are still able to complete your project in 13 months. Develop a resource schedule to see if it is possible to complete the project in 13...

  • EX8-4 (Algo) You have prepared the following schedule... You have prepared the following schedule for a...

    EX8-4 (Algo) You have prepared the following schedule... You have prepared the following schedule for a project in which the key resource is a tractor. There are three tractors available to the project. The resource requirements are as shown in the diagrams below. Develop a resource-constrained schedule. Use the parallel method and heuristics given. Be sure to update each period as the computer would do. Legend ESIDER SUK RES SUK U DURU 106 12 OO 5510 0155 5 5 Use...

  • You have prepared the following schedule for a project in which the key resource is a...

    You have prepared the following schedule for a project in which the key resource is a backhoe. This schedule is contingent on having 3 backhoes. You receive a call from your partner, Brooker, who desperately needs 1 of your backhoes. You tell Brooker you would be willing to let him have the backhoe If you are still able to complete your project in 11 months. Develop a resource schedule in the loading chart that follows to see if it is...

  • Plan ME Develop a loading schedule for each resource below. (Figure 8.3) EE ME 0 1...

    Plan ME Develop a loading schedule for each resource below. (Figure 8.3) EE ME 0 1 2 3 4 5 6 7 8 9 10 11 12 Fill in the times below for a resource activity schedule. ID/RES ES LSEF LF SL 1-EE Schedule 2.EE Legend ES ID EF 3-ME SL LS DUR LF 4.EE 5-ME 6-ME 7-EE Resource EX8-1 (Static) Given the network plan that... Given the network plan that follows, compute the early, late, and slack times. What...

  • Below is the network diagram for a construction project. Given ONLY THREE (3) workers are available...

    Below is the network diagram for a construction project. Given ONLY THREE (3) workers are available at all times, develop a resource schedule using the parallel heuristics for resource-constrained projects. 0 A 1 1 2 1 1 1 2 4 E 7 0 0 4 3 7 IN نا 7 G 2 c 4 3 0 2 24 1 ON 0 7 00 000 7 1 4 1 F 1 0 B 2 02 o 0 2 2 N ON...

  • Part 2 Remember the old saying, “A project plan is not a schedule until resources are...

    Part 2 Remember the old saying, “A project plan is not a schedule until resources are committed.” This exercise illustrates this sometime subtle, but important point. Using your files from Part 1, input resources and their costs if you have not already done so. All information is found in Tables A2.1 and A2.2. Prepare a memo that addresses the following questions: 1. Which if any of the resources are overallocated? 2. Assume that the project is time constrained and try...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • 1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 20...

    1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 200 | 1200 | 500 | 700 | 1200 | 800 | 1800 | 1500 | 400 (a) Construct the activity-on-node (AoN) network for the relations among the activities in the (b) Using the activity-on-node (Ao) network developed in part (a), determine the critical path and the minimum time required to complete the project. Develop the earliest start and finish times, the latest finish...

  • 1 According to the project plan, a contractor is scheduled to deliver some software components today...

    1 According to the project plan, a contractor is scheduled to deliver some software components today afternoon. A regular payment is due to be made to this contractor tomorrow. You and your project team received a note this morning informing you that the software delivery will be delayed by 2 weeks. What should you do right now? a You should delay the payment for two weeks b You must immediately find a different contractor c You should conduct a meeting...

  • You have recently been hired to help with planning for a music festival in Sydney, Australia...

    You have recently been hired to help with planning for a music festival in Sydney, Australia planned for late December 2020. Much still needs to be done in order for the event to go ahead. As the project manager working with the city, you are tasked with determining whether it is feasible to put on the event by the proposed date. The following activities would have to be undertaken before the festivities. Immediate Predecessor Activity A B С D E...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT