Question

EX8-4 (Algo) You have prepared the following schedule... You have prepared the following schedule for a project in which the
Use the following order of heuristics: 1. Minimum slack, 2. Smallest duration, 3. Lowest identification number ID Resource Du
image.png
How long will the resource-constrained project take? time periods. List the order in which you scheduled the activities of th
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Gantt chart and Resource loading chart based on Earliest Start time is following:

ID 3 4 Gantt chart based on earliest start time RES DURE LS EF LF Slack 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 4 0 1 4 5 1 2 5

In the resource loading diagram, we see that resource usage in TP 5,6,7,8 exceeds the available resources, which is 3 .

The resource over-allocation is because of parallel occurrence of tasks 3,4 and 5

Tasks 3 and 5 have slack of 2 TPs. each. So tasks 3 and 5 have to be rescheduled.

After rescheduling tasks 3 and 5, the resulting Gantt chart and resource loading profile based on resource constraint is following:

Gantt chart based on resource-constraint ID RES DUR E LS EF LF Slack 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 140 145 1 2 2 5 0 0

If NOT resource-constrained, project will take : 12 time periods

Resources-constrained project will take :   14 time periods

Order in which activities are scheduled are:

First 2
Second 1
Third 3
Fourth 4
Fifth 5
Sixth 6



Add a comment
Know the answer?
Add Answer to:
EX8-4 (Algo) You have prepared the following schedule... You have prepared the following schedule for a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Check my word 1 You have prepared the following schedule for a project in which the...

    Check my word 1 You have prepared the following schedule for a project in which the key resource is a tractor. There are three tractors available to the project. The resource requirements are as shown in the diagrams below. Develop a resource-constrained schedule. Use the parallel method and heuristics given. Be sure to update each period as the computer would do. ts SESSE DURU FEE eBook 1 eferences Use the following order of heuristics: 1. Minimum slack, 2. Smallest duration,...

  • You have prepared the following schedule for a project in which the key resource is a...

    You have prepared the following schedule for a project in which the key resource is a backhoe. This schedule is contingent on having four backhoes. You receive a call from your partner, Brooker, who desperately needs one of your backhoes. You tell Brooker you are willing to let him have the backhoe if you are still able to complete your project in 13 months. Develop a resource schedule to see if it is possible to complete the project in 13...

  • You have prepared the following schedule for a project in which the key resource is a...

    You have prepared the following schedule for a project in which the key resource is a backhoe. This schedule is contingent on having 3 backhoes. You receive a call from your partner, Brooker, who desperately needs 1 of your backhoes. You tell Brooker you would be willing to let him have the backhoe If you are still able to complete your project in 11 months. Develop a resource schedule in the loading chart that follows to see if it is...

  • Plan ME Develop a loading schedule for each resource below. (Figure 8.3) EE ME 0 1...

    Plan ME Develop a loading schedule for each resource below. (Figure 8.3) EE ME 0 1 2 3 4 5 6 7 8 9 10 11 12 Fill in the times below for a resource activity schedule. ID/RES ES LSEF LF SL 1-EE Schedule 2.EE Legend ES ID EF 3-ME SL LS DUR LF 4.EE 5-ME 6-ME 7-EE Resource EX8-1 (Static) Given the network plan that... Given the network plan that follows, compute the early, late, and slack times. What...

  • Below is the network diagram for a construction project. Given ONLY THREE (3) workers are available...

    Below is the network diagram for a construction project. Given ONLY THREE (3) workers are available at all times, develop a resource schedule using the parallel heuristics for resource-constrained projects. 0 A 1 1 2 1 1 1 2 4 E 7 0 0 4 3 7 IN نا 7 G 2 c 4 3 0 2 24 1 ON 0 7 00 000 7 1 4 1 F 1 0 B 2 02 o 0 2 2 N ON...

  • CME403/603 Scheduling and Project Control (10 pts PDM) For the following PDM schedule, manually perform CPM...

    CME403/603 Scheduling and Project Control (10 pts PDM) For the following PDM schedule, manually perform CPM calculation to show items as on legend (key) node - ES, EF, LS, LF, TF, SF and FNF. Highlight critical path(s). 2. 25 8 8 D 11 | 42 46 34 42 3 8 1 3 B 10 C T 16 10 18 29 40 37 Start Finis h 2 0 0 9 12 37 G 24 10 12 4 Legend ES Activity N...

  • Consider a project with the following information: Activity Duration Predecessors A 5 -- B 7 A...

    Consider a project with the following information: Activity Duration Predecessors A 5 -- B 7 A C 9 B D 5 B E 7 C, D F 6 D G 4 C H 7 E, F, G Activity Duration ES EF LS LF Float A 5 0 5 0 5 B 7 5 12 5 12 C 9 12 21 12 21 D 5 12 17 16 21 E 7 21 28 21 28 F 6 17 23 22 28...

  • Consider the following project where times are in weeks. Activity Duration Immediate Predecessors A B с...

    Consider the following project where times are in weeks. Activity Duration Immediate Predecessors A B с D E F G H A.B B A с E,F 8 12 7 4 2 3 7 3 DF a) Determine the activity schedule (ES, EF, LS, and LF) as well as slack using the information from the table above (11 marks) b) Determine all the possible paths of this project and determine the shortest possible time this project can be completed? (4 marks)...

  • Megah Holding Sdn. Bhd is in progress to start their housing project. The list of activity...

    Megah Holding Sdn. Bhd is in progress to start their housing project. The list of activity and scheduled of the project is proposed as in Table 1. If the indirect costs for each duration is as follows, compute the direct and total cost for each duration. What is the optimum cost-time schedule? Indirect cost 27 weeks – RM 350 26 weeks – RM 270 25 weeks – RM 160 24 weeks – RM 100 12 weeks – RM 70 (12...

  • Question E (8 points): 1. Construct an EDF schedule with HVDF scheduling policy for the following...

    Question E (8 points): 1. Construct an EDF schedule with HVDF scheduling policy for the following tasks. What is the total value obtained? Ti-(cipi): T (6,24); T2- (4, 8); T3- (4, 8); T4- (4, 12). The values of these tasks are 2, 3, 1, and 2 respectively. Note: Schedule tasks based on deadline as the primary criteria for priority assignment (EDF); if there is a tie in priority, then choose the task with HVDF (High Value Density First) basis. 2....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT