Question

Project 1 Project 2 Year o Year 1 Year 2 Year 3 IRR -10000 3500 3500 4500 7.0% -10000 1000 2000 8500 5.4% Project 3 -10000 90

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Q5)

For any Project / Major CAPEX evaluations, the three most common approaches are Payback period, Internal rate of return (IRR) and Net Present Value (NPV).

The payback period determines how long it would take a company to see enough in cash flows to recover the original investment.

The internal rate of return (IRR) calculates the percentage rate of return at which those same cash flows will result in a net present value of zero. It used to determine the attractiveness of the Project on the given amount of the value of the investment.

The Net Present Value (NPV) results in the total net cash inflows expected from a project at the present value using a discounting factor. This is used to quantify the results in value terms from the entire project, covering all the cashflows from the project.

While most of the times NPV and IRR result in the same outcome on the feasibililty of the Project, there shall be cases of conflicting opinions as well;

Incase of analysis of a single conventional project, both NPV and IRR might provide same indicator on the evaluation of the project or not. However, while comparing two projects, the NPV and IRR may provide conflicting results.

Also, incase of mutiple cash flows trends (positive, negative, positive, negative etc) during the Project period, the IRR fails to provide answer and in this case NPV shall be useful as it covers all the cashflows - either Positive or Negative.

However, incase of projects with different investment during their year 0, the IRR provides the better options to choose among the projects based on the threshold limit of the investment budget available.

Q6) Incase of the the projects with equal investment value and lives, the IRR with higher value shall be ranked as priority for invesment with decreasing priority along with the next higher IRR values, in the choice of options.

Q7) Based on the given projects IRR, the IRR of Project 3 is higher and the same need to be funded first.

Q8) Project 2 and Project 1 are with the lower IRRs among the given five projects; Hence, if there is a capital budget limit of $ 30000, then Project 2 and Project 1 should NOT be selected;

Q9) Althought the Projects 2, 3 and 4 have same values, the timing of cash flows determine the value of the IRR; Incase of Project 3, the amount of $ 9000 (higher cash flow amount all the three years) received in the Year 1 only, resulting in the higher IRR. Time value of money is considered.

Q 10) Although the Project 5 is recovering the least amount of cash flows as compared to rest of the projects the timing of receipt of cash flow ($ 11000 during Year 1 itself) is very important factor. No other project is having such higher cash flow during Year 1 and if you can obseve, this timing of receipt of cashflow has resulted in higher IRR of 10% and this is much higher than other Projects 1,2 & 4. Hence, this project can be funded as a next priority to Project 3.

Add a comment
Know the answer?
Add Answer to:
Project 1 Project 2 Year o Year 1 Year 2 Year 3 IRR -10000 3500 3500...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Using the NPV rule, which of the following projects should a firm undertake if it can...

    Using the NPV rule, which of the following projects should a firm undertake if it can invest $25000. Year   Project A   Project B   Project C 0 -9000 -1200 -18200 1 2000    5000 0 2    5000 4000 5000 3 1000 6000 10000 4 4000 2000 12000 Group of answer choices A. A B. C C. B D. A and B

  • You have 3 projects with the following cash flows: O Year Project 1 Project 2 -...

    You have 3 projects with the following cash flows: O Year Project 1 Project 2 - $149 $21 $42 4 $79 -6,500 - 246 0 0 $58 6,996 81 - 826 20 41 58 a. For which of these projects is the IRR rule reliable? b. Estimate the IRR for each project (to the nearest 1%). c. What is the NPV of each project if the cost of capital is 5%? 20%? 50%? b. Estimate the IRR for each project...

  • For each of the following projects determine the NPV of each one (provide your answer), and rank them. Then, determine w...

    For each of the following projects determine the NPV of each one (provide your answer), and rank them. Then, determine which of the following projects should a firm undertake if it can invest $25000. Please use a WACC of 11%. Turn your answer in to the drop folder provided.    You will receive 1 point for the correct NPV, Ranking and Recommendation. Year Project A Project B Project C 0 -9000 -12000 -18200 1 2000 5000 0 2 5000 4000 5000...

  • 1. A. Which of the following mutually exclusive projects should be accepted? Project NPV Payback IRR...

    1. A. Which of the following mutually exclusive projects should be accepted? Project NPV Payback IRR A +42,176 2 years, +$10,500 16.4% B +39,090 2 years, +9,670 15.8% C +41,894 3 years, +16,620 13.2% D +43,778 3 years, +11,625 14.9% E +38,952 2 years, +15,475 15.9% B. What is the Payback Period of a project with an initial cost of $75,000, Year 1 cash flow of $20,000 which increases by 5% each year? If the Payback cutoff is 3 years,...

  • Qs assignment - The Basics of Capital Budgeting Year Year 1 Year 2 Year 3 Year 4 Cash Flow $300,000 $425,000...

    Qs assignment - The Basics of Capital Budgeting Year Year 1 Year 2 Year 3 Year 4 Cash Flow $300,000 $425,000 $475,000 $450,000 Which of the following is the correct calculation of project Sigma's IRR? 24.54% 30.00% 28.63% 27.27% If this is an independent project, the IRR method states that the firm should reject project Sigma If mutually exclusive projects are proposed that both have an IRR greater the accept: the IRR method states that the firm should accept project...

  • QUESTION 2 Suppose that you consider the following project. Year 0 3000 Year 1 -1000 Year...

    QUESTION 2 Suppose that you consider the following project. Year 0 3000 Year 1 -1000 Year 2 -1000 Year 3 -2000 Do the IRR rule and the NPV rule generate the same results? Assume a 10% discount rate. A. Yes B.NO OCNA O D.NA

  • Q 1 Project A has an IRR of 23.4%. Project B has an IRR of 33.1%....

    Q 1 Project A has an IRR of 23.4%. Project B has an IRR of 33.1%. The firm's cost of capital is 18%. Now you are told that the cash flows of the two projects are as shown below. Which project is better, A or B, or can't you tell? Period 0 Period 1 Period 2 Period 3 IRR Project A -500 +250 +250 +250 23.4% Project B -200 +115 +115 +115 33.1% Question options: 1- Project A is better...

  • A firm evaluates all of its projects by applying the IRR rule. Year © 1 2...

    A firm evaluates all of its projects by applying the IRR rule. Year © 1 2 3 Cash Flow -$157,000 59,000 80,000 64,000 What is the project's IRR? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) Internal rate of return If the required return is 15 percent, should the firm accept the project? (Click to select)

  • Year Project A Project B 0 -425,000 -500,000 1 200,000 280,000 2 210,000 220,000 3 175,000...

    Year Project A Project B 0 -425,000 -500,000 1 200,000 280,000 2 210,000 220,000 3 175,000 180,000 4 175,000 180,000 5 175,000 180,000 Use the IRR approach to determine which project to choose. Graph the NPV profiles for each project. At what rate will the two projects have the same NPV?

  • 20. You have 3 projects with the following cash flows: Year 0 1 2 3 Proient...

    20. You have 3 projects with the following cash flows: Year 0 1 2 3 Proient Project 1 -150 20 40 60 80 Project 2 -825 0 0 7000 -6500 Project 3 20 40 60 80 -245 a. For which of these projects is the IRR rule reliable? b. Estimate the IRR for each project to the nearest 1%). c. What is the NPV of each project if the cost of capital is 5%? 20%? 50%?!

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT