Answer:
The correct answer is “C. 15”.
As shown in the below “Gantt chart” the duration of project is “15”.
For the network shown in the figure above what is the project? duration?
Q4 The network diagram of a project is shown below E.4 B.3 G.5 D.5 A.7 F.2 C.4 (a) Use two-pass method to determine the critical path. (3 points) (b) What is the project duration? ( points) (c) What is the slack time of activity F? ( points) Q4 The network diagram of a project is shown below E.4 B.3 G.5 D.5 A.7 F.2 C.4 (a) Use two-pass method to determine the critical path. (3 points) (b) What is the project...
QUESTION 14 A firm is planning a project for the development of a new product. The network of activities and data are shown follow. Time Immediate Activity (weeks) Predecessor 2 5 В 4 C 5 В 6 В.С D,E F What are the slack times of Activities D and E? 0 and 0, respectively 1 and 1, respectively 2 and 0, respectively 0 and 1, respectively 1 and 0, respectively shown follow. A firm is planning a project for the...
2- Consider the AON network illustrated below: B G H A F Activity A B с D E F Duration 5 3 7 6 2 3 4 5 H a) Calculate the project completion time b) What is the critical path? c) Calculate the slack time for each activity.
QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questions 1-15. The expected activity completion times are provided in days. Each question is 1 point. Most Probable Activity Optimistic Pessimistic A 7 B 12 C 5 12 7 E 10 15 20 6 9 18 G 6 13 H 11 What is the early start (ES) time for activity F? 13 12 10 None of the above are...
To In the figure above, A=33, B=24,C=18, D=9, E-13, F-15, G=19, H=21. Tau In the figure above, A=33, B-24, C=18, D=9, E-13, F=15, G=19, H-21. If the government auctions off the quota licenses, what is the maximum amount of revenue it could raise?
Use a PERT network to establish the expected duration for the project described in the table below: (SHOW the PERT NETWORK) Activity Predecessors Duration a m b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400 600 D B, C 4 6 8 200 600 E B, C 6 9 12 400 300 F C 4 6 14...
A network for a project is shown below. Activity times, in days, are indicated by the figure that appears under the activity. 3 6 6 5 2 3 6 8 10 2 3 5 2 2 3 2 (i) Analyze the network and determine the earliest and latest EVENT times and the duration of the project.
Given is a CPM project network diagram as shown below. A F Start E H End B D G Start H Activity day А 6 B 3 с 8 D 7 E 4 F 9 G 4 End 0 0 6 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G - days. c) The Latest Finish time, LF, of Acitivity - dayy d) The critical activities are (ex. Fill in answer as: ABCD)
Q1: Use the network below to answer the following questions: D 7 G 8 E 5 C H 10 F 3 B 3 i. ii. Assume the duration is given in weeks(numbers shown above), how long will it take to finish this project? Show your work. (4 marks) Determine the critical path. (1 mark) List the activities that could be delayed without affecting the submission of the project and determine the duration of this delay ( 1 Marks) iii.