Question

Problem 5-5 Your project to obtain charitable donations is now 41 days into a planned 51-day project. The project is divided
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

Activity Budgeted Revenue Planned completion Actual completion Planned Value = (Budgeted Revenue * Planned completion) Earned Value = (Budgeted Revenue * Actual Completion)
1 25,700 100% 90% 25,700 23,130
2 150,700 83% 54% 125,081 81,378
3 51,400 0% 0% 0 0
Total Planned Value = $150,781 Total Earned Value = $104,508
Schedule Variance = Total Earned Value - Total Planned Value 104,508 -150,781 = -$46,273 Actual cost of work =178,000
Schedule Performance Index = Total Earned Value/Total Planned value 104,508/150,781 = 0.6931112
Cost variance = Total Earned Value - Actual Cost of work 104,508 - 178,000 = -$73,492
Cost performance index = Total Earned Value / Actual cost of work 104,581/178,000 = 0.5871236
Add a comment
Know the answer?
Add Answer to:
Problem 5-5 Your project to obtain charitable donations is now 41 days into a planned 51-day...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Your project to obtain charitable donations is now 43 days into a planned 53-day project. The...

    Your project to obtain charitable donations is now 43 days into a planned 53-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 37 days of the project and to bring in $25,900. Even though we are 43 days into the project, we still see that we have only 89% of this activity complete. The second activity relates to company donations and is scheduled to...

  • Problem 5-5 Your project to obtain charitable donations is now 38 days into a planned 48-day...

    Problem 5-5 Your project to obtain charitable donations is now 38 days into a planned 48-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 33 days of the project and o bring in S25 300. ven though we are 38 days to the pro ect we stil see hat we have only 8 % of his activity complete. The second activity relates company donations...

  • Problem 5-5 Your project to obtain charitable donations is now 40 days into a planned 50-day...

    Problem 5-5 Your project to obtain charitable donations is now 40 days into a planned 50-day project. The project is divided into activities. The first activity is designed to solo individual dortions, it is sched project and to bring in $25,600. Even though we are 40 days into the project, we still see that we have only 92% of this activity complete. The second ye s to company donanons and is on day 5 and extending through day 45. We...

  • For a project, in X day, planned value, earned value and actual cost of the tasks...

    For a project, in X day, planned value, earned value and actual cost of the tasks are given in dollar in the table below. Planned $1000 to complete project. Task Actual Cost Work Performed Budgeted Cost Work Scheduled 50 70 30 100 50 2 3 4 5 Budgeted Cost Work Performed 50 70 30 50 0 Total: 250 a. Find schedule and cost variance. Explain what it means? b. Find schedule and cost performance index. c. Find estimate to complete...

  • Problem 5-6 A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the...

    Problem 5-6 A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 70% complete. The planners were only expecting to be 57% through the third activity at this time. The first activity involves prepping the site for the bridge. It was...

  • 2 Problem 5-6 (Algo) A project to build a new bridge seems to be going very...

    2 Problem 5-6 (Algo) A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 65% complete. The planners were expecting to be only58 % through the third activity at this time. The first activity involves prepping the site for the bridge....

  • At week 10 of a project below to improve distance learning platform, assume that the planned...

    At week 10 of a project below to improve distance learning platform, assume that the planned values (PV) are based on time proportionality but the “% Complete” values for earned values (EV) are from the workers actually doing the tasks. ACTIVITY PRE- DECESSORS DURATION (WEEKS) BUDGET ($) ACTUAL COST ($) % COMPLETE A - 5 500 640 100 B A 3 300 400 100 C B 4 320 310 80 D B 6 600 250 60 E C,D 3 300...

  • Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days...

    Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...

  • 2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate....

    2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...

  • NO EXPLANATION NEEDED, JUST ANSWER. A senior manager is in the process of selecting a project...

    NO EXPLANATION NEEDED, JUST ANSWER. A senior manager is in the process of selecting a project manager for a new initiative that is very important for the company’s future. What is the key factor in choosing a project manager? The project manager should be the most technically competent person on the team The PM works well with various levels of management The project manager should be the functional manager of the most people on the team The project manager must...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT