Question

Question 17 (2 points) (17-18) The following table shows a computer manufacturers overall production process information for
Question 18 (2 points) 18. Refer to the previous question. Calculate the utilization rate of Operation A relative to the maxi
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

Question 17:d) 490

Operation C is the bottleneck process of the system with minimum capacity among all operations.

Max Capacity of the Process= Max Capacity of Bottleneck Process (Operation C) = 490

Question 18: a) 75%

Utilization Rate of A = 100*Actual Output/Max Possible Output = 100*420/560 = 75%

Add a comment
Know the answer?
Add Answer to:
Question 17 (2 points) (17-18) The following table shows a computer manufacturer's overall production process information...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 17 (2 points) (17-18) The following table shows a computer manufacturer's overall production process information...

    Question 17 (2 points) (17-18) The following table shows a computer manufacturer's overall production process information for last month. The overall production sequence is A -> B-C -> D. Some operations (A and C) use only a single machine, while the other operations (B and D) use multiple machines that perform the same job simultaneously. Operation Machine A Maximum capacity of each machine (units/hour) 560 140 112 210 175 490 266 329 A1 B1 B2 B3 B4 C1 D1 D2...

  • Problem 2 (5 pts) Use the process Information provided in the following table, when the sequence...

    Problem 2 (5 pts) Use the process Information provided in the following table, when the sequence of flow is B (any machine can be used if available) → C D (any machine can be used if available). → Operation Number of Units of Equipment Design Capacity (by equipment) 240 units/hr 130, 120, 160, 110 250 units/hr 140, 95 Planned Utilization (overall) 57.5% 82.0% 77.0% 62.5% Calculate the maximum (design) capacity of the entire process and effective capacity of the entire...

  • Question 8 5 pts Use the process information provided in the following table, when the sequence...

    Question 8 5 pts Use the process information provided in the following table, when the sequence of flow i B (any machine can be used if available) C D (any machine can beused if available Number of Units of Equipment Design Capacity (by equipment) Planned Utilization (overall) Operation 210 units/hr 160, 150,190, 140 units/hr 220 units/hr 110, 240 95.0% 80.0% 85.0% 830% 4 2 Calculate the maximum (design) capacity and effective capacity Which of the following gives the right values...

  • Question 6 Which of the statements below best describe peak capacity: A. The process is run...

    Question 6 Which of the statements below best describe peak capacity: A. The process is run to the maximum production limit B. Is not sustainable for a long period of time C. The longer an operation performs at peak capacity the higher the probability a failure or error in the process will occur D. All the above.

  • Problem 3. The figure below shows a typical process chart. a. Complete the summary (top right)...

    Problem 3. The figure below shows a typical process chart. a. Complete the summary (top right) portion of the chart. b. Step 1 takes 2.5 minutes, so the maximum number of units that can be processed is 60/2.5 24 per hour. Step 2 takes 2.0minutes, so the maximum output is 30 per hour. By going similarly through each step, determine the maximum output of the whole process (this is the bottleneck). Assume the process variable cost is $25 each time...

  • A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation...

    A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). Q 2.5 units.hr 1.8 units/hr Assembly a Sawing 0.8 units/hr Sanding Welding 5 units/hr Assembly 0.8 units/hr Driling 5 units.hr Assembly 0.8 units/hr a) Sanding is the bottleneck b) The bottleneck...

  • A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation...

    A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). Q 2.5 units/hr Sawing 2.1 units/he Sanding Assembly 0.8 unitsthe Welding 6 units.hr Assembly 0.8 units Drilling 5 unitshe Assembly 0.8 untui is the bottleneck 0.7 units/hr a) Drilling is the...

  • QUESTION 2 The table below shows the total production of a firm as the quantity of...

    QUESTION 2 The table below shows the total production of a firm as the quantity of labor employed increases. The quantities of all other resources employed remain constant. Units of labor Total production Marginal product of labor (MP) Average product of labor (AP) 80 200 400 450 480 490 480 a. Compute the marginal products of the first through the eighth units of labor and enter them in the table. b. Now compute the average products of the various quantities...

  • (Process with Rework) Consider the following three-stage production process of glass ceramics, wh...

    Matching supply with Demand (3rd Edition) - Question 10.2 (Process with Rework) Consider the following three-stage production process of glass ceramics, which is operated as a worker-paced line. Q10.2 Components 6 min./unit 5 min./unit min. /unit Finished Units Rework The process is experiencing severe quality problems related to insufficiently trained work- ers. Specifically, 20 percent of the parts going through operation 1 are badly processed by the operator. Rather than scrapping the unit, it is moved to a highly skilled...

  • just 18 please! For questions 1-30, please enter your answers on the scan sheet provided (Blue...

    just 18 please! For questions 1-30, please enter your answers on the scan sheet provided (Blue side) and ONLY use pencil. For questions 31-34, use separate sheet(s) and make sure your NAME is on sheets to be handed in. 17. In a job order cost system, a credit to Manufacturing Overhead will be accompanied by a debit to A) Cost of Goods Manufactured. B) Finished Goods Inventory. CWork in Process Inventory Dy Raw Materials Inventory. 18) In a process cost...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework