Question

Question 85 There are various similarities between the CPM and PERT methods. Which of the following is not one of those similQuestion 78 How many paths are there in the following project precedence network? B A E D O a. 6 ob.9 C. 8 od. 7

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Question 85:

Answer: d)

CPM uses Single time estimate i.e. there is no variance in estimating the time element whereas PERT uses Three time estimate. It may be Beta or Triangular time estimate which means it has characteristics of Variance, Std. Deviation and Mean expected time.

Question 78:

Answer: b)

The paths are:

A-B-E-F-I

A-B-E-G-I

A-B-E-H-I

A-C-E-F-I

A-C-E-G-I

A-C-E-H-I

A-D-E-F-I

A-D-E-G-I

A-D-E-H-I

-----------------------------------------------------------------------------------------------------------------------

In case of any doubt, please ask through the comment section before Upvote/downvote.

If you liked the answer, please give an upvote. This will be quite encouraging for me, thank-you!!!

Add a comment
Know the answer?
Add Answer to:
Question 85 There are various similarities between the CPM and PERT methods. Which of the following...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 11. In CPM/PERT, an activity that is on the critical path A. has equal values for...

    11. In CPM/PERT, an activity that is on the critical path A. has equal values for "Latest Start" and "Earliest Start" ( LS = ES ) B. has equal values for "Latest Finish" and "Earliest Finish" ( LF = EF ) C. is used in calculating total project duration D. has slack equal to zero E. all of the above 12. In CPM/PERT, the critical path through the network A. will require the most time of any path B. will...

  • Given all the information in the table, use PERT/CPM to help Mr. Hawthorne address to the...

    Given all the information in the table, use PERT/CPM to help Mr. Hawthorne address to the following questions. A. Create the network diagram representing the problem. B. What is the total time expected to be required to complete the project if no delays occur? C. What are the earliest and latest start and finish times for the individual activities required to meet the expected project completion time provided in question B (show your method for determining this)? D. Which are...

  • Please the question consists of (a) , (b) and (c). I need the crashing part which is the (c) than everything. Is ver...

    Please the question consists of (a) , (b) and (c). I need the crashing part which is the (c) than everything. Is very urgent Question 7 The Family Entertainment Group is about to begin the production of its most Ebo Whyte, ensive) movie of the year. The movie's producer, Mr. project. He has identified the eight major activities (labe and H) rcquired to produce the movie. Activities weeks respectively, cannot start until activity A completed. Activities E and F tak...

  • QUESTION 9 Consider the following project; for which activities is it possible that the slack can...

    QUESTION 9 Consider the following project; for which activities is it possible that the slack can be greater than zero? Activity Immediate Predecessors B, E a. Only activities B or E could have slack, but they could not both have slack. Ob. Only activities B or C could have slack, but they could not both have slack. Oc. It is possible for any or all activities in this project to have slack. Od. It is possible for either all three...

  • Microsoft Project Assignment Description A system development project has been defined to contain the following list of...

    Microsoft Project Assignment Description A system development project has been defined to contain the following list of activities along with their estimated times for completion. The project will start on 5/1/2019. Project Data Provided: Activity ID Activity Name Days Predecessors Optimistic(O) Realistic(R) Pessimistic(P) 1 Gather Requirement 1 2 3 2 Analyze processes 1 2 6 1 3 Define DFDs 0.5 1 1.5 2 4 Design Processes 2 7 12 2 5 Design database 4 7 22 3 6 Design UI...

  • Choose an event or significant task and prepare an activities list following a format similar to...

    Choose an event or significant task and prepare an activities list following a format similar to that used in the text, Table 9.3, Chapter 9, page 391. Be sure to include the immediate predecessors. Then, create a project network similar to that shown in Figure 9.7, Chapter 9, page 392. Do NOT include times for the activities and do NOT attempt to determine the critical path. Examples of events you might consider (there are many others): formal dinner for 5...

  • Question 16 4 points Save Answe The following provides information about a project, including a list...

    Question 16 4 points Save Answe The following provides information about a project, including a list of activities and precedence relationships, activity durations (normal and "crash" times), direct activity costs (normal and "crash"), indirect costs for the project, as well as calculated crash costs/day and the maximum amount that each activity can be shortened (crashed) by. There are no penalty costs for this project. Total project cost (using normal times), a network diagram, and the four paths and durations have...

  • Question 3 2 pts Which of the following is NOT an aspect of glycolysis? It occurs...

    Question 3 2 pts Which of the following is NOT an aspect of glycolysis? It occurs in the absence of oxygen It generates ATP It is irreversible It generates two molecules of pyruvate Previous Next → Question 9 2 pts Which of the following defines "android" obesity? Accumulation of fat during the mid-years of life Overfatness due to reliance on high fat foods as a central part of the diet Storage of excess fat around the central part of the...

  • QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an...

    QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. It describes how the project costs will be planned, structured, and controlled. It is based on project cost estimates and is separate from the project management plan. It may specify the level of precision, which is the...

  • Which of the following factors would NOT be part of a process to improve a business’...

    Which of the following factors would NOT be part of a process to improve a business’ competitive positioning in a global marketplace? Focusing on customers. Practicing continuous improvement. Relying on the Internet to unite companies. Reducing product quality to keep costs low. Which of the following statements concerning the U.S. service sector today is most accurate? This sector has grown much more rapidly than the manufacturing sector. It has become the low-wage sector of the U.S. economy. It focuses less...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT