Question
urgent
-) !! uestion 14 of 20 Fiew Policies Current Attempt in Progress In 2021. Cullumber Corporation began construction work under
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer - $1,480,000

Percentage of gross profit recognized in 2020 as a % of revenue = Gross profit /Revenue recognized

                                              = $18500/$925000

                                                = .20 or 20%

the initial estimated total income before tax on this contract =Contract price *% of gross profit

                                         = $7,400,000 * 20%

                                         = $ 1,480,000

If u r satisfied plz give a like

In case of any doubts plz let me know tanq

Add a comment
Know the answer?
Add Answer to:
urgent -) !! uestion 14 of 20 Fiew Policies Current Attempt in Progress In 2021. Cullumber...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • urgent iew Policies urrent Attempt in Progress Carla Vista Construction Company had a contract starting April...

    urgent iew Policies urrent Attempt in Progress Carla Vista Construction Company had a contract starting April 2021, to construct a $37000000 building that is expected to be completed in September 2022, at an estimated cost of $34000000. At the end of 2021, the costs to date were $15640000 and the estimated total costs to complete had not changed. The progress billings during 2021 were $8300000 and the cash collected during 2021 was $5550000. Carla Vista uses the percentage-of-completion method. At...

  • urgent 0/1 uestion 10 of 20 "iew Policies Show Attempt History Current Attempt in Progress Cullumber...

    urgent 0/1 uestion 10 of 20 "iew Policies Show Attempt History Current Attempt in Progress Cullumber Inc. charges an initial franchise fee of $3500000, with $620000 paid when the agreement is signed and the balance in 5 annual payments. The present value of the future payments, discounted at 9%, is $2240439. The franchisee has the option to purchase $420000 of equipment for $348000. Cullumber has substantially provided all initial services required and collectibility of the payments is reasonably assured. The...

  • In 2010, Concrete Inc. began a three year construction contract for $3,500,000. Cement uses the percentage-of-completion...

    In 2010, Concrete Inc. began a three year construction contract for $3,500,000. Cement uses the percentage-of-completion method. The income to be recognized each year is based on the proportion of costs incurred to total estimated costs for completing the contract. The financial statement presentation relating to this contract for calendar 2010 follow: Statement of Financial Position Current Assets: Accounts receivable $150,000 Contract asset/liability 105,000 (Contract cost $425,000 less Billings of $320,000) Income Statement Income (before tax) on the contract recognized...

  • Prachce Problem 9 In Year 1, Amber Construction Corporation began construction work under a three-year contract....

    Prachce Problem 9 In Year 1, Amber Construction Corporation began construction work under a three-year contract. The contract price is $1,610,000. Long uses the percentage-of-completion method for financial reporting purposes. The financial statement presentation relating to this contract at December 31, year 1, is as follows: Balance Sheet $30,000 Accounts receivable (from construction progress billings) Construction in progress Less: Billings on Construction Contract $100,000 (93,000) 7,000 Cost of uncompleted contracts in excess of billings Income Statement $24,000 Income (before tax)...

  • n 2016, Long Construction Corporation began construction work under a three-year contract. The contract price is...

    n 2016, Long Construction Corporation began construction work under a three-year contract. The contract price is $1,600,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2016, is as follows: Balance Sheet Accounts receivable (from construction progress billings) $ 30,000 Construction in progress $ 100,000 Less: Billings on construction contract (94,000 ) Cost and profit of uncompleted contracts in excess of billings 6,000 Income...

  • Question 12 --/1 View Policies Current Attempt in Progress During 2020, Headland Company started a construction...

    Question 12 --/1 View Policies Current Attempt in Progress During 2020, Headland Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date Estimated costs to complete $410,000 $901,180 $1,067,000 590,000 197,820 -O- 297,000 903,000 1,590,000 271,000 805,000 1,434,000 Billings to date Collections to date Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used....

  • Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Cullumber Construction Company...

    Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Cullumber Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,920,000. On July 1, Cullumber estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020,...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,500,000. During 2021, costs of $2,200,000 were incurred, with estimated costs of $4,200,000 yet to be incurred. Billings of $2,740,000 were sent, and cash collected was $2,450,000. In 2022, costs incurred were $2,740,000 with remaining costs estimated to be $3,900,000. 2022 billings were $2.990,000, and $2,675,000 cash was collected. The project was completed in 2023 after additional costs of...

  • E6.37 (LO 12) (Recognition of Profit on Long-Term Contract) Vaughn Enterprises Ltd. has entered into a...

    E6.37 (LO 12) (Recognition of Profit on Long-Term Contract) Vaughn Enterprises Ltd. has entered into a contract beginning in February 2020 to build two warehouses for Atlantis Structures Ltd. The contract is a non-cancellable fixed price contract for $10 million. The following data pertain to the construction period (all figures in thousands). 2020 2021 2022 Costs for the year $3,825 $4,675 $1,200 Estimated costs to complete 4,675 1,270 –0– Progress billings for the year (non-refundable) 3,500 4,100 2,400 Cash collected...

  • Question 2 --/1 View Policies Current Attempt in Progress Vaughn Company reports pretax financial income of...

    Question 2 --/1 View Policies Current Attempt in Progress Vaughn Company reports pretax financial income of $63,900 for 2020. The following items cause taxable income to be different than pretax financial income. 1. Depreciation on the tax return is greater than depreciation on the income statement by $17,600. 2. Rent collected on the tax return is greater than rent recognized on the income statement by $23,300. 3. Fines for pollution appear as an expense of $11,800 on the income statement....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT