Question

13. The fixed manufacturing overhead variance caused by actual activity being different from the estimated activity used in c

0 0
Add a comment Improve this question Transcribed image text
Answer #1

13. The fixed manufacturing overhead variance caused by actual activity being different from the estimated activity used in calculating the predetermined overhead application rate is called the;

Answer D .Volume Variance

Explanation

Predetermined overhead application rate is calculated on the basis of estimated activity used such as direct labor hours or machine hours. When the actual activity is different from estimated activity level then fixed manufacturing overhead variance is calculated.

14 How is performance evaluated for a cost center?

Answer A ) Actual Cost incurred compared to Budgeted Costs

Explanation

Performance of a cost center is evaluated by comparing the actual cost incurred with the budgeted cost and if the actual cost incurred is less than budgeted then the performance is good otherwise not.

15 A favorable material quantity variance would occur if

Answer B) Actual pounds of materials used were less than the standard pounds allowed

Explanation

If the actual material used were less than the standard pounds of material allowed then it results in favorable quantity variance.

16 Material Price Variance = A Q* (A P – SP)

                                                 = 2000 * ($3.80 - $3.75)

                                                 = $100 (UF)

17 An individual interested in making a judgment about the profitability of a company should

Answer C) Review the trend of the company’s ROI for several years.

18 Which of the following is not a category of financial statements ratios?

Answer D) Prospectus

Prospectus is not a part of financial statement ratios. It is issued when the company issues the shares.

19 Increasing information systems capabilities would be a critical success factor found in which perspective of the balanced scorecard?

Answer A) Internal Business

Add a comment
Know the answer?
Add Answer to:
13. The fixed manufacturing overhead variance caused by actual activity being different from the estimated activity...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 10 Direct materials Standard per unit Actual $ 4 per pound Used 15 Materials quantity variance...

    10 Direct materials Standard per unit Actual $ 4 per pound Used 15 Materials quantity variance $ 3 2 pounds pounds Produced 10 finished units (AQ used - SQ allowed) SP A B C D 15 20 39 78 2 pt Variance is A favorable B unfavorable SQ allowed Standard per unit actual units 11 FACTORY OVERHEAD Machine Hours Budgeted $50 Standard allowed 16 Actual 180 Actual Variable factory overhead (activity base) rate per machine hour $10 Efficiency variance 10...

  • Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come...

    Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come from material costs that are higher or lower than expected, material usage that is not what was expected, higher or lower labor costs than expected, or more or less time spent to produce an item than expected. Overhead cost and volume variances are another cause for costs to be higher or lower than what was expected. The total manufacturing variance can be broken down...

  • Assume when you calculated direct material price variance, you found that actual costs of direct material...

    Assume when you calculated direct material price variance, you found that actual costs of direct material used is greater than the material budgeted costs based on actual units purchased and used. In this case the material price variance is: a. Favorable b. Unfavorable c. Significant d. Positive Given: Actual labor costs: $200.00 Flexible budget allowed for actual units used: $180.00 based on budgeted units: $189.00 Labor rate variance is: a. $20 Favorable b. $20 Unfavorable c. $9 Favorable d. $9...

  • Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come...

    Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come from material costs that are higher or lower than expected, material usage that is not what was expected, higher or lower labor costs than expected, or more or less time spent to produce an item than expected. Overhead cost and volume variances are another cause for costs to be higher or lower than what was expected. The total manufacturing variance can be broken down...

  • Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead...

    Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead along with the related controllable and volume variances.Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical into plastic. A detailed estimate of what a product should cost.Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 70,000 units of product were as follows: Standard Costs Actual Costs Direct materials 189,000 lbs. at $6.00 187,100...

  • 1 Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on...

    1 Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor- hours and its standard cost card per unit is as follows: 2 3 4. 5 6 7 (1) (2) Standard Standard Quantity Price or Hours or Rate 5 pounds $8.00 per pound 2 hours $14 per hour 2 hours $5 per hour 8 Inputs Direct materials Direct labor Variable overhead Total standard cost per unit Standard Cost (1) (2) $40.00 28.00 10.00...

  • 1) 2) 3) 4) 5) A favorable cost variance occurs when Oa. actual costs are the...

    1) 2) 3) 4) 5) A favorable cost variance occurs when Oa. actual costs are the same as standard costs Ob. actual costs are more than standard costs Oc. standard costs are more than actual costs Od. standard costs are less than actual costs The Flapjack Corporation had 8,042 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units, but only 999 units were actually produced. Labor standards were 7.9...

  • gndelssohn Manufacturing, Inc. uses a standard costing system with fixed manufacturing overhead (FMOH) applied based on...

    gndelssohn Manufacturing, Inc. uses a standard costing system with fixed manufacturing overhead (FMOH) applied based on machine-hours (MHs). According to their standards, each unit of their most popular product requires 2 MHs For the most recent period: Budgeted Units Actual Units 1,600 units 1,586 units 3,400 MHs Actual MHs Budget Actual $ 45,200 FMOH $ 44,800 The FMOH volume variance for the period was closest to: $392.00 Unfavorable A. В. $400.00 Unfavorable $3,004.24 Unfavorable $2,800.00 Favorable C. D. Е. None...

  • The following describes production activities of Mercer Manufacturing for the year. Actual direct materials used Actual...

    The following describes production activities of Mercer Manufacturing for the year. Actual direct materials used Actual direct labor used Actual units produced 31,000 lbs. at $5.80 per lb. 10,600 hours for a total of $217,300 63,000 1,600 hour. 29.9 5. IS DE $217,300 Budgeted standards for each unit produced are 0.50 pound of direct material at $5.75 per pound and 10 minutes of direct labor at $21.50 per hour. AH = Actual Hours SH = Standard Hours AR = Actual...

  • The following information describes production activities of Mercer Manufacturing for the year. Actual direct materials used...

    The following information describes production activities of Mercer Manufacturing for the year. Actual direct materials used 22,000 lbs. at $4.35 per lb. 6,575 hours for a total of Actual direct labor used $128,870 Actual units produced 36,000 Budgeted standards for each unit produced are 0.50 pounds of direct material at $4.30 per pound and 10 minutes of direct labor at $20.60 per hour. AQ = Actual Quantity SQ = Standard Quantity AP = Actual Price SP = Standard Price AH...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT