Question

Ironlove Inc. considers a project to supply a car manufacturer with 105,000 tons of steel plates...

Ironlove Inc. considers a project to supply a car manufacturer with 105,000 tons of steel plates annually for five years. It requires an initial investment of 42 million dollars in steel plate production machinery. The variable cost of the production is $430 per ton. The overhead cost will be 15 million dollars a year, and the company estimates the price of the steel plates at $950 per ton. To run this project, Ironlove needs to invest 8 million dollars in the net working capital at time zero.

The machinery belongs to Class 6, with a CCA rate of 15%. The company estimates that it can sell the machinery at a salvage value of 12 million dollars. Assume the company requires a 15% rate of return, and the tax rate is 40%.

a) What are the estimated OCF and NPV for this project? Should you pursue this project?

b) Suppose you believe that the accounting department’s initial cost and salvage value projections are accurate only to within ±20%; the marketing department’s steel price estimate is accurate only within ±15%, and the net working capital estimate is accurate only to within ±10%. What is your worst-case and best-case scenario for this project?

c) Suppose you are not confident about the car manufacturer’s actual steel plates requirement. What is the sensitivity of the project OCF to changes in the quantity supplied?

d) What about the sensitivity of NPV to changes in quantity supplied? Given the sensitivity number you calculated, what is the minimum level of output below which you wouldn’t want to operate?

0 0
Add a comment Improve this question Transcribed image text
Answer #1
(a)
Year Operating Cash Flow Cash outflow Net Cashflow Depreciation Net profit Tax Cashflow after tax PVF @
15 %
Discounted Value  
(a) (b) (c ) (d=b-c) (e ) (f=d-e) (g=f x 40%) (h=d-g) (i) (J=h x i)
                                      -                              -           5,00,00,000         -5,00,00,000                          -           -5,00,00,000                            -           -5,00,00,000          1.00         -5,00,00,000
                                       1         3,96,00,000                            -             3,96,00,000           31,50,000          3,64,50,000         1,45,80,000          2,50,20,000          0.87          2,17,56,522
                                       2         3,96,00,000                            -             3,96,00,000           58,27,500          3,37,72,500         1,35,09,000          2,60,91,000          0.76          1,97,28,544
                                       3         3,96,00,000                            -             3,96,00,000           49,53,375          3,46,46,625         1,38,58,650          2,57,41,350          0.66          1,69,25,355
                                       4         3,96,00,000                            -             3,96,00,000           42,10,369          3,53,89,631         1,41,55,853          2,54,44,148          0.57          1,45,47,774
                                       5         3,96,00,000                            -             3,96,00,000           35,78,813          3,60,21,187         1,44,08,475          2,51,91,525          0.50          1,25,24,640
                                       5         2,00,00,000                            -             2,00,00,000                          -            2,00,00,000            80,00,000          1,20,00,000          0.50              59,66,121
Net Present Value          4,14,48,957
Working Notes:
(i)Net cash inflow (Operating Cash flow):
Year Sales VC Fixed Overheads Net cash inflow
(+/(-) + - -
1-5         9,97,50,000         4,51,50,000           1,50,00,000       3,96,00,000
5 Salvage vale and WC recovery ( 12 + 8) = $ 2,00,00,000
Sales (105000 x 950 )         9,97,50,000
VC (105000 x 430 )         4,51,50,000
(ii) Initial cost Machine '(42*1000000) + WC (8*1000000)       5,00,00,000
(iii) Depreciation
Year Beg. Value Depreciation End. Value
(a) (b) (c=b x 15%) (d=b-c)
1         4,20,00,000             31,50,000           3,88,50,000
2         3,88,50,000             58,27,500           3,30,22,500
3         3,30,22,500             49,53,375           2,80,69,125
4         2,80,69,125             42,10,369           2,38,58,756
5         2,38,58,756             35,78,813           2,02,79,943
Know the answer?
Add Answer to:
Ironlove Inc. considers a project to supply a car manufacturer with 105,000 tons of steel plates...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production. You will need an initial $4,600,000 investment in threading equipment to get the project started; the project will last for 3 years. The accounting department estimates that annual fixed costs will be $750,000 and that variable costs should be $410 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 3-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $4,800,000 investment in threading equipment to get the project started; the project will last for three years. The accounting department estimates that annual fixed costs will be $850,000 and that variable costs should be $250 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the three-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will need an initial $6,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,500,000 and that variable costs should be $285 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 28,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 28,000 tons of machine screws annually for automobile production. You will need an initial $5,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,250,000 and that variable costs should be $235 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $1,700,000 investment in threading equipment to get the project started: The project will last for 5 years. The accounting department estimates that annual fixed costs will be $450,000 and that variable cost should be $210 per ton; account will depreciate the initial fixed asset investment straight line to zero over the five year project life. It also estimates a...

  • Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production. You will need an initial $4.3 million investment in threading equipment to get the project started; the project will last for five years. The accounting department estimates that annual fixed costs will be $1.025 million and that variable costs should be $190 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the five-year project life. It also estimates a...

  • Scenario Analysis [L02] Consider a project to supply Detroit with 30,000 tons of machine screws annually...

    Scenario Analysis [L02] Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production. You will need an initial $4.3 million investment in threading equipment to get the project started: the project will last for five years. The accounting department estimates that annual fixed costs will be $1.025 million and that variable costs should be $190 per ton: accounting will depreciate the initial fixed asset investment straight-line to zero over the five-year project life. It...

  • Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production. You will need an initial $2,200,000 investment in threading equipment to get the project started; the project will last for five years. The accounting department estimates that annual fixed costs will be $700,000 and that variable costs should be $400 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the five-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,300,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,275,000 and that variable costs should be $240 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...

  • Consider a project to supply Tacoma with 40,000 tons of machine screws annually for automobile production....

    Consider a project to supply Tacoma with 40,000 tons of machine screws annually for automobile production. You will need an initial $5,600,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $600,000 and that variable costs should be $250 per ton. Further, the accounting department will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life and estimate a...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT