Schedule A can be solved as shown below (Excel Formula is shown in each cell. Kindly note this to understand):
This is for Level planning; means constant production over period to meet demand.
Its solution will be as shown below:
Hence total cost of Production for this Schedule A is $ 17,800.00
Schedule B:
Since in this schedule, the only change is that, the # of workers have reduced and hence the production capacity. Since overtime is allowed but no subcontracting, hence its solution will be as shown below:
The Formula will remain same as shown in Schedule A. The only changes I made in Shell B7; Begining workforce is 700:
Hence the overall cost for this schedule is $ 19,000.00
Schedule C:
In this case, the Formula will be changed in Row No 28 & 29. Row # 28 will be zero. But Subcontracting is allowed hence the value in Row # 29 will be as shown below:
And its solution is shown below:
Hence the cost in this case is $ 20,200.00
Please answer questions using Microsoft excel, and please show formulas. Thank you. School of Business BUS...
cheek the answer plz Solve this Aggregate Planning Problem by minimizing the cost of matching the capacity various options in various periods to the future demand? Find inventory cost, regular time cost, overtime cost and subcontract cost, and the total cost? Sales Period Mar Apr May Pemand 700 1000 1100 Capacity: Regular Time 1000 800 800 Overtime 100 100 100 200 200 100 Subcontracting Beginning inventory is zero O Cost Regular Time Overtime $20 per tire $30 per tire $50...
needing help with solving in Excel 6. Given the following forecast and cost information, determine the total cost of a plan that uses regular time production output of 600 units per month, overtime is used when needed up to a maximum of 60 units per month, and subcontracting is used if additional units are needed to meet the forecast. Month 1 2 3 5 6 Forecast 570 600 630 650 670 690 Regular time cost = $40 per unit Overtime...
Andree’s All-American manufactures fashionable tennis wear, needs help planning production for next year. Demand for tennis gear is fairly stable, but has peaks during the summer months. Month Demand Forecast January 500 February 300 March 200 April 1500 May 2500 June 3500 July 4500 August 2500 September 500 October 300 November 300 December 2500 Beginning workforce 9 workers Production per day 9 units per employee Production cost during regular time $50 per unit Subcontracting cost $75 per unit Increasing production...
How do I calculate the one time adjustment of workforce to support the level production plan? Problem information: Month: 1 2 3 4 5 6 7 8 9 10 11 12 Demand: 500 800 1000 1400 2000 3000 2700 1500 1400 1500 2000 1200 Management at the Kerby Corporation has determined the following aggregated demand schedule in Units. An employee can produce an average of 10 units per month. Each worker on the payroll costs $2,000 in regular time wages...
Company AAA produces only one product which other manufacturers purchase as a component for their final products. The operations manager wants to plan the production and inventory quantities of the product for the first six months of the next year. The monthly demand is forecasted as follows. January February March April May June 1200 1400 1800 2400 2600 2200 The company has three production options: regular production, overtime production, and subcontracting. Production cost per unit during regular time is $80...
Answer Part B using excel and show equations that were used. explain if the problem is suffiecent or not. You would like to construct an aggregate production plan for four quarters of 2021. Product name: TRX3010 Cost of regular production = 50 $/u Cost of overtime production = 65 $/u Inventory holding cost = 5 $/u/qtr Cost of increasing production = 40 $/u Cost of decreasing production = 45 $/u Previous quarter's regular production = 4200 u Beginning inventory level...
Gang Aft Agley, a manufacturing company, faces the aggregate planning problem shown in the table below. Cost of regular production is $5 per unit, the cost of producing the same unit on overtime is $7.50, the cost of subcontracting is S9 per unit, an<d the cost of carrying a unit in inventory from one month to the next is $2 The labor contract at the plant prohibits overtime output to exceed 300 units in any five month window (that is...
Medisan Inc. has just signed a contract to supply walky-talkiesto the Turkish Armed Forces. During the next four months, the firm must deliver 150 in December, 160 in January, 225 in February and 180 in March. Medisan’s factory in Temelli can produce walky-talkies at a cost of $20 per unit (labor cost is not included). To produce a walky-talky 10 hours of labor are required and there are 10 workers available at the plant at the beginning of December. Each...
Management at the Kerby Corporation has determined the following aggregated demand schedule (in units): Month 1 2 3 4 Demand 500 800 1,000 1,400 Month 5 6 7 8 Demand 2,000 3,000 2,700 1,500 Month 9 10 11 12 Demand 1,400 1,500 2,000 1,200 An employee can produce an average of 10 units per month. Each worker on the payroll costs $2,000 in regular-time wages per month. Undertime is paid at the same rate as regular time. In accordance with...
Here is an operations planning case analysis. You are expected to do the following questions and submit them for marking at the end of the semester via utsonline and in hard copy to your tutor in week 10. A company has the following demand forecast next year, expressed in six bimonthly periods: Forecast Demand: Period 1 = 4,500 units Period 4 = 6,500 units Period 2 = 3,000 units Period 5 = 5,100 units Period 3 = 4,800 units Period...