Question
Please answer questions using Microsoft excel, and please show formulas. Thank you.
School of Business BUS 476-Operations Management Dr. Enrique G. Zapatero, Professor Homework #8-Aggregate Planning Instructions: Use MS Excel to produce the computations to support your answers to ProblemsI, and I. Problem I: A production manager needs to develop a production schedule to meet the following demand Period Demand 600 600 800 1000 1200 600 2 Productions costs are as follows: (a) regular time: $3 per unit. (b) over-time: $5 per unit. (c) subcontract: $7 per unit. (d) Inventory carrying cost $2 per unit per period (e) Back-order costs = $5 per unit per period. You have to meet all the demand. You start with no inventory at the beginning of the first period, and end with no inventory at the end of the sixth period Schedule A: Suppose the manager has adopted a policy of level production (i.e., constant production rate for all periods). Assume no over-time or subcontracting is allowed Schedule B: Suppose some workers have retired, and the regular production rate can be only 700 units per period. Further, no subcontracting is allowed However, it is possible to schedule production on an over-time basis. (Hint: You normally schedule over-time production during peak demand.) Schedule C: Suppose the regular rate of production per period is 700. However you are allowed to buy 200 units from a subcontractor during each of the periods 3, 4, and 5. Develop a production schedule to meet the demand Schedule D: Suppose the regular rate of production is 700 units per period Further, you are allowed to produce 100 units during each of the periods 3,4 and 5 on an overtime basis, but the subcontractor has gone out of business. You can hire two temporary workers during the periods 3, 4, and 5. Each worker can produce 50 units per period at the regular cost. But it costs $200 to train a worker and check the quality of the product during each of the three periods

media%2F2bb%2F2bb96eb9-9dee-4873-94df-4a
media%2Feaa%2Feaae00f6-5230-467c-ad25-c8
media%2F54d%2F54d8b6d2-9a65-4ee0-af61-8e
media%2Fa0d%2Fa0daca9e-73cb-4adf-abd7-35
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Schedule A can be solved as shown below (Excel Formula is shown in each cell. Kindly note this to understand):

This is for Level planning; means constant production over period to meet demand.

Costs Per Unit Units Cost Regular Time Labor Co Overtime SUM(B28.G28 G4 H4 6 Beginning Inventor 8 Labor Standard (units/workeIts solution will be as shown below:

Costs Reqular Time Labor Cost Overtime Subcontractin Inventory Holding Cost Backorders Hirin Per Unit Units Cost $3.001 48001

Hence total cost of Production for this Schedule A is $ 17,800.00

Schedule B:

Since in this schedule, the only change is that, the # of workers have reduced and hence the production capacity. Since overtime is allowed but no subcontracting, hence its solution will be as shown below:

The Formula will remain same as shown in Schedule A. The only changes I made in Shell B7; Begining workforce is 700:

Costs Reqular Time Labor Cost Overtime Subcontractin Inventory Holding Cost Backorders Per Unit Units Cost $3.004200$12,600 6Hence the overall cost for this schedule is $ 19,000.00

Schedule C:

In this case, the Formula will be changed in Row No 28 & 29. Row # 28 will be zero. But Subcontracting is allowed hence the value in Row # 29 will be as shown below:

Costs Per Unit Units Cost Regular Time Labor Co Overtime Subcontra Inventory Holding Cost -SUM(B27 G27)G3 H3 SUM(B28 : G28) GAnd its solution is shown below:

Costs Regular Time Labor Cost Overtime Subcontractin Inventory Holding Cost Backorders Per Unit Units Cost $3.004200$12,600 $Hence the cost in this case is $ 20,200.00

Add a comment
Know the answer?
Add Answer to:
Please answer questions using Microsoft excel, and please show formulas. Thank you. School of Business BUS...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • cheek the answer plz Solve this Aggregate Planning Problem by minimizing the cost of matching the...

    cheek the answer plz Solve this Aggregate Planning Problem by minimizing the cost of matching the capacity various options in various periods to the future demand? Find inventory cost, regular time cost, overtime cost and subcontract cost, and the total cost? Sales Period Mar Apr May Pemand 700 1000 1100 Capacity: Regular Time 1000 800 800 Overtime 100 100 100 200 200 100 Subcontracting Beginning inventory is zero O Cost Regular Time Overtime $20 per tire $30 per tire $50...

  • needing help with solving in Excel 6. Given the following forecast and cost information, determine the...

    needing help with solving in Excel 6. Given the following forecast and cost information, determine the total cost of a plan that uses regular time production output of 600 units per month, overtime is used when needed up to a maximum of 60 units per month, and subcontracting is used if additional units are needed to meet the forecast. Month 1 2 3 5 6 Forecast 570 600 630 650 670 690 Regular time cost = $40 per unit Overtime...

  • Andree’s All-American manufactures fashionable tennis wear, needs help planning production for next year. Demand for tennis...

    Andree’s All-American manufactures fashionable tennis wear, needs help planning production for next year. Demand for tennis gear is fairly stable, but has peaks during the summer months. Month Demand Forecast January 500 February 300 March 200 April 1500 May 2500 June 3500 July 4500 August 2500 September 500 October 300 November 300 December 2500 Beginning workforce 9 workers Production per day 9 units per employee Production cost during regular time $50 per unit Subcontracting cost $75 per unit Increasing production...

  • How do I calculate the one time adjustment of workforce to support the level production plan?...

    How do I calculate the one time adjustment of workforce to support the level production plan? Problem information: Month: 1 2 3 4 5 6 7 8 9 10 11 12 Demand: 500 800 1000 1400 2000 3000 2700 1500 1400 1500 2000 1200 Management at the Kerby Corporation has determined the following aggregated demand schedule in Units. An employee can produce an average of 10 units per month. Each worker on the payroll costs $2,000 in regular time wages...

  • Company AAA produces only one product which other manufacturers purchase as a component for their final...

    Company AAA produces only one product which other manufacturers purchase as a component for their final products. The operations manager wants to plan the production and inventory quantities of the product for the first six months of the next year. The monthly demand is forecasted as follows. January February March April May June 1200 1400 1800 2400 2600 2200 The company has three production options: regular production, overtime production, and subcontracting. Production cost per unit during regular time is $80...

  • Answer Part B using excel and show equations that were used. explain if the problem is...

    Answer Part B using excel and show equations that were used. explain if the problem is suffiecent or not. You would like to construct an aggregate production plan for four quarters of 2021. Product name: TRX3010 Cost of regular production = 50 $/u Cost of overtime production = 65 $/u Inventory holding cost = 5 $/u/qtr Cost of increasing production = 40 $/u Cost of decreasing production = 45 $/u Previous quarter's regular production = 4200 u Beginning inventory level...

  • Gang Aft Agley, a manufacturing company, faces the aggregate planning problem shown in the table below....

    Gang Aft Agley, a manufacturing company, faces the aggregate planning problem shown in the table below. Cost of regular production is $5 per unit, the cost of producing the same unit on overtime is $7.50, the cost of subcontracting is S9 per unit, an<d the cost of carrying a unit in inventory from one month to the next is $2 The labor contract at the plant prohibits overtime output to exceed 300 units in any five month window (that is...

  • Medisan Inc. has just signed a contract to supply walky-talkiesto the Turkish Armed Forces. Durin...

    Medisan Inc. has just signed a contract to supply walky-talkiesto the Turkish Armed Forces. During the next four months, the firm must deliver 150 in December, 160 in January, 225 in February and 180 in March. Medisan’s factory in Temelli can produce walky-talkies at a cost of $20 per unit (labor cost is not included). To produce a walky-talky 10 hours of labor are required and there are 10 workers available at the plant at the beginning of December. Each...

  • Management at the Kerby Corporation has determined the following aggregated demand schedule (in units): Month 1...

    Management at the Kerby Corporation has determined the following aggregated demand schedule (in units): Month 1 2 3 4 Demand 500 800 1,000 1,400 Month 5 6 7 8 Demand 2,000 3,000 2,700 1,500 Month 9 10 11 12 Demand 1,400 1,500 2,000 1,200 An employee can produce an average of 10 units per month. Each worker on the payroll costs $2,000 in regular-time wages per month. Undertime is paid at the same rate as regular time. In accordance with...

  • Here is an operations planning case analysis. You are expected to do the following questions and...

    Here is an operations planning case analysis. You are expected to do the following questions and submit them for marking at the end of the semester via utsonline and in hard copy to your tutor in week 10. A company has the following demand forecast next year, expressed in six bimonthly periods: Forecast Demand: Period 1 = 4,500 units Period 4 = 6,500 units Period 2 = 3,000 units Period 5 = 5,100 units Period 3 = 4,800 units Period...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT