Question

Conceptual Question 19-11 Consider two projects that have the same activities... Consider two projects that have the same act

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer is : cannot be determined.

The reason being, in case of second project, the activity times are always in line to the expectation. While, in case of the first project, the activity times are as per the expected outcomes, i.e. they are dependent on the output. Thus, we cannot predict whether the first project will be completed before or after second project.

Add a comment
Know the answer?
Add Answer to:
Conceptual Question 19-11 Consider two projects that have the same activities... Consider two projects that have...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • value 6.66 points Conceptual Question 6-7 Consider two processes,... Consider two processes, A and B, with...

    value 6.66 points Conceptual Question 6-7 Consider two processes,... Consider two processes, A and B, with an initial cost of c(1)-20. Process A has a leaning rate of LR-0.95 and process B has a learning rate of LR-0.8. After 20 units Process A is cheaper Process B is cheaper The two processes will have the same cost Cannot be determined from the given information

  • Consider two projects, A and B. The CFO and her team have compared the risks of...

    Consider two projects, A and B. The CFO and her team have compared the risks of these two projects with all other business lines within the company. Their analysis suggests that the betas of projects A and B are 0.8 and 1.2, respectively. The CFO and her team have also calculated the expected returns (IRRs) for these projects: Project A has an expected return of 7.00%, and project B's expected return is 8.5%. Suppose CAPM holds. The risk-free rate is...

  • Consider the following variation on the Activity Selection Problem.You have a resource that may be used for activities...

    Consider the following variation on the Activity Selection Problem.You have a resource that may be used for activities 24 hours a day,ever day.Activities repeat that may be used for activities repeat on a daily basis. As in the original problem, each activity has a start time and as end time.If an activity is selected, it will exclusively use the resource during the duration between the start and end time(i.e., no other activity may be scheduled during this time). Note that...

  • You could consider each week of a course as a small project. It requires you to...

    You could consider each week of a course as a small project. It requires you to study some learning resources, participate in a discussion, and possibly complete a paper or a test. Create a work breakdown structure (WBS) that represents your projects for this week. Document the tasks you were asked to perform in this week of the course (you can use the list above as a starting point). Decompose each main task into subtasks that can be completed in...

  • Problem 5-6 A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the...

    Problem 5-6 A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 70% complete. The planners were only expecting to be 57% through the third activity at this time. The first activity involves prepping the site for the bridge. It was...

  • Choose an event or significant task and prepare an activities list following a format similar to...

    Choose an event or significant task and prepare an activities list following a format similar to that used in the text, Table 9.3, Chapter 9, page 391. Be sure to include the immediate predecessors. Then, create a project network similar to that shown in Figure 9.7, Chapter 9, page 392. Do NOT include times for the activities and do NOT attempt to determine the critical path. Examples of events you might consider (there are many others): formal dinner for 5...

  • 2 Problem 5-6 (Algo) A project to build a new bridge seems to be going very...

    2 Problem 5-6 (Algo) A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 65% complete. The planners were expecting to be only58 % through the third activity at this time. The first activity involves prepping the site for the bridge....

  • PRACTICE 4 DMUR only You are considering two investment projects each having the same cost. Each...

    PRACTICE 4 DMUR only You are considering two investment projects each having the same cost. Each project is facing the following events, probabilities and net profits: ALTERNATIVES: EVENTS: NET PROFITS: PROBABILITIE: aj: Newspaper ei e2 e3 4000 6000 9000 .3 .SO 2 a: Pamphlet ei e2 e3 3000 7000 8000 .30 SO .20 1. Construct a decision tree and show which project you would chose by using the expected value method )? 2. Calculate the coefficient of variation of each...

  • . Verizon LTE 1:22 PM 10 77% 3. It is common for activities in projects to...

    . Verizon LTE 1:22 PM 10 77% 3. It is common for activities in projects to run late. What should be DONE when this happens differs between traditional Critical Path Method (CPM) and TOC's Critical Chain Project Management (CCPM). The upper-most of the two diagrams provided below is a typical Critical Path Method (CPM) Gantt PERT Chart schedule. The lower of the two diagrams is a typical Critical Chain Project Management (CCPM) schedule (with resource, feeding and project buffers included)....

  • QUESTION THREE A. A company is considering two alternative investment projects both of which have a...

    QUESTION THREE A. A company is considering two alternative investment projects both of which have a positive net present value. The projects have been ranked on the basis of both net present value (NPV) and internal rate of return (IRR). The result of the ranking is shown below: Project A Project B NPV Ist 2nd IRR 2nd 1st Discuss any four (4) potential reasons why the conflict between the NPV and IRR ranking may have arisen. (12 marks) B. Kumi...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT