Question

A certain project has the following planned cost schedule: It will spend $400 per day for...

A certain project has the following planned cost schedule:
It will spend $400 per day for the first 4 days.
It will spend $1,400 per day for the next 3 days.
It will spend $2,200 per day for the next 5 days.
It will spend $3,400 per day for the next 7 days.
It will spend $4,700 per day for the next 7 days.
It will spend $5,500 per day for the next 8 days.
It will spend $4,200 per day for the next 4 days.
It will spend $2,600 per day for the next 7 days.
It will spend $1,800 per day for the next 4 days.
It will spend $800 per day for the next 3 days.

At the end of day 22:
The cost variance is given by $27,700.
The schedule variance is given by $71,200.
What is the time variance? __________

Make sure that you get the correct sign! (+/-)

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
A certain project has the following planned cost schedule: It will spend $400 per day for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • For a project, in X day, planned value, earned value and actual cost of the tasks...

    For a project, in X day, planned value, earned value and actual cost of the tasks are given in dollar in the table below. Planned $1000 to complete project. Task Actual Cost Work Performed Budgeted Cost Work Scheduled 50 70 30 100 50 2 3 4 5 Budgeted Cost Work Performed 50 70 30 50 0 Total: 250 a. Find schedule and cost variance. Explain what it means? b. Find schedule and cost performance index. c. Find estimate to complete...

  • what is the normal cost of this project? what is the cost of the project after...

    what is the normal cost of this project? what is the cost of the project after 2 days shortening? what is the crashing cost per day for avtivity G? Given the following data and network, find answer the questions 18-20 if you're asked to finish this project 2 days earlier than its normal duration. Indirect cost (overhead) is $200 per day. 9.12 E 1.8 اليا 12.19 10.13 B 7 H 7 1.8 13, 20 0.1 1.7 8.15 20,25 15, 20...

  • Question 1: I)-What is the normal cost of this project? II)-What is the cost of the...

    Question 1: I)-What is the normal cost of this project? II)-What is the cost of the project after 2 days shortening? III)-What is the crashing cost per day for activity G? Given the following data and network, find answer the questions 18-20 if you're asked to finish this project 2 days earlier than its normal duration. Indirect cost (overhead) is $200 per day. 9.12 E 3 1.8 12. 19 10,13 B 7 1,8 13.20 0,1 1,7 8.15 20,25 15.20 F...

  • The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the pr...

    The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given $150 per day. The company will incur a $100 per day penalty for each day the project lasts beyond day 15. the following table. Indirect project costs amount to Normal Time Crash Time Crash Cost Immediate Normal Cost (S) Activity Predecessor(s) (S) (days) (days) 1.200 A 6 800 4 6 1,000 2 2,200 600 900 C...

  • Problem 5-5 Your project to obtain charitable donations is now 41 days into a planned 51-day...

    Problem 5-5 Your project to obtain charitable donations is now 41 days into a planned 51-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 34 days of the project and to bring in $25,700. Even though we are 41 days into the project, we still see that we have only 90% of this activity complete. The second activity relates to company donations and is...

  • The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the pr...

    The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given in the following table. Indirect project costs amount to S150 per day. The company will incur a $100 per day penalty for each day the project lasts beyond day 15. Normal Time Crash Time Crash Cost Immediate Normal Cost ($) Activity (S) (days) (days) Predecessor(s) 6 800 1,200 A 4 6 1,000 2,200 C 600 1...

  • Given the following information for the Macro Economy answer the following questions. In this economy we...

    Given the following information for the Macro Economy answer the following questions. In this economy we have an MPC equal to 0.60, Autonomous Consumption of $100 billion, Planned Investment (I) of $1,000 billion, Government Spending (G) of $1,200 billion and Net Taxes (T) of $500 billion. a) Fill in the missing data in the table below (all the numbers are in billions). Y T Yd C S AE $2,000 500 1,500 1,000 1,000 3,200 $3,000 500 2,500 1,600 1,400 3,800...

  • Given the following information for the Macro Economy answer the following questions. In this economy we...

    Given the following information for the Macro Economy answer the following questions. In this economy we have an MPC equal to 0.60, Autonomous Consumption of $100 billion, Planned Investment (I) of $1,000 billion, Government Spending (G) of $1,200 billion and Net Taxes (T) of $500 billion. a) Fill in the missing data in the table below (all the numbers are in billions). Y T Yd C S AE $2,000 500 1,500 1,000 1,000 3,200 $3,000 500 2,500 1,600 1,400 3,800...

  • Happyland is the only theme park in the nation. The table sets out the demand schedule...

    Happyland is the only theme park in the nation. The table sets out the demand schedule for theme park passes and the cost schedule for running the theme park. Calculate Happyland's profit-maximizing price, output and economic profit if it charges a single price for all passes. Price (dollars per pass) 10 9 passes a day. Happyland's profit-maximizing output is Happyland's profit-maximizing price is $ >>> Answer to 2 decimal places. 8 7 6 Quantity (passes per day) 0 100 200...

  • Project Cycle

    The Advanced Tech Company has a project to design an integrated information database for a major bank. Data for the project are given in Table 1 below. Indirect project costs amount to $300 per day. The company will incur a $150 per day penalty for each day the project lasts beyond day 14.(a) What is the shortest time duration for this project regardless of cost?(30 marks) (b) What is the total cost and time of the minimum-cost schedule?(10 marks)Table 1:...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT