SOLUTION:-
2.) OPTION "A" IS A CORRECT ANSWER
ACTUAL INTEREST COST INCURRED DURING 2017 IS $450,000
($3,600,000 * 9% * 10/12) + ($1500,000 *12%) = $450,000
if you have any query please ask me in comment box i am here to helps you don't give direct Thumbs down.if you satisfied my work give Thumbs UP.
#THANK YOU#
2. On March 1, 2017, Newton Company purchased land for an office site by paying $2,700,000...
On March 1, 2014, Newton Company purchased land for an office site by paying $1,800,000 cash. Newton began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2014 $ 1,200,000 April 1, 2014 1,680,000 May 1, 2014 3,000,000 June 1, 2014 4,800,000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $2,400,000 was borrowed on March 1, 2014 on...
On March 1, 2017, Crane Company purchased land for an office site by paying $2600000 cash. Crane began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2017 $1700000 April 1, 2017 2460000 May 1, 2017 4400000 June 1, 2017 4700000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3500000 was borrowed on March 1, 2017 on a...
On March 1, 2017, Sheridan Company purchased land for an office site by paying $2600000 cash. Sheridan began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2017 $ 1810000 April 1, 2017 2490000 May 1, 2017 4420000 June 1, 2017 4700000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3670000 was borrowed on March 1, 2017 on...
On March 1, 2020, Swifty Corporation purchased land for an office site by paying $2660000 cash. Swifty began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2020 $1750000 April 1, 2020 2480000 May 1, 2020 4530000 June 1, 2020 4710000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3690000 was borrowed on March 1, 2020 on a...
9. On March 1, 2020, Bonita Industries purchased land for an office site by paying $2700000 cash. Bonita began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2020 $ 1700000 April 1, 2020 2490000 May 1, 2020 4590000 June 1, 2020 4890000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3550000 was borrowed on March 1, 2020...
On March 1, 2020, Concord Corporation purchased land for an office site by paying $2740000 cash. Concord began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2020 $ 1790000 April 1, 2020 2530000 May 1, 2020 4490000 June 1, 2020 4880000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3560000 was borrowed on March 1, 2020 on a...
1.On March 1, 2020, Sunland Company purchased land for an office site by paying $2680000 cash. Sunland began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2020 $1780000 April 1, 2020 2510000 May 1, 2020 4510000 June 1, 2020 4720000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3540000 was borrowed on March 1, 2020 on a...
Interest Costs During Construction Comprehensive Illustration: On November 1, 2016, Shalla Company contracted Pfeifer Construction Co. to construct a building for $1,400,000 on land costing S100,000 (purchased from the contractor and included in the first payment). Shalla made the following payments to the construction company during 2017 January 1 $210,000 March 1 $300,000 May 1 $540,000 December 31 $450,000 Total $1,500,000 Interest Costs During Construction Pfeifer Construction completed the building, ready for occupancy, on December 31, 2017. Shalla had the...
On March 1, 2021, Beldon Corporation purchased land as a factory site for $71,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2021. Costs incurred during this period are listed below: Demolition of old building $ 9,500 Architect’s fees (for new building) 10,000 Legal fees for title investigation of land 7,500 Property taxes on land (for period beginning March 1, 2021) 4,100 Construction costs 610,000 Interest on...
On March 1, 2021, Beldon Corporation purchased land as a factory site for $76,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2021. Costs incurred during this period are listed below: Demolition of old building $ 7,000 Architect’s fees (for new building) 15,000 Legal fees for title investigation of land 3,500 Property taxes on land (for period beginning March 1, 2021) 4,600 Construction costs 660,000 Interest on...