On March 1, 2014, Newton Company purchased land for an office site by paying $1,800,000 cash. Newton began construction on the office building on March 1. The following expenditures were incurred for construction:
Date Expenditures
March 1, 2014 $ 1,200,000
April 1, 2014 1,680,000
May 1, 2014 3,000,000
June 1, 2014 4,800,000
The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $2,400,000 was borrowed on March 1, 2014 on a 9%, 3-year note payable. Other than the construction note, the only debt outstanding during 2014 was a $1,000,000, 12%, 6-year note payable dated January 1, 2014.
a) The weighted-average accumulated expenditures on the construction project during 2014 were
b) The actual interest cost incurred during 2014 was
c) Assume the weighted-average accumulated expenditures for the construction project are $2,900,000. The amount of interest cost to be capitalized during 2014 is
Please provide work
a) Weighted-average accumulated expenditures on the construction project during 2014=
($3,000,000 x 4/12) + (1,680,000 x 3/12) + (3,000,000 x 2/12) + (4,800,000 x 1/12) = $2,320,000
b) Actual interest cost incurred during 2014
($2,400,000 x 9% x 10/12) + ($1,000,000 x 12%) = $300,000
c) amount of interest cost to be capitalized during 2014
=($2,400,000 × 9%) + ($500,000 ×12%) = $276,000.
On March 1, 2014, Newton Company purchased land for an office site by paying $1,800,000 cash. New...
2. On March 1, 2017, Newton Company purchased land for an office site by paying $2,700,000 cash. Newton began construction on the office building on March 1. The following expenditures were incurred for construction: Date March 1, 2017 April 1, 2017 May 1, 2017 June 1, 2017 $ 1,800,000 2,520,000 4,500,000 4,800,000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3,600,000 was borrowed on March 1, 2017 on...
On March 1, 2020, Concord Corporation purchased land for an office site by paying $2740000 cash. Concord began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2020 $ 1790000 April 1, 2020 2530000 May 1, 2020 4490000 June 1, 2020 4880000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3560000 was borrowed on March 1, 2020 on a...
On March 1, 2017, Sheridan Company purchased land for an office site by paying $2600000 cash. Sheridan began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2017 $ 1810000 April 1, 2017 2490000 May 1, 2017 4420000 June 1, 2017 4700000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3670000 was borrowed on March 1, 2017 on...
9. On March 1, 2020, Bonita Industries purchased land for an office site by paying $2700000 cash. Bonita began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2020 $ 1700000 April 1, 2020 2490000 May 1, 2020 4590000 June 1, 2020 4890000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3550000 was borrowed on March 1, 2020...
On March 1, 2017, Crane Company purchased land for an office site by paying $2600000 cash. Crane began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2017 $1700000 April 1, 2017 2460000 May 1, 2017 4400000 June 1, 2017 4700000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3500000 was borrowed on March 1, 2017 on a...
1.On March 1, 2020, Sunland Company purchased land for an office site by paying $2680000 cash. Sunland began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2020 $1780000 April 1, 2020 2510000 May 1, 2020 4510000 June 1, 2020 4720000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3540000 was borrowed on March 1, 2020 on a...
On March 1, 2020, Swifty Corporation purchased land for an office site by paying $2660000 cash. Swifty began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2020 $1750000 April 1, 2020 2480000 May 1, 2020 4530000 June 1, 2020 4710000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3690000 was borrowed on March 1, 2020 on a...
On January 1, 2021, the Blackstone Corporation purchased a tract of land (site number 11) with a building for $740,000. Additionally, Blackstone paid a real estate broker's commission of $50,000, legal fees of $8,000, and title insurance of $25,000. The closing statement indicated that the land value was $570,000 and the building value was $170,000. Shortly after acquisition, the building was razed at a cost of $89,000. Blackstone entered into a $4,400,000 fixed-price contract with Barnett Builders, Inc., on March...
On January 1, 2018, the Marjlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in 2019. Construction expenditures for 2018, which were incurred evenly throughout the year, totaled $7,200,000. Marjlee had the following debt obligations which were outstanding during all of 2018: Construction loan, 115 Long-term note, 105 Long-term note, 71 $1,800,000 2,100,000 4,800,000 Required: Calculate the amount of interest capitalized in 2018 for the building using the specific...
On January 1, 2021, the Marjlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in 2022. Construction expenditures for 2021, which were incurred evenly throughout the year, totaled $7,200,000. Marjlee had the following debt obligations which were outstanding during all of 2021:Construction loan, 10%$1,800,000Long-term note, 9%2,400,000Long-term note, 6%4,800,000Required:Calculate the amount of interest capitalized in 2021 for the building using the specific interest method.