1.On March 1, 2020, Sunland Company purchased land for an office site by paying $2680000 cash. Sunland began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2020 $1780000 April 1, 2020 2510000 May 1, 2020 4510000 June 1, 2020 4720000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3540000 was borrowed on March 1, 2020 on a 9%, 3-year note payable. Other than the construction note, the only debt outstanding during 2020 was a $1410000, 12%, 6-year note payable dated January 1, 2020. The actual interest cost incurred during 2020 was
a.$487800.
b.$406500.
c.$243900.
d. $434700.
2.
Concord Corporation constructed a building at a cost of $30650000.
Weighted-average accumulated expenditures were $13000000, actual
interest was $1170000, and avoidable interest was $604000. If the
salvage value is $2490000, and the useful life is 40 years,
depreciation expense for the first full year using the
straight-line method is
a |
$781350. |
b |
$719100. |
c |
$748350. |
d |
$1044100 |
3. A machine cost $1416000, has annual depreciation of $236000,
and has accumulated depreciation of $1121000 on December 31, 2020.
On April 1, 2021, when the machine has a fair value of $324500, it
is exchanged for a machine with a fair value of $1593000 and the
proper amount of cash is paid. The exchange had commercial
substance.
The gain to be recorded on the exchange is
a |
$88500 |
b |
$59000 |
c |
$177000 |
d |
$0 |
Question No. - (1) - Answer -
Step - (1) - Information Given -
On March 1, 2020, Sunland Company purchased land for an office site by paying $2680000 cash. Sunland began construction on the office building on March 1.
The following expenditures were incurred for construction
Date | Expenditures |
March 1, 2020 | $1780000 |
April 1, 2020 | 2510000 |
May 1, 2020 | 4510000 |
June 1, 2020 | 4720000 |
To help pay for construction, and purchase of land $3540000 was borrowed on March 1, 2020 on a 9%, 3-year note payable.
Other than the construction note, the only debt outstanding during 2020 was a $1410000, 12%, 6-year note payable dated January 1, 2020.
.
Step - (2) - Calculation of Actual interest cost incurred during 2020 -
= [ Amount borrowed * Interest rate * Month ] + [ Debt amount outstanding * Interest rate * Month ]
= [ $3540000 * 9% * 10 / 12 ] + [ $1410000 * 12% * 12 / 12 ]
= $265500+ $169200
= $434700.
.
Step - (3) - Conclusion -
Therefore, Option - (d), is Correct, because actual interest cost incurred during 2020 is $434700.
1.On March 1, 2020, Sunland Company purchased land for an office site by paying $2680000 cash....
On March 1, 2020, Swifty Corporation purchased land for an office site by paying $2660000 cash. Swifty began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2020 $1750000 April 1, 2020 2480000 May 1, 2020 4530000 June 1, 2020 4710000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3690000 was borrowed on March 1, 2020 on a...
On March 1, 2020, Concord Corporation purchased land for an office site by paying $2740000 cash. Concord began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2020 $ 1790000 April 1, 2020 2530000 May 1, 2020 4490000 June 1, 2020 4880000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3560000 was borrowed on March 1, 2020 on a...
9. On March 1, 2020, Bonita Industries purchased land for an office site by paying $2700000 cash. Bonita began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2020 $ 1700000 April 1, 2020 2490000 May 1, 2020 4590000 June 1, 2020 4890000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3550000 was borrowed on March 1, 2020...
On March 1, 2014, Newton Company purchased land for an office site by paying $1,800,000 cash. Newton began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2014 $ 1,200,000 April 1, 2014 1,680,000 May 1, 2014 3,000,000 June 1, 2014 4,800,000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $2,400,000 was borrowed on March 1, 2014 on...
On March 1, 2017, Crane Company purchased land for an office site by paying $2600000 cash. Crane began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2017 $1700000 April 1, 2017 2460000 May 1, 2017 4400000 June 1, 2017 4700000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3500000 was borrowed on March 1, 2017 on a...
On March 1, 2017, Sheridan Company purchased land for an office site by paying $2600000 cash. Sheridan began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2017 $ 1810000 April 1, 2017 2490000 May 1, 2017 4420000 June 1, 2017 4700000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3670000 was borrowed on March 1, 2017 on...
2. On March 1, 2017, Newton Company purchased land for an office site by paying $2,700,000 cash. Newton began construction on the office building on March 1. The following expenditures were incurred for construction: Date March 1, 2017 April 1, 2017 May 1, 2017 June 1, 2017 $ 1,800,000 2,520,000 4,500,000 4,800,000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3,600,000 was borrowed on March 1, 2017 on...
On January 1, 2020, Marin Corporation purchased for $720,000 a tract of land (site number 101) with a building. Marin paid a real estate broker's commission of $51,840, legal fees of $8,640, and title guarantee insurance of $25,920. The closing statement indicated that the land value was $720,000 and the building value was $144,000. Shortly after acquisition, the building was razed at a cost of $77,760. Marin entered into a $4,320,000 fixed-price contract with Slatkin Builders, Inc. on March 1,...
Problem 10-5 On January 1, 2020, Sheridan Corporation purchased for $680,000 a tract of land (site number 101) with a building. Sheridan paid a real estate broker’s commission of $48,960, legal fees of $8,160, and title guarantee insurance of $24,480. The closing statement indicated that the land value was $680,000 and the building value was $136,000. Shortly after acquisition, the building was razed at a cost of $73,440. Sheridan entered into a $4,080,000 fixed-price contract with Slatkin Builders, Inc. on...
On January 1, 2020, Marigold Corporation purchased for $680.000 a tract of land (site number 101) with a building Marigold paid a real estate broker's commission of $48,960, legal fees of $8,160, and title guarantee insurance of $24.480. The dosing statement indicated that the land value was $680,000 and the building value was $136,000. Shortly after acquisition, the building was razed at a cost of $73,440. Marigold entered into a $4,080,000 fixed-price contract with Slatkin Builders, Inc. on March 1,...