On March 1, 2017, Sheridan Company purchased land for an office
site by paying $2600000 cash. Sheridan began construction on the
office building on March 1. The following expenditures were
incurred for construction:
Date | Expenditures | |
March 1, 2017 | $ 1810000 | |
April 1, 2017 | 2490000 | |
May 1, 2017 | 4420000 | |
June 1, 2017 | 4700000 |
The office was completed and ready for occupancy on July 1. To help
pay for construction, and purchase of land $3670000 was borrowed on
March 1, 2017 on a 9%, 3-year note payable. Other than the
construction note, the only debt outstanding during 2017 was a
$1470000, 12%, 6-year note payable dated January 1, 2017.
Assume the weighted-average accumulated expenditures for the
construction project are $4370000. The amount of interest cost to
be capitalized during 2017 is
$414300. |
$150550. |
$168900. |
$131100. |
If it is helpful, please rate the answer and if any doubt arises let me know
Correct option is: $414,300 | ||||||
Workings: | ||||||
Interest Capitalized in 2017 | ||||||
$ 43,70,000 | ||||||
Less: | $ 36,70,000 | X | 9.00% | = | $ 3,30,300 | |
$ 7,00,000 | X | 12.00% | = | $ 84,000 | ||
Total Interest Capitalized in 2017 | = | $ 4,14,300 |
On March 1, 2017, Sheridan Company purchased land for an office site by paying $2600000 cash. Sheridan began constructio...
On March 1, 2017, Crane Company purchased land for an office site by paying $2600000 cash. Crane began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2017 $1700000 April 1, 2017 2460000 May 1, 2017 4400000 June 1, 2017 4700000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3500000 was borrowed on March 1, 2017 on a...
On March 1, 2020, Swifty Corporation purchased land for an office site by paying $2660000 cash. Swifty began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2020 $1750000 April 1, 2020 2480000 May 1, 2020 4530000 June 1, 2020 4710000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3690000 was borrowed on March 1, 2020 on a...
On March 1, 2020, Concord Corporation purchased land for an office site by paying $2740000 cash. Concord began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2020 $ 1790000 April 1, 2020 2530000 May 1, 2020 4490000 June 1, 2020 4880000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3560000 was borrowed on March 1, 2020 on a...
On March 1, 2014, Newton Company purchased land for an office site by paying $1,800,000 cash. Newton began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2014 $ 1,200,000 April 1, 2014 1,680,000 May 1, 2014 3,000,000 June 1, 2014 4,800,000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $2,400,000 was borrowed on March 1, 2014 on...
2. On March 1, 2017, Newton Company purchased land for an office site by paying $2,700,000 cash. Newton began construction on the office building on March 1. The following expenditures were incurred for construction: Date March 1, 2017 April 1, 2017 May 1, 2017 June 1, 2017 $ 1,800,000 2,520,000 4,500,000 4,800,000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3,600,000 was borrowed on March 1, 2017 on...
9. On March 1, 2020, Bonita Industries purchased land for an office site by paying $2700000 cash. Bonita began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2020 $ 1700000 April 1, 2020 2490000 May 1, 2020 4590000 June 1, 2020 4890000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3550000 was borrowed on March 1, 2020...
1.On March 1, 2020, Sunland Company purchased land for an office site by paying $2680000 cash. Sunland began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2020 $1780000 April 1, 2020 2510000 May 1, 2020 4510000 June 1, 2020 4720000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3540000 was borrowed on March 1, 2020 on a...
Problem 10-5 On January 1, 2020, Sheridan Corporation purchased for $680,000 a tract of land (site number 101) with a building. Sheridan paid a real estate broker’s commission of $48,960, legal fees of $8,160, and title guarantee insurance of $24,480. The closing statement indicated that the land value was $680,000 and the building value was $136,000. Shortly after acquisition, the building was razed at a cost of $73,440. Sheridan entered into a $4,080,000 fixed-price contract with Slatkin Builders, Inc. on...
Sheridan Company is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6380000 on March 1, $5350000 on June 1, and $8150000 on December 31. Sheridan Company borrowed $3250000 on January 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 3-year, $6360000 note payable and an 11%, 4-year, $12450000 note payable. What amount of interest should be charged to...
On January 1, 2020, Marin Corporation purchased for $720,000 a tract of land (site number 101) with a building. Marin paid a real estate broker's commission of $51,840, legal fees of $8,640, and title guarantee insurance of $25,920. The closing statement indicated that the land value was $720,000 and the building value was $144,000. Shortly after acquisition, the building was razed at a cost of $77,760. Marin entered into a $4,320,000 fixed-price contract with Slatkin Builders, Inc. on March 1,...