Question

9. On March 1, 2020, Bonita Industries purchased land for an office site by paying $2700000 cash. Bonita began construction o

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans:

1.Weighted average expenditure=

[4,400,000*4//12]+[2,490,000*3/12]+[4,590,000*2/12]+[4,890,000*1/12]

                = 1,466,667+ 622,500+ 765,000+407,500

                   = $ 3,261,667

Note:

**Initial cost: 2,700,000 land+1,700,000 = 4,400,000

The construction is completed on july1 so expenditure will be capitalised only for period 1-Mar to-1 July out of total 12 months.

2 .Actual Interest cost incurred during 2020:

$35,50,000*9/100*10/12+1580,000*12/100*12/12=

=266,250+189,600

=455,850

3.

Amount of interest cost to be capitalized during 2020

=($3,550,000 × 9%) + ($850,000 ×12%) = $412,500

Add a comment
Know the answer?
Add Answer to:
9. On March 1, 2020, Bonita Industries purchased land for an office site by paying $2700000...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On March 1, 2017, Crane Company purchased land for an office site by paying $2600000 cash....

    On March 1, 2017, Crane Company purchased land for an office site by paying $2600000 cash. Crane began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2017 $1700000 April 1, 2017 2460000 May 1, 2017 4400000 June 1, 2017 4700000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3500000 was borrowed on March 1, 2017 on a...

  • On March 1, 2020, Concord Corporation purchased land for an office site by paying $2740000 cash....

    On March 1, 2020, Concord Corporation purchased land for an office site by paying $2740000 cash. Concord began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2020 $  1790000 April 1, 2020 2530000 May 1, 2020 4490000 June 1, 2020 4880000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3560000 was borrowed on March 1, 2020 on a...

  • On March 1, 2020, Swifty Corporation purchased land for an office site by paying $2660000 cash....

    On March 1, 2020, Swifty Corporation purchased land for an office site by paying $2660000 cash. Swifty began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2020 $1750000 April 1, 2020 2480000 May 1, 2020 4530000 June 1, 2020 4710000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3690000 was borrowed on March 1, 2020 on a...

  • On March 1, 2017, Sheridan Company purchased land for an office site by paying $2600000 cash. Sheridan began constructio...

    On March 1, 2017, Sheridan Company purchased land for an office site by paying $2600000 cash. Sheridan began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2017 $   1810000 April 1, 2017 2490000 May 1, 2017 4420000 June 1, 2017 4700000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3670000 was borrowed on March 1, 2017 on...

  • On March 1, 2014, Newton Company purchased land for an office site by paying $1,800,000 cash. New...

    On March 1, 2014, Newton Company purchased land for an office site by paying $1,800,000 cash. Newton began construction on the office building on March 1. The following expenditures were incurred for construction: Date                                                   Expenditures March 1, 2014                                  $   1,200,000 April 1, 2014                                          1,680,000 May 1, 2014                                          3,000,000 June 1, 2014                                         4,800,000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $2,400,000 was borrowed on March 1, 2014 on...

  • 2. On March 1, 2017, Newton Company purchased land for an office site by paying $2,700,000...

    2. On March 1, 2017, Newton Company purchased land for an office site by paying $2,700,000 cash. Newton began construction on the office building on March 1. The following expenditures were incurred for construction: Date March 1, 2017 April 1, 2017 May 1, 2017 June 1, 2017 $ 1,800,000 2,520,000 4,500,000 4,800,000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3,600,000 was borrowed on March 1, 2017 on...

  • 1.On March 1, 2020, Sunland Company purchased land for an office site by paying $2680000 cash....

    1.On March 1, 2020, Sunland Company purchased land for an office site by paying $2680000 cash. Sunland began construction on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2020 $1780000 April 1, 2020 2510000 May 1, 2020 4510000 June 1, 2020 4720000 The office was completed and ready for occupancy on July 1. To help pay for construction, and purchase of land $3540000 was borrowed on March 1, 2020 on a...

  • On January 2, 2020, Bonita Industries began construction of a new citrus processing plant. The automated...

    On January 2, 2020, Bonita Industries began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 September 1, 2020 December 31, 2020 March 31, 2021 September 30, 2021 $ 609000 1812000 1812000 812000 198000 1 1 Bonita Industries borrowed $3290000 on a construction loan at 12% interest on January 2, 2020. This loan was outstanding during the construction period....

  • Bonita Industries is constructing a building. Construction began on January 1 and was completed on December...

    Bonita Industries is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6440000 on March 1, $5260000 on June 1, and $8850000 on December 31. Bonita Industries borrowed $3190000 on January 1 on a 5-year, 11% note to help finance construction of the building. In addition, the company had outstanding all year a 9%, 3-year, $6440000 note payable and an 10%, 4-year, $12650000 note payable. What are the weighted-average accumulated expenditures? $11700000 $9860000...

  • On January 1, 2020, Marin Corporation purchased for $720,000 a tract of land (site number 101)...

    On January 1, 2020, Marin Corporation purchased for $720,000 a tract of land (site number 101) with a building. Marin paid a real estate broker's commission of $51,840, legal fees of $8,640, and title guarantee insurance of $25,920. The closing statement indicated that the land value was $720,000 and the building value was $144,000. Shortly after acquisition, the building was razed at a cost of $77,760. Marin entered into a $4,320,000 fixed-price contract with Slatkin Builders, Inc. on March 1,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT