Question


Use the information given in the figure below to determine the critical path. Mention path length of each path calculation. I
0 0
Add a comment Improve this question Transcribed image text
Answer #1

The different paths to finish are

  1. A-B-G= 7+9 =16 Days
  2. A-B-D-E-G= 7+7+2+4 =20 Days
  3. A-B-D-E-F-G= 7+7+2+2+4 =22 Days
  4. A-C-D-E-G= 5+4+2+4 =15 Days
  5. A-C-D-E-F-G= 5+4+2+2+4 =17 Days

Critical path is identified from all the path as the path which is taking maximum time for completion of project/Work.

The critical path is shown in the figure with red colour arrows :

B 9 days G Finish 7 days Start A 7 days E 4 days D 4 days 2 days 2 day 5 days 4 days F

The critical path is Path 3: A-B-D-E-F-G. Which is taking is maximum time of 22 days for finishing the work/Project.

Please like the answer, Thank you

Add a comment
Know the answer?
Add Answer to:
Use the information given in the figure below to determine the critical path. Mention path length...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT