 Find the sequence that minimizes the total elapsed time required to complet the following tasks (in hrs) on series of Machine-I and Machine-II: Task:      

                 A   B  C  D   E   F   G    H 

Machine-I: 6  2   8   9   9   6    7    6 

Machine-II:8  7   3   6   4  10   4    8 

 

Calculate the minimum elapsed time and idle times of machine-I and machine-II. Identify the task which has to wait more time for machine-II. 


0 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 10 more requests to produce the answer.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
Operation research
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A...

    For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A 45 - B 11 A C 9 B D 50 - E 26 D F 11 E G 12 C H 10 C I 9 F, G, H J 10 I 193 b. Determine the minimum and maximum cycle times in seconds for a desired output of 500 units in a seven-hour day. (Round your answers to 1 decimal place.)    The minimum cycle...

  • . The operation manager of a body and paint shop has five cars to schedule for...

    . The operation manager of a body and paint shop has five cars to schedule for repair. He would like to minimize throughput time to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body and paint work on each are listed below. (a) Determine the job sequence using the Johnson rule. (b) How much idle time is related to painting? (use a chart to find...

  • 3. A manager wants to assign tasks to workstations in order to achieve an hourly output...

    3. A manager wants to assign tasks to workstations in order to achieve an hourly output rate of four units. The depart- working time of 56 minutes per hour. ment uses a Assign the tasks shown in the following precedence network (times are on the nodes and are in minutes) to workstations using the following heuristic rules: (i) Assign the task with the largest positional weight. (ii) Tiebreaker: "Assign the task with the longest time." If a tie still exists,...

  • Agent Smith, operations manager at the Matrix franchise, faces assembly line balancing problems. He has been...

    Agent Smith, operations manager at the Matrix franchise, faces assembly line balancing problems. He has been told that the firm needs to assemble 1400 agents per day. There are 420 minutes of productive time in each working day. The assembly line activities are given below: Task Time (seconds) Predecessor A 13 - B 4 A C 10 B D 10 - E 6 D F 12 E G 5 E H 6 F, G I 7 H J 5 H...

  • You have been asked to balance a flow shop assembly operation to achieve an output rate...

    You have been asked to balance a flow shop assembly operation to achieve an output rate of 80 units over two eight-hour shifts - 16 hours. Task times and precedence relationships are shown in the table below: Task Predecessor Time (minutes) A -- 2 B A 4 C 7 D A, B 11 E C 9 F D 10 G E, F 7 H D, G 4 What is the cycle time in minutes? What is the theoretical number of...

  • OPERATIONS AND SUPPLY CHAIN MANAGEMENT L06-4 SOLVED PROBLEM 2 TASKS THAT MUST PRECEDE TASK TIME (SECONDS)...

    OPERATIONS AND SUPPLY CHAIN MANAGEMENT L06-4 SOLVED PROBLEM 2 TASKS THAT MUST PRECEDE TASK TIME (SECONDS) 50 TASK A B С D E F G H 40 20 45 20 25 10 35 A С С D E B, F, G a. Draw the schematic diagram. b. What is the theoretical minimum number of stations required to meet a forecast demand ei 400 units per eight-hour day? c. Use the longest-task-time rule and balance the line in the minimum number...

  • Solve the following Job Sequencing problem. Draw Gantt chart. Find total time elapsed to complete the...

    Solve the following Job Sequencing problem. Draw Gantt chart. Find total time elapsed to complete the jobs and idle time for machines. Job/Machine M1 M2 M3 1 5 9 8 2 3 6 7 3 4 7 6 4 2 8 9 5 6 7 5 6 4 6 9

  • Dr. John Watage, deputy director of the family planning Research Center in Nigeria’s Over-The-River Providence, was...

    Dr. John Watage, deputy director of the family planning Research Center in Nigeria’s Over-The-River Providence, was assigned the task of organizing and training five teams of field workers to perform educational and outreach activities as part of a large project to demonstrate acceptance of a new method of birth control.  These workers already had training in family planning education but must receive specific training regarding the new method of contraception.  Two types of materials must also be prepared: (1) those for use...

  • Dr. John Watage, deputy director of the family planning Research Center in Nigeria’s Over-The-River Providence, was...

    Dr. John Watage, deputy director of the family planning Research Center in Nigeria’s Over-The-River Providence, was assigned the task of organizing and training five teams of field workers to perform educational and outreach activities as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those...

  • Case #2 Table 2 Family Planning Research Center Costs Activity A В. Crash Time (days) 3...

    Case #2 Table 2 Family Planning Research Center Costs Activity A В. Crash Time (days) 3 4 2 1 3 Normal Time (days) 6 8 4 3 7 5 3 6 7 10 10 Dr. John Watage, deputy director of the family planning Research Center in Nigeria's Over-The-River Providence, was assigned the task of organizing and training five teams of field workers to perform educational and outreach activities as part of a large project to demonstrate acceptance of a new...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT