During these project objectives, you will work with project scope and handling changes to prevent catastrophic failure to the project. The project scope is usually defines as the use-case documentation is created and approved. The project manager should finally get signatures from the other managers when everyone agrees on the final draft of the project. The final draft is the scope and it will typically not change unless there is a change request. At the bottom of the project use-case documentation, add a signature page for all required manager signatures. Make sure the signature page looks and feels professional which should include the date of when a manager signed the use-case documentation for approval. You have more objectives in the course to build and integrate into your documentation but this should always be the last page of the document. Next document a typical scenario that might actually be a good reason to change the scope of a project. For instance, the documentation might not include form validation controls. As the users are testing, the validation is always necessary to keep the data clean in the database. Create your own scenario that could change the scope of the project and would cause the managers to agree and accept the change request. Document the change request procedure. This professional procedure would be used in a business when a tester found an issue that requires a project change and the requestor would need to follow through each step before the change would even be considered. Document the procedure in a chronological order as if each step was a checklist.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Change Management Process for External Facia Change for Front Loading Washing Machine

1) Purpose:

The purpose of this document is to provide the project manager, sponsors and all other stakeholders with a standard process for managing changes on "Facia Change for Front Loading Washing Machine". This is also to manage change requests so that approved changes will be controlled, ensuring the project remains on schedule, within budget and provides the agreed deliverables.

2) Objectives:

The primary objectives of change management are to:

  • manage each change request from initiation through to closure;
  • process change requests based upon direction from the appropriate authority;
  • communicate the impact of changes to appropriate personnel; and
  • allow small changes to be managed with a minimum of overhead.

In this case the design change of the facia to uplift the looks of the washineg machine.

3) Scope:

The scope is to have the face change of the Front Loading Washing Machine without changing the basic platform.

4) Change Management Documents:

4.1 Change Request Form

The ‘Change Request Form’ is used to identify and describe a proposed change to the project.

Change of the Facia for the following models (vix. WM1....WN10) with part nos. (X1,.... Xn)

4.2 CID (Change Issue, Decision) Log

This is used for tracking no. of version changes of the facia or any other parts for the washing machine model or variants.

5) Change Management Roles:

5.1 Project Manager/Lead

A team member initially recognizes a need for change to the project and formally communicates this requirement to the Project Manager and/or Lead. The Project Manager and/or Lead are then responsible for:

  • Identifying the requirement to make a change to the project- e.g. BOM change, System change, Stock back flashing, etc.
  • Documenting the requirement by completing a Change request form (CRF)
  • Submitting the CRF to "Facia change for Front Loading Washing Machine" Leadership for review.

5.2 Project Managers

The Project Manager receives, logs, monitors and controls the progress of all changes within the project. The Project Managers are responsible for:

  • Documenting and or receiving all CRFs and logging them in the CID Log
  • Reviewing all CRFs to determine whether additional information is required
  • Forwarding the CRF to "Project Name" Leadership for approval
  • Escalating all CRF issues and risks to "Project Name" Leadership
  • Reporting and communicating all decisions made by "Project Name" Leadership
  • Close the Change Request and update the CID Log when completed

5.3 "Project Name" Leadership (CIO, Program Manager, Business Sponsor)

"Project Name" Leadership is the Steering Committee or other authorized body who is the principal authority for all CRFs forwarded by the Project Manager. "Project Name" Leadership is responsible for:

  • Reviewing all CRFs forwarded by the Project Manager
  • Categorizing and prioritizing all CRFs
  • Considering all supporting documentation
  • Approving / rejecting each CRF based on its relevant merits and when necessary escalating to the executive steering committee.
  • Resolving change conflict (where 2 or more changes overlap)

6) Procedure:

The use of the formal change management procedure will be required when any changes are discovered or requested which impact previously reviewed, approved and published project deliverables.

The documentation and tracking of all change requests will be managed using the defined procedure and facilitated by the use of the CID log.

6.1 Identify and Submit a Change Request

This process provides the ability to submit a request for a change to the project. The Change Requester:

  • Identifies a requirement for change to any aspect of the project (e.g. scope, deliverables, timescales and organization)
  • Completes a Change Request Form (CRF) and distributes the form to the Project Manager. The CRF summarizes the change:
  • -Description- Facia Change for VIBS WM1... WM10 with the part no. x1... xn.
  • -Reasons- Reduction in cost and better look
  • -Benefits- User friendly and trendy
  • -Costs- Cheaper
  • -Any supporting documentation- relavent drawings and part list.
  • -Approvals

6.2 Review the Change Request

The Project Manager and Lead reviews the CRF and determines whether or not additional information is required for "Project Name" Leadership to assess the full impact of the change to the project time, scope and cost. The decision will be based on factors, such as:

  • Number of change options presented
  • Feasibility and benefits of the change
  • Complexity and/or difficulty of the change options requested
  • Scale of the change solutions proposed.

The Project Manager will record the CRF details in the CID Log to track the status of the change request.

6.3 Approval of the Change Request

  • Impact on the project in implementing the change (time, resources, finance, quality).

After a formal review, "Project Name" Leadership may:

reject or accept or request for modification.

6.4 Closing the Change Request

If the change is approved, the following will occur:

  • The change will be communicated to the team
  • Project deliverables will be updated to reflect the change
  • The change request will be closed on the CID Log
  • All approved change requests will be communicated in the "Project Name" status report
Add a comment
Know the answer?
Add Answer to:
During these project objectives, you will work with project scope and handling changes to prevent catastrophic...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Assignment Details Scenario You have been asked to be the project manager for the development of...

    Assignment Details Scenario You have been asked to be the project manager for the development of an information technology (IT) project. The system to be developed will allow a large company to coordinate and maintain records of the professional development of its employees. The company has over 30,000 employees who are located in four sites: Florida, Colorado, Illinois, and Texas. The system needs to allow employees to locate and schedule professional development activities that are relevant to their positions. Sophisticated...

  • !!!Only Project 2 need to be answered!!! Project Report 1 Once the business case has been approved, you need to make a...

    !!!Only Project 2 need to be answered!!! Project Report 1 Once the business case has been approved, you need to make a project plan showing each task. Assume you are a project manager to lead your team to acquire an additional delivery van for the company. Please find the details below. The current month is January. Activity (What is to be done?) Objective (Why will we do it?) Resources (Where will it be done?) Procedures (How will it be done?)...

  • 1 You are project manager in a global project with a team consisting of people from...

    1 You are project manager in a global project with a team consisting of people from various countries. What can you try to prevent misunderstandings due to cross-cultural differences? a Use all communication methods available that are suitable for the team and follow up in writing when communicating verbally. Remember that cultural and individual diversity may help project teams solving unforeseen problems during the course of the project. b When you are about to form a team for your project,...

  • Part 2: Project Scope Management Congratulations! You have been selected as the project manager for the...

    Part 2: Project Scope Management Congratulations! You have been selected as the project manager for the Green Computing Research Project. The company’s CIO, Ben, is the project sponsor, and Ito is the program manager for the larger Environmental Technologies Program that this project is part of. Now you need to put together your project team and get to work on this high-visibility project. You will work with Ben to handpick your team. Ben had already worked with the HR department...

  • RADICO’S CHALLENGE The executive staff at Radico Corporation was quite pleased with the one-day training program...

    RADICO’S CHALLENGE The executive staff at Radico Corporation was quite pleased with the one-day training program they attended on the benefits of using agile and Scrum on some of their projects. Radico provided products and services to both public and private sector clients, almost all of it through competitive bidding. IT was not required for any of the products and services Radico provided. Agile and Scrum had proven to be successful on internal IT projects, but there were some concerns...

  • can you make 200 words introduction for this please This page will close and will not...

    can you make 200 words introduction for this please This page will close and will not allow further submissions after this Late Submission period has expired. nately per day for three days. . In the event of an emergency situation preventing you from submitting within this time frame, special permission must be obtained from your instructor. Documentation substantiating emergency is required. In such a circumstance, if the extension is granted, the professor will reopen the submission function for you on...

  • Performance Improvement programs and effective project management require an understanding of the four phases of the...

    Performance Improvement programs and effective project management require an understanding of the four phases of the project life-cycle: initiation, planning, execution/implementation, and closure. It is important to have each phase of the project mapped on a timeline and to be sure the project team has the appropriate members with the right skills to ensure a successful program. Using a case study from the text, students will demonstrate their ability to review and evaluate a performance improvement program by arranging the...

  • BUSINESS ADMINISTRATION DUE DATE: 17 MAY 2019 PROJECT 2: BUSINESS ADMINISTRATION 2A n went online in 1995, the e-commerce juggernaut has undergone a slew of changes- despite , during the ensuing t...

    BUSINESS ADMINISTRATION DUE DATE: 17 MAY 2019 PROJECT 2: BUSINESS ADMINISTRATION 2A n went online in 1995, the e-commerce juggernaut has undergone a slew of changes- despite , during the ensuing two-plus decades. When the Seattle-based company d its website, all it sold was books, Gradally, Bezos and his team expanded Amazon's offerings to include things like CDs and DVDs. But Amazon never really stopped changing the inventory it sold. Bezos said he Ever since Amazo being led by the...

  • Please read through the article below and answer the question at the end of the article....

    Please read through the article below and answer the question at the end of the article. What Are the Project Management Knowledge Areas? PMI created a set of standard terminology and guidelines for project management, which is known as the project management knowledge areas. This is an evolving standard that is updated periodically in its PMBOK. Project management knowledge areas coincide with the process groups, which are project initiation, project planning, project execution, monitoring and controlling, and project closing. These...

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT