PROBLEM 3: ACTIVITY-ON-THE-NODE PROBLEM FOR PRECEDENCE DIAGRAM. Figure A-3 shows an activity on the node of...
Using the precedence table given, draw an activity-on-node diagram network and determine the ESD EFD. LSDLFD, and Te for each activity. What is the critical path for this project? activity duration (months predecessor O A-D-GH O ACE-GH O A-C-F-H O A-B-F-H • Previous Next
Assignment #2 is to provide a problem statement, WBS diagram, activity listing, and precedence diagram. Deliverables for HW2 shall include: · A Project Statement For the attached example (see item 3 below), the Project Statement is: “Owner to design and build a new residence. Hiring and oversight of architectural, design, and construction professionals will be managed by the Owner. All materials and permits will be provided by the Owner.” · An Activity Listing The activity listing should be prepared and...
Problem #2 (25 points) For the project below, choose a random duration for each activity (Activity A already has a duration of 3). Calculate the ES, EF, LS, LF, TF and FF for all activities. Use the legend shown below for each activity and highlight the critical path. Fill the answers in the activity's boxes shown below. F с E H A 3 D G Legend: ES TF EF FF Activity LS Duration LF
Activity Duration Precedence Problem# 3 For the project information given below (wecks) information a) Draw the network diagram to accurately B must be after C represent the information given C must be after A 10 15 b) Determine the earliest start, earliest D must be after B E must be after C F must be after D and E G must be after F H must be after G 1 must be after F finished, latest start, latest finish for...
I request the answer for this question please; Their are similar questions but I need specifically the answer of the question I posted Thank you 4. Compute the early start, early finish, late start, and late finish dates and floats (total float and free float) for the activities of the project shown below. Identify the critical activities on the AON diagram. Draw an early bar chart for the project and show critical activities. TF= TF = TF= FS= -2 TF...
1. Given the major activities and their duration for a building project as follows: Activity DurationSuccessors B,C D,E,F HI,J K,L L,M K,L 10 4 (a) Draw the precedence network. (b) Calculate the EST, EFT, LST and LFT of each activity using the forward pass and backward pass methods entire project about a delay of the activity D by 3 days? (Remark: please redraw the diagram to verify (c) Highlight/identify the critical path in the precedence network and find the duration...
Draw the bar chart, and Precedence Diagram for the given project and highlight the critical path. Determine the project total duration, ES, EF, LS, LF, and TF for each given activity. + Activity Description Duration Predecessor A Move in 2 B Set up Scaffolds 3 A C Tear off Shingles 3 B ID Inspect Roof Truss & Deck 2 C E Remove Old Shingles 3 C IF Purchase New Shingles G G Install New Shingles 15 C,D H 3 G...
For each of the following predecessor tables (Tables A-C): 1. 2. 3. 4. 5. Draw a corresponding AON network. Compute EST and EFT for each activity and complete the table. Compute LST and LFT for each activity and complete the table. Find and mark the critical path. Determine the total float and free float and complete the table. Table B Activity Duration Preceding Activity ES EF LSLF TF FF 0 60600 4 A, B 10 D, E C,F.G C, G...
Problem 3 A project for improving a billing process has the following precedence relationships and activity times: Activity Time (weeks) Activity Immediate Predecessor(s) A В 7 C 7 A В, С D 14 Е 10 5 D E Н F, G a. Choose the correct network diagram below. O A. O B. в O C. O D. S в Problem 3 Question Help O D. O C b. Calculate the slack for each activity. Which activities are on the critical...
3 & 15. For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Repeat exercise 3 with an imposed finish date of 15 and then 20 days. Activity Duration IPA ES EF LS LF TF FF A 2 - B 4 A C 6 A D 9 A E 5 B F 7 B, C G 3 D, E, F