Question

2. A major home appliances company produces compressors for their refrigerators in one of their plants. The most critical par

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Sand Casting One Molling Operation I Sand blasting Orinding I Cooting | Dogory NoHk Quality Cheek | Assembly Nota en LOK Fras

Question no "a" ref attached image

For "b"

Improvement no 1

Quality Checking should be in each process

In existing process quality checking is present after almost the entire process completion. The quality of product should be checked in each process it will eliminate the possibility of bulk rejection in the final stage.It will save the 4M's of the manufacturing system. In every process starting station there should be on Stage inspector has to verify the initial out come of the part. Based on his inspection report only further production has to done.it will eliminate investigation done in after assembling the parts. it reduces the rework cost

Improvement no 2

FIFO need to follow up in every process

in existing process flow there is no mentioning in first in first out

Jobs are getting placed by batch in current process. FIFO followed means there is stagnation of job getting lagged between stations. It will help in clearing the inventory also

Add a comment
Know the answer?
Add Answer to:
2. A major home appliances company produces compressors for their refrigerators in one of their plants....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • summatize the following info and break them into differeng key points. write them in yojr own...

    summatize the following info and break them into differeng key points. write them in yojr own words   apartus 6.1 Introduction—The design of a successful hot box appa- ratus is influenced by many factors. Before beginning the design of an apparatus meeting this standard, the designer shall review the discussion on the limitations and accuracy, Section 13, discussions of the energy flows in a hot box, Annex A2, the metering box wall loss flow, Annex A3, and flanking loss, Annex...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT