It is week 1 and there are currently 10 As in stock. We need 300 As...

It is week 1 and there are currently 10 As in stock. We need 300 As at the start of week 5. If there are scheduled receipts planned for week 3 and week 4 of 120 As each and A has a lead time of 1 week, when and how large of an order should be placed to meet the requirement of 300 As?

Four A washers, five B washers, two C bolts, and two D bolts are required to make one grill parts kit. If 100 grill parts kits are needed, how many more washers will be consumed than bolts?

Consider the following product structure. Fifty units of Product A are needed. How many units of F are needed?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

We have 10A at the start of week 1. We need 300A at the start of Week 5. As we get 120+120A at the start of week 3 and 4. Which leads to 250A (in total) at the seat of week 4. To have 300A at the start of week 5 we need 50A more and they are ordered at the start of week 4 as it has a lead time of 1 week.

One grill require 5 washer and 2 bolts which means to make 1 grill we need 3B more washer which leads to 300 more washer if we need 100grills.

Add a comment
Know the answer?
Add Answer to:
It is week 1 and there are currently 10 As in stock. We need 300 As...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 5 6 CD-ROM drivers: Lead Time = 1 week: Minimum order quantity = 15,500 Week 1...

    5 6 CD-ROM drivers: Lead Time = 1 week: Minimum order quantity = 15,500 Week 1 2 3 4 Gross requirements Scheduled receipts Projected ending inventory: 1,000 Net requirements Planned receipts Planned orders Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level...

  • Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a...

    Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level O kits. Complete the MRP records, using the following information: • Production plans for complete kits are as follows: Start assembling 8,000 kits in week 2 Start assembling 2,500 kits in weeks 3,...

  • Suppose that there is incoming demand of 179 units of a certain product at the start...

    Suppose that there is incoming demand of 179 units of a certain product at the start of 3, and 91 units of the same product at the start of week 6. Scheduled receipts of 120 are planned for week 2, and 90 for week 5. The product has a lead time of 1 week and must be ordered in batches of s. When, and how large of an order should be placed to meet the requirements in weeks 3 and...

  • Given the information shown, if there are currently 200 units available, the batch size is 500,...

    Given the information shown, if there are currently 200 units available, the batch size is 500, and lead time is two weeks, planned order releases will be needed in weeks ____. Week 1 2 3 4 Gross Requirements 320 360 300 380 Scheduled Receipts 500 A. 1 and 2 B. 1 and 3 C. 2 and 3 D. None of the above

  • Week 1 2 3 4 5 6 7 8 9 10 Demand 41 44 84 42...

    Week 1 2 3 4 5 6 7 8 9 10 Demand 41 44 84 42 84 86 7 18 49 30 End item A has a planned lead time of two weeks. There are currently 120 units on hand and no scheduled receipts. a. Compute the planned order releases using lot-for-lot b. Compute the planned order releases using part-period balancing where the ratio of the setup cost to the holding cost is 200 c. Compute the planned order releases...

  • Eighty units of end item X are needed at the beginning of week 6, and another...

    Eighty units of end item X are needed at the beginning of week 6, and another 30 units are needed at the beginning of week 8 B(2) D(3) D(2) F(2) Prepare a material requirements plan for component D. D can only be ordered in whole cases (50 units per case). One case of D is automatically received every other week, beginning in week 1 (i.e., weeks 1, 3, 5, 7). Also, there are 30 units of B and 20 units...

  • Problem 14-5 To simplify data handling to include the receipt of orders that have actually been...

    Problem 14-5 To simplify data handling to include the receipt of orders that have actually been placed in previous periods, the following six-level scheme can be used. (A number of different techniques are used in practice, but the important issue is to keep track of what is on hand, what is expected to arrive, what is needed, and what size orders should be placed.)      One unit of A is made of three units of B, one unit of C, and...

  • Assume that Product Z is made of two units of A and three units of B. A is made of four units of ...

    Assume that Product Z is made of two units of A and three units of B. A is made of four units of C and four of D. D is made of two units of E      Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks.      Fifty one units of Product Z are required in Period 10. (Assume that...

  • Assume that Product Z is made of two units of A and four units of B....

    Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E. Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty units of Product Z are required in Period 10. (Assume that there...

  • Assume that Product Z is made of two units of A and four units of B....

    Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and three of D. D is made of three units of E      Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks.      Fifty seven units of Product Z are required in Period 10. (Assume that...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT