Question

Question No.2: Table below provides the processing times in hours of seven jobs to be processed on four machines in the order
0 0
Add a comment Improve this question Transcribed image text
Answer #1


ANSWER * Here To apply jhonsons rule of sequencing we need to convert the problem for the a machines. 1. e. from y machineshere, as per conditions ; condition - - 329 Hence, condition is not satistied. condition - 9 29 Here Honce condition is salis

М-1 3, т во 1, 1, ( a5 43 44 3, е 13 41 5, 14 14 , 15 14 16 аз м - а Hence, as per Thomsons rule following sequence can be ac

Machine Time Caluclation

Total Idl Time = 56 hours

B C D E F G H I | Machine -1 IN OUT Machine-2 IN OUT Machine-3 IN OUT 6 11 Machine-4 IN OUT 0 33 10 4 11 12 Idle Time 46 50 5

                   ....................................Please Give Me a Thumb Up..........................

                                      ................................Thanking You............................

Add a comment
Know the answer?
Add Answer to:
Question No.2: Table below provides the processing times in hours of seven jobs to be processed...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1. Suppose you have four jobs that must be processed, with the following table giving their...

    1. Suppose you have four jobs that must be processed, with the following table giving their charac- teristics(all times in hours): Each job can be processed on any of three identical machines; to be Job 1 23 4 Processing time 21.524 | 2 | 0 | 0.5 | 1 Release time Processing time 5346 finished, a job must be processed for its entire processing time, but this processing time can be interrupted and even moved to a different machine if...

  • Problem #1 Five jobs are to be processed through a single machine. The processing times and...

    Problem #1 Five jobs are to be processed through a single machine. The processing times and due dates are given here. Assume all released dates are zero. Job 1 2 3 4 5 Processing time 3 6 5 4 2 Due date 4 8 12 21 15 In each of the following cases determine the sequence in which she should perform and compute Mean Flow Time, Average Tardiness and the number of tardy jobs. A) Shortest Processing Time B) Early...

  • Suppose we have five jobs to be processed on a single machine. The processing times and...

    Suppose we have five jobs to be processed on a single machine. The processing times and the due dates of the jobs are shown below Job 2 3 4 Processing Time 2 6 5 4 Due Date 10 11 15 4 13 Find a schedule that minimizes the number of tardy jobs

  • 3. Consider the following seven-job problem. Each job must be processed by two ma chines A...

    3. Consider the following seven-job problem. Each job must be processed by two ma chines A and B, first on machine A and then machine B. The operation processing times at machine A and B are as follows: Job i 1 2 3 5 6 Processing time on machine A (a9 8 5 10 6 8 5 Processing time on machine B (b) 6 5 7912 11 4 a. Suppose jobs arrived in their natural order (i.e, job before job...

  • Five jobs are waiting to be processed. Their processing times and due dates are given below....

    Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the shortest processing time dispatching rule, in which order should the jobs be processed? Processing Time (days) Job due date (days) Job A B 4 C 11 D 8 5 8 O A. D, A, E, B, C О в. D. В. Е. А. С О С. С. А, Е, в.р O D. C, E, A, B, D O E. B, D, A,...

  • 1. Five jobs are waiting to be processed. Their processing times and due dates are given...

    1. Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the longest processing time dispatching rule, in which order should the jobs be processed? All dates are specified as days from today. Job Processing Time (days) 4 Job due date (days) 7 A B 7 4 11 с 3 D 8 5 E 5 8 A) D, B, E, A, C B) C, A, E, B, D C) B, D, E, A,C...

  • Question 2: The times required to complete each 2. The times required to complete each of...

    Question 2: The times required to complete each 2. The times required to complete each of eight jobs in a two-machine flow shop are shown table that follows. Each job must follow the same sequence, beginning with machine A and moving to machine B. Job TIME (hours) Machine A Machine B OOOO a. Determine a sequence that will minimize makespan time. b. Find machine B's idle time. c. For the sequence determined in part a, how much would machine B's...

  • Six jobs are to be processed through a​ two-step operation. The first operation involves​ sanding, and...

    Six jobs are to be processed through a​ two-step operation. The first operation involves​ sanding, and the second involves painting. Processing times are as​ follows: JOB OPERATION 1 (HOURS) OPERATION 2 (HOURS) A 4 8 B 10 5 C 3 11 D 14 14 E 6 1 F 7 12 a. Using​ Johnson's rule for​ 2-machine scheduling, the sequence​ is: Scheduled Order Job 1 ? 2 ? 3 ? 4 ? 5 ? 6 ? b. For the schedule developed...

  • Processing times and due dates for five jobs are shown in the table below. Assume the...

    Processing times and due dates for five jobs are shown in the table below. Assume the jobs are processed using the earliest-due-date rule Job Processing time (weeks) 3.00 0.40 1.10 4.00 1.50 Due date (weeks) 3 556 3 12. What would be the lateness of job B? 13. What would be the tardiness of job E? 14. What is the average flow time for this set of jobs? 15. What is the maximum tardiness for this set of jobs? (0.10...

  • Question 1: Sequence the jobs shown below by using a Gantt chart. Assume that the move...

    Question 1: Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority order 1, 2, 3, 4. Job Work Center/Machine Hours                                  Due Date (days) 1 A/3, B/2, C/2 3 2 C/2, A/4 2 3 B/6, A/1, C/3 4 4 C/4, A/1, B/2 3 Using finite capacity scheduling, draw a Gantt chart for the schedule (Marks 0.5) What is the makespan? (Marks 0.5) How much machine...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT