Question

Question 1: Sequence the jobs shown below by using a Gantt chart. Assume that the move...

Question 1:

Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority order 1, 2, 3, 4.

Job Work Center/Machine Hours                                  Due Date (days)

1

A/3, B/2, C/2

3

2

C/2, A/4

2

3

B/6, A/1, C/3

4

4

C/4, A/1, B/2

3

  1. Using finite capacity scheduling, draw a Gantt chart for the schedule (Marks 0.5)
  2. What is the makespan? (Marks 0.5)
  3. How much machine idle time is there? (Marks 0.5)
  4. How much idle time (waiting time) is there for each job? (Marks 0.5)
  5. When is each job delivered? (Marks 0.5)
  6. Which department is the bottleneck? (Marks 0.5)
  7. Calculate the machine utilization? (Marks 0.5)
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution : b : Machine idle times are : A - 9 hours, B - 8 hours, C - 7 hours

Solution : c : Job completion is well before due dates.

Solution : d : Idle times are as follows.

Solution : e : Better priority schedule : 3-1-2-4 with timespan - 14 hours.

Add a comment
Know the answer?
Add Answer to:
Question 1: Sequence the jobs shown below by using a Gantt chart. Assume that the move...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • a-) Draw the gantt chart and computecpu waiting time using preeptive-priority algorithm for the cpu I/O...

    a-) Draw the gantt chart and computecpu waiting time using preeptive-priority algorithm for the cpu I/O device is using FCFS. Compute cpu utilization as well. b-) Draw the gantt chart and compute cpu waiting time using round-robin algorithm for the cpu where quantum is 3 milli seconds. Compute cpu utilization as well. comp 214 2019/2020 Summer School Assignment 1 Priority Arrival Time 4 cpu 12 cpu 6. 3 3 P2 2 4 2 4 loane P3 4 ㅋ 8 6...

  • Solve the following Job Sequencing problem. Draw Gantt chart. Find total time elapsed to complete the...

    Solve the following Job Sequencing problem. Draw Gantt chart. Find total time elapsed to complete the jobs and idle time for machines. Job/Machine M1 M2 M3 1 5 9 8 2 3 6 7 3 4 7 6 4 2 8 9 5 6 7 5 6 4 6 9

  • Use the Gantt chart below to answer this question. Task 1 Job 1 (CT= 12 min...

    Use the Gantt chart below to answer this question. Task 1 Job 1 (CT= 12 min Task 2 (CT-20 min Task 3 Job 2 Job 3 Job 2 Job 3 Job 1 Job 3 16 min) 20 The bottleneck cycle time is「minutes. Enter an integer for your answer (no decimals). What is the capacity of this system ? jobs per hour. Integer answer The expected lead time (LT) for a typical job entering the system shown in the Gantt chart...

  • 6. Draw GANTT charts (plots of activity vs. time) for the Round Robin and Priority scheduling...

    6. Draw GANTT charts (plots of activity vs. time) for the Round Robin and Priority scheduling strategies for the following jobs (assume larger numbers mean higher priority and that the time quantum is 2): (10 marks ) Job Arrival Time Duration Priority tam What is the average waiting time under each scheme? Time → Average wait time for round robin is: PRIORITY Time → Average wait time for round robin is:

  • 2. Determine the processing sequence for the six jobs shown below using Johnson's Rule. (A) Calculate...

    2. Determine the processing sequence for the six jobs shown below using Johnson's Rule. (A) Calculate total throughput (makespan) time. (12 pts) (B) Can the makespan be reduced by splitting the latest job? If so, by how much? (8 pts) Working Working Center 1 Center 2 Job 6 8 c 10 900 Resolution 20p HD-Ready Gateway FPD1975W TFTLCD Monitor Theft Detemce 4 8 c 10 9 e 11 7 Gateway FPD TFT LC

  • (a) Allan's job shop takes order for making spare parts for textile manufacturing equipment. The operation...

    (a) Allan's job shop takes order for making spare parts for textile manufacturing equipment. The operation milling and involves first milling and then finishing. Table Q4(a) presents the data of processing times for each job. (i) Determine the sequencing rule using First Come First Serve (FCFS) and Johnson's Rule. (4 marks) (ii) Make a work schedule on a Gantt chart using FCFS rules indicating the makespan. (6 marks) (iii) Make a work schedule on a Gantt chart using Johnson's rules...

  • Can you please help me with the following questions without using excel Question 2: The times...

    Can you please help me with the following questions without using excel Question 2: The times required to complete each of eight jobs in a two-machine flow shop are shown in the table that follows. Each job must follow the same sequence, beginning with machine A and moving to machine B. Job Machine A Machine B 13 14 14 18 20 14 a. Determine a sequence that will mininize makespan time b. Find machine B's idle time. c. For the...

  • Question 2: The times required to complete each 2. The times required to complete each of...

    Question 2: The times required to complete each 2. The times required to complete each of eight jobs in a two-machine flow shop are shown table that follows. Each job must follow the same sequence, beginning with machine A and moving to machine B. Job TIME (hours) Machine A Machine B OOOO a. Determine a sequence that will minimize makespan time. b. Find machine B's idle time. c. For the sequence determined in part a, how much would machine B's...

  • 2. Consider the following processes with the arrival time, burst time, and priority. Draw Gantt chart...

    2. Consider the following processes with the arrival time, burst time, and priority. Draw Gantt chart for a priority-based preemptive CPU scheduling algorithm (the highest number refers the highest priority, in case of same priority, follow FCFS) (4 points) Priority PIDATBT PI 0 10 P3 10 6 3

  • need typed answer Create a Gantt chart for two jobs and identify on the chart the...

    need typed answer Create a Gantt chart for two jobs and identify on the chart the following two jobs that are reviewed on day 4: Job 111 - It started on day 2 and should take 4 days, but has fallen behind by one day: Job 112 - It started on day 3 and should take two days. It finished early on day 4. TT TT Paragraph Arial 3 (12pt) T %D9 EESEES T'T Mashups - © © BE HTHLESS...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT