Item A                 Period 1 2 3 4 5 6 7 8
Gross requirements 47 16 34 25 50 40 16 12
Scheduled receipts 0 0 0 0 0 0 0 0
Projected available balance 72 25 9 0 0 0 0 0 0
Net requirements 0 0 25 25 50 40 16 12
Planned order recepits 0 0 25 25 50 40 16 12
Planned order releases 25 25 50 40 16 12 0 0
Item B                 Period 1 2 3 4 5 6 7 8
Gross requirements 50 50 100 80 32 24 0 0
Scheduled receipts 0 0 0 0 0 0 0 0
Projected available balance 130 80 30 110 30 178 154 0 0
Net requirements 0 0 70 0 2 0 0 0
Planned order recepits 0 0 180 0 180 0 0 0
Planned order releases 0 180 0 180 0 0 0 0
Item C                 Period 1 2 3 4 5 6 7 8
Gross requirements 75 75 150 120 48 36 0 0
Scheduled receipts 0 0 0 0 0 0 0 0
Projected available balance 150 75 0 0 36 0 0 0
Net requirements 0 0 150 0 48 0 0 0
Planned order recepits 0 0 270 0 84 0 0 0
Planned order releases 270 0 84 0 0 0 0 0
Add a comment
Know the answer?
Add Answer to:
Fill in the following question marks (?) to complete thr MRP Chart. E l T able...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT