The planning technique used by the project manager here is Rolling Wave technique. It is a form of Progressive elaboration where the work to be accomplished in near future is planned in greater detail whereas the work to be accomplished in future is planned at higher level.

It allows work and activities to move in sync with near-term deliverables while continuing to plan for future term work packages. This technique is highly suitable for projects where outcome of phases are highly variable and depend on the successful completion of previous phase work packages. Invention projects are examples where Rolling wave technique can be employed.

Here also, in Zimbo project, all project requirements are not known and scope may change based on availability of more information. Since the outcome of phases is variable, the Rolling wave iteration planning technique is suited for this project.

Add a comment
Know the answer?
Add Answer to:
6. On the Zimbo project, not all requirements are known and the ones that are gathered...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT