Assume that Product Z is made up of four units of A and two units of C and two units of D. A is made of three units of D. The total demand for Z is 2000 units Additional information is the following:
Item | Z | A | C | D |
On hand | 750 | 500 | 460 | 2,000 |
Safety stock | 0 | 120 | 140 | 200 |
Allocated | 0 | 80 | 160 | 200 |
Scheduled Receipts | -- | 500 in Week 1 | 1,500 in Week 1 | -- |
Provide the additional number of all items, including Z, that are required to meet the total demand shown for Product Z. Ignore the timing of these requirements |
Requirement of Z = demand -Units on hand = 2000-750 =1250
Requirement of A = (4 x Number of Z needed) + safety stock - units on hand - units allocated - scheduled receipts
= (4x1250)+ 120 -500-80-500 = 4040
Requirement of C = ( 2x Number of Z needed) + Safety stock - units on hand - allocation -scheduled receipts
= (2x1250) +140-460-160-1500 = 520
Requirement of D = 2 x Number of Z needed + 3 x Number of A needed + safety stock - allocation -units on hand - scheduled receipts
= 2x1250 + 3x4040 +200 -200 -2000 =12620
Assume that Product Z is made up of four units of A and two units of...
Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E. Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty units of Product Z are required in Period 10. (Assume that there...
Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and three of D. D is made of three units of E Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty seven units of Product Z are required in Period 10. (Assume that...
Assume that Product Z is made of two units of A and three units of B. A is made of four units of C and four of D. D is made of two units of E Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty one units of Product Z are required in Period 10. (Assume that...
One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time...
One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time...
One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of...
One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of...
Problem 9 Assume that Product Z is made of two units of A and three units of B. A is made of hree units of C and four of D. D is made of two units of E Lead times for purchase or fabrication of each unit to final assembly are Z takes wo weeks: A, B. C and D take one week each; and E takes three weeks Fifty five units of Product Z are required in Period 10.(Assume...
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...
Suppose that there is incoming demand of 179 units of a certain product at the start of 3, and 91 units of the same product at the start of week 6. Scheduled receipts of 120 are planned for week 2, and 90 for week 5. The product has a lead time of 1 week and must be ordered in batches of s. When, and how large of an order should be placed to meet the requirements in weeks 3 and...