Activity | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
Activity time (weeks) | 2 | 5 | 4 | 2 | 7 | 5 | 8 | 4 | 3 | 1 |
Immediate predecessor | - | 1 | 1 | 2 | 2, 3 | 3 | 4 | 5 | 5, 6 | 7, 8, 9 |
Please build the GANTT chart for the given question above (note: you may use excel if that is easier for you)
Please draw the Gantt chart for the project. Use different color for critical path activities and non-critical path activities. Use arrows to indicate the slack time on the Gantt chart. (1 point) Note: if you use Excel or other graphical tools to create the Gantt chart, you may submit the files separately. YOUR SCORE: TOTAL POINTS: 5 Question (a), (b) and (e) are related to Lecture 17. Questions (c) and (d) are related to Lecture 18 The activity information and...
Hello, could you help me solve this question, please? Thank you very much! Question: (a) A project has EIGHT (8) activities listed in the following table: Activity Immediate Predecessor (s) Time (Weeks) Activity Immediate Predecessor (s) Time (Weeks) A - 2 E C 3 B A 5 F C 7 C A 3 G D, E 2 D B 4 H F 3 (i) Use the GRAPH PAPER provided to construct a Gantt chart for the above project. [Note: You...
Please help with this civil engineering problem! I promise I'll rate your answer! Question 6 Gantt Chart (20 points) Develop the Gantt chart for the following network diagram. Indicate in the Gantt chart the total float value for each activity that is not part of the critical path by marking the corresponding cells of an activity with dash marks “ “ ESD Duration EFD Activity Name LSD| Float LFD 213 3 2 5 5 2 7 13 10 15 15...
. Construct a Gantt chart and project network for the following set of activities, compute the length of each path in the network, and indicate the critical path: Activity Activity Predecessor Time (months) 1 ___ 4 2 ___ 7 3 1 8 4 1 3 5 2 9 6 3 5 7 3 2 8 4,5,6 6 9 2 5
1. Using Microsoft Excel prepare a Gantt Chart for the following project. Predecessor(s) Duration (Days) Activity 1. Forming the problem statement 2. Identifying functional requirements 3. Identifying constraints and limitations 4. Defining a schedule 5. Defining the design parameters 6. Identifying alternatives 7. Evaluating and analyzing alternatives 8. Select a solution 9. Gather supplies 10. Construct prototype 11. Test performance 12. Redesign 13. Demonstrate solution to class 2,3 2 8 10 11 12
Create a Gantt Chart for the following project, and show the Gantt Chart below. Set a start date of January 6, 2020. Assume that work can be done 5 days per week. Identify the Critical Path. When will the project be completed? Create a Gantt Chart for the following project, and show the Gantt Chart below. Set a start date of January 6, 2020. Assume that work can be done 5 days per week. Identify the Critical Path. When will...
Solve the following Job Sequencing problem. Draw Gantt chart. Find total time elapsed to complete the jobs and idle time for machines. Job/Machine M1 M2 M3 1 5 9 8 2 3 6 7 3 4 7 6 4 2 8 9 5 6 7 5 6 4 6 9
3. (20 points) A landscaping upgrade project consists of following activities. Times are given in weeks. Activity | Immediate Predecessor Activity Time A А ထင်ထ F B, DC D D 3 3 a. Draw the network diagram and find the ES, EF, LS, LF, and slack for each activity b. Construct an early-start-date Gantt chart for the project. C. As a project manager, where would you focus your attention, given your analysis?
ASSIGNMENT- Scheduling a. Draw the EARLY start Gantt chart and state the critical activities b. Draw the LATE start Gantt chart c. Draw the AON chart - Forward pass d. Draw the AON chart - Backward pass e. Identify the critical path from the table (follow ppt/notes) MUST BE DONE NEATLY! ACTIVITY WEEKS PRECEDENCE A B с D E F 3 4 5 7 2 4 3 A B B E C,D GF H
a-) Draw the gantt chart and computecpu waiting time using preeptive-priority algorithm for the cpu I/O device is using FCFS. Compute cpu utilization as well. b-) Draw the gantt chart and compute cpu waiting time using round-robin algorithm for the cpu where quantum is 3 milli seconds. Compute cpu utilization as well. comp 214 2019/2020 Summer School Assignment 1 Priority Arrival Time 4 cpu 12 cpu 6. 3 3 P2 2 4 2 4 loane P3 4 ㅋ 8 6...